Professional Documents
Culture Documents
GROUP 2 CPM Course Work
GROUP 2 CPM Course Work
YEAR: YEAR IV
GROUP 2
REGISTRATON STUDENT
NAME COURSE
NUMBER NUMBER
SSEKAJJA ABDULSWAMADU BSQS 19/U/0111 1900700111
AKANKUNDA MAXIM BSQS 19/ U/0580 1900700580
TUMWESIGYE ALLAN BSQS 19/U/0554 1900700554
KEMIGISA MARTHA ALUM V BSQS 19/U/0120 1900700120
TUHAISE BRAIN BSQS 19/U/8271/PS 1900708271
NABAWENDA JOAN BSQS 19/U/0561 1900700561
AHEEBWA GLORIA BSQS 19/U/0124 1900700124
ANGWEN ANGELLA BSQS 19/U/0573 1900700573
TABLE OF CONTENTS
1 INTRODUCTION..............................................................................................................1
3 WORK SCHEDULING......................................................................................................3
4 NETWORK ANALYSIS....................................................................................................7
4.1 Introduction.................................................................................................................7
6 STATISTICAL APPROACHES......................................................................................19
6.2 S curve.......................................................................................................................19
7 References.........................................................................................................................22
CONSTRUCTION MANAGEMENT TOOLS AND TECHNIQUES
1 INTRODUCTION
Construction management involves control of the construction process, and optimum
aggregation of construction resources including money, manpower, materials, machinery and
methods of work (M’s).
It addresses how the resources available to the Project Manager (PM) can be best applied.
The job of the Project Manager is to efficiently and economically apply the required
resources to realize a constructed facility of accepted quality within the time frame and
budgeted cost specified (Halpin & Senior, 2010).
A Project Manager can apply the different resources within the limited funding and time
available with the help of the construction management tools and techniques. These include;
Work Breakdown Structure(WBS), Project Evaluation and Review Technique (PERT), Non-
linear Distribution Method, Activity Cost Estimation, Precedence Network Analysis (PNA),
Resource Planning Data, Critical Path Method (CPM) and Graphical Evaluation and Review
Technique (GERT) methods.
This report mainly focuses on; WBS, CPM, PERT, PNA and work scheduling. It also entails
details of the cash flow projections and statistical approaches to construction management.
2 WORK BREAKDOWN STRUCTURE (WBS)
According to Project Management Institute, Work Breakdown Structure is a hierarchical
representation of work contents, whereby the project is progressively subdivided into smaller
units.
It is a hierarchical structure that defines and organizes the total project scope based on
deliverables, with each descending level in the hierarchy representing an increasingly detailed
definition of the project work. Deliverables are tangible, measurable parts of the project that
can be broken into levels of sub-projects, tasks, work packages and activities (PMI, 2001).
2.1 Levels of the Work Breakdown Structure
a) Project level: This represents the entire project. It is the highest level in the WBS
configuration.
b) Sub-project level: This is derived by decomposing the scope of project work into
independent large-volume mini-projects which can be progressed in a systematic
manner.
c) Task level: The sub-project can be split into various tasks. A task is an identifiable
and deliverable major work.
1
d) Work-packages level: A project task can be further sub-divided into one or more work
packages. This level represents the responsibility for the performance of the work
assigned to an individual or organization.
e) Activity level: A work package can be further broken down into various identifiable
jobs, operations and processes, which consume time and possible resources which are
necessary for its completion (Chitkara, 2014).
2.2 Representation of the Work Breakdown Structure
The WBS can be represented in three forms such as;
a) Hierarchical inverted tree structure
b) Numbered levels table
c) Task matrix format
2.3 Importance of a Work Breakdown Structure
According to Devi & Reddy (2012), a WBS outlines where the project will start, what phases,
levels and tasks would be followed. Skipping the WBS could cause delays, confused tasking
by team members and project overruns. The WBS also helps to define the specifics of the
project outlined in the project scope. Below are some of the importance of the WBS to the
project and the project teams;
2.3.1 To the Project Teams
i. Project Teams need a WBS because it has a number of benefits in addition to defining
and organizing the project work. By allocating time and cost estimates to specific
sections of the work breakdown structure, a project schedule and budget can be
quickly developed.
ii. Project WBS can also be used to identify potential risks in a given project. By
integrating the work breakdown structure with an organization breakdown structure,
the project manager can identify communication points and formulate a
communication plan across the project organization.
iii. When a project is falling behind, referring to the work breakdown structure will
quickly identify the major deliverables impacted by a failing work package or late
sub-deliverable.
2.3.2 To the project
i. The work breakdown structure helps to define and organize the scope of the total
project more accurately and specifically. The most common way this is done is by
using a hierarchical tree structure.
ii. A work breakdown structure in projects is to help with assigning responsibilities,
resource allocation, monitoring the project, and controlling the project. The WBS
makes the deliverables more precise so that the project team knows exactly what has
to be accomplished within each deliverable.
iii. It also allows for better estimating of cost, risk and time since execution is done from
smaller tasks up to the level of the entire project.
iv. It allows double checking of all the deliverables’ specifics with the stakeholders and
making sure that there is nothing missing or overlapping.
2.4 Common Pitfalls and Misconceptions
i. A WBS is not an exhaustive list of work. It is instead a comprehensive classification
of project scope.
ii. A WBS is not a project plan or a project schedule and it is not a chronological listing.
It is considered poor practice to construct a project schedule before designing a proper
WBS.
iii. A WBS is not an organizational hierarchy. Some project managers make the mistake
of creating a WBS that shadows the organizational chart.
iv. Short-memory capacity should not dictate the size and span of a WBS tree structure.
A WBS level is suggested to be limited to 5-9 elements because that is a theoretical
limit to short-term memory.
v. WBS updates, require formal change control. This is another reason why a WBS
should be outcome oriented and not be prescriptive of methods. Methods can and do
change frequently, but changes in planned outcomes require a higher degree of
formality.
3 WORK SCHEDULING
Scheduling is the determination of the timing and sequence of operations in the project and
their assembly to give the overall completion time (Mubarak, 2010).
According to Chitkara (2014), a schedule can be defined as a work programme that is set
date-wise in a logical sequence. A work schedule is an action plan with calendar date targets
of construction operations that serves as a principal guideline for project execution.
3.1 Purposes of Work Scheduling
Chitkara (2014) stated that work scheduling serves a number of purposes as discussed below;
3.1.1 Simplifies the project plan
The bar-chart type (Gantt chart) work schedule provides a simplified version of the work
plan, which can easily be understood by all concerned authorities or departments dealing with
planning, coordination, execution, and control of the project.
3.1.2 Validates the time objectives
A work schedule shows the planned sequence of activities in date-wise manner. It also
verifies the deadlines imposed for completion of each activity as well as the entire project and
achievement of the milestones.
3.1.3 Optimizes resources
A work schedule is based on the most economical employment of the resources of
manpower, materials, and machinery. It smoothens abrupt changes, which may occur from
time to time. Resource optimisation is achieved by a systematic utilisation of the floats of
non-critical activities.
3.1.4 Forecasts the input resources and predicts the output
A work schedule enables the forecasting of resources and also indicates the pattern of
resource consumption. The time schedule of work forms the basis for predicting the resource
requirement as well as the financial state of the project in terms of investment, expenditure,
output, income, and cash flow.
3.1.5 Evaluates the implications of scheduling constraints
A work schedule brings out the implications of constraints, and enables preparation of a work
plan within the framework of these constraints.
3.2 Work Scheduling Techniques and methods
According to Chitkara (2014), work schedules can be broadly categorised into Bar Chart
Schedules, Network-Based Complex Projects Schedules and the Line of Balance (LOB)
schedules for repetitive project depending on the nature of project, time, and resource
constraints.
3.2.1 Bar Chart (Gantt chart) Method
A bar chart is ‘‘a graphic representation of project activities, shown in a time-scaled bar line
with no links shown between activities’’ (Mubarak, 2010).
In this method, work is first broken down into activities with the aid of Work Breakdown
Structure (WBS) and then these activities are listed in the order of precedence relationships
( sequence of execution) on the left hand side column of the chart with a time scale showing
the project calendar plotted horizontally on the top and/or bottom of the chart.
Generally, the project calendar covers the project’s construction span from the start date to
the final completion date and specifies the dates when the activities are scheduled. The bar
chart calendar clearly highlights the months, weeks, working days, non- working days and
holidays.
The bar against each activity represents its work schedule with a start and finish of each
activity. The length of the bar on the calendar scale represents the duration of the activity and
horizontally, each row represents the activity description and activity data.
The advantage of bar charts over networks is that they are time-scaled; that is, the length of a
bar representing certain activity is proportional to the duration of that activity making them
easy to comprehend.
The main disadvantage of bar charts is lack of logical representation (relationships) which
ideally could be a logical relationship, a resource constraint, or a subjective decision by the
project manager.
The limitation of bar charts is that they may not be practical for projects with large numbers
of activities and hence at times limited by size and complexity of the project. This is due to
the following reasons;
i. It does not reflect the relationship between various activities, which are a common
feature of all complex projects, unless a time scale network is plotted.
ii. It cannot identify and highlight the emerging critical tasks that need special attention
for preventing schedule slippages, time overruns, contractual disputes, and other
bottlenecks.
iii. In complex projects, time durations often are estimated. Any change in schedule or
time duration would require redrawing of the multi-task bar chart schedule.
3.2.2 Network Based Scheduling Method
In complex projects, activities are sequenced using network techniques. A time analysed
network depicts the start and completion times of critical and non-critical activities.
Network based schedules can be broadly categorised into two categories namely;
3.2.2.1 Time Limited Schedule
This schedule is prepared based on project time constraints, in such a way that entire project
duration is not exceeded.
3.2.2.2 Resources Limited Schedule
This schedule is prepared based on resource constraints by making use of the available floats
of non-critical activities to reduce conflicts in resource requirements or conform to a given
predetermined pattern of resources.
According to Richard H. Clough & Sears (2008), the following guidance steps are considered
in devising an efficient and workable schedule;
a) Estimate the time required to carry out each network activity.
b) Compute the time required for the overall project completion using the activity
duration estimates.
c) Establish time intervals within which each activity must start and finish to satisfy the
completion date requirement.
d) Identify the critical and non-critical activities.
e) Adjust the start and finish times of non-critical activities to minimise resource
conflicts and smooth out demands of manpower and equipment using the available
total float. This is termed as resource optimization.
f) Make a working project schedule that shows anticipated calendar dates for the start
and finish of each activity.
g) Record assumptions made and the plan’s vital boundary conditions which will
eventually become an integral aspect of the completed baseline project schedule.
3.2.2.3 Resource Optimization
Resource optimisation is a schedule network analysis technique applied to a schedule that has
already been analysed using CPM/PERT. It is needed when;
a) Resources are scarce or have been over-allocated resulting in resource conflicts.
b) There is a need to keep resource usage at a constant level.
Resource optimization techniques include resource smoothing and resource leveling.
Resource smoothing Resource leveling
Time limited scheduling technique Resource limited scheduling technique
Removes as much resource conflicts as Removes all resource conflicts
possible, but may not remove all resource
conflicts
Activities are shifted only to the extent of the Activities may be shifted beyond available
float available float while scheduling activities
The project duration must not be exceeded The project duration gets exceeded
No change in the critical path May change the critical path
Where;
Latest Finish Date (LFD) = Latest Finish Time (LFT),
Total Float (TF) = Latest Finish Time (LFT) – Earliest Finish Time (EFT) OR
= Latest Start Time (LST) – Earliest Start Time (EST),
Dur = Duration,
No. = Activity number or identification label,
Resource = Gang size or man-days or cost earned value etc. can be written below description,
if considered necessary.
4.4.2 Precedence network logic
A logic network shows the sequence of activities in a project cross time. It indicates which
activity logically precedes or follows another.
The job dependency logic shows the sequence in which the activities progress, for example
blinding activity starts after the completion of excavation. It generally follows the rule that
except the start activity, each activity can start only after, its preceding activity(ies) is
completed.
The construction job time constraints logic arises from the restrain on start and completion
of dependent activities that is imposed due to the construction process at site. It is of two
types, i.e., ‘Lag’ or ‘Lead’, which are situational requirements. Most Project Management
software do display lag or lead on the network display. For example, the start of blinding
activity may get delayed by two days after completion of excavation for grading and soil
testing of the excavated surface.
4.4.3 Types of precedence relationship
In precedence diagrams, a number of different relationships exist between activities.
i. Finish-to-start: Delay from the finish of preceding activity to the start of the
succeeding one.
ii. Finish-to-finish: Delay from the finish of preceding activity to the finish of the
succeeding one.
iii. Start-to-start: Delay from the start of preceding activity to the start of the succeeding
one.
iv. Start-to-finish: Delay from the start of preceding activity to the finish of the
succeeding one.
7 References
Barrie, D. S., & Paulson, B. C. (1992). PROFESSIONAL CONSTRUCTION MANAGEMENT
Including C.M., Design-Construct and General Contracting (3rd ed.). Singapore: McGRAW-
HILL INTERNATIONAL EDITIONS.
Chen, M. T. (2007). ABC of Cash Flow Projections. AACE International Transaction, 85-89.
Chitkara. (2014). Construction Project Management Planning, Scheduling and Controlling, (Third
Edition ed.). New Delhi: McGraw Hill Education (India) Private Limited.
Chitkara, K. (2014). Construction Project Management (3 ed.). Delhi: Mc Graw Hill Education
( India) Private Limited.
Devi, R. T., & Reddy, S. V. (2012, Mar-Apr). Work Breakdown Structure of the Project.
International Journal of Engineering Research and Applications, Vol. 2(Issue 2), 683-686.
Eugene, L. (1966). PERT Military Contribution to Management Science. University of Montana. East
Parkway: UMI Dissertation Publishing. From https://scholarworks.umt.edu/etd/3207
Frank Harris, R. M. (2021). Modern Construction Management. Oxford: John Wiley & Sons Limited.
Halpin, D. W., & Senior, B. A. (2010). Construction Management (4th edition ed.). USA: John Wiley
& Sons. Inc.
Lt. Col. (Retd.) K K CHITKARA, A. (2014). Constrction Project Management Planning, Scheduling
and Controlling (3rd ed.). New Delhi, India: McGraw Hill Education (India) Private Limited.
Mubarak, S. (2010). Construction Project Scheduling and Control (2 ed.). Canada: John Wiley &
Sons.
PMI. (2001). Project Management Institute Practice Standard for Work Breakdown Structure.
Newton Square, PA.
Richard H. Clough, G. A., & Sears, S. K. (2008). Construction Project Management. Apractical
Guide to Field Construction Management (5 ed.). Canada: John Wiley & Sons.
Yahaya M. Ibrahim, A. K., & K., M. (2008). Framework for a generic work breakdown structure for
building projects. Construction Innovation, 388-405.