PROJECT: CONSTRUCTION OF RESIDENTIAL BUILDING FOR Mr.EDISOR AT MADURAI.

MASONRY, CENTERING & REBAR WORKS


MEASUREMENT SHEET
Measurements Qty Rate (INR) Amount (INR)
Sl.No Item Particulars Location Nos Unit
L B D QS Contractor QS Contractor QS Contractor
A BUILDING AREA
1 G.FLOOR ENTIRE AREA 1 1,300.00 1,300.00 1,300.00 Sft 360.00 360.00 4,68,000 4,68,000
F.FLOOR ROOM&KITCHEN 1 26.25 12.50 328.13
TOILET 1 5.75 9.50 54.63
382.75 400.00 Sft 360.00 400.00 1,37,790 1,60,000

SUB TOTAL -A 1,682.75 1,700.00 6,05,790 6,28,000


B ADDITIONAL WORKS
OHT TERRACE 1 1.00 1.00 LS 8,000.00 8,600.00 8,000.00 8,600

SEPTIC TANK G. LEVEL 1 48.00 48.00 48.00 Sft 350.00 350.00 16,800.00 16,800

UG SUMP PARKING 1 51.00 51.00 51.00 Sft 400.00 400.00 20,400.00 20,400

COMPOUND WALL SOUTH 1 40.00 8.00 320.00 320.00 Sft 110.00 110.00 35,200.00 35,200
COMPOUND WALL NORTH TO BE DISCUSSED
5A HANDRAIL BELT BEAM
FORMWORK&REBAR 1 63.00 63.00 63.00 Rft 40.00 40.00 2,520.00 2,520
CONCRETING 1 63.00 63.00 63.00 Rft 20.00 20.00 1,260.00 1,260
EXTRA PLASTER 2 63.00 126.00 126.00 Rft 15.00 20.00 1,890.00 2,520
BORDER 1 63.00 63.00 63.00 Rft 30.00 40.00 1,890.00 2,520
ADDITIONAL WALL CONSTRUCTION
BELOW PARAPET 1 11.00 3.00 33.00 33.00 Sft 40.00 40.00 1,320.00 1,320

ELEVATION OUTER BORDER NEAR SEPTIC TANK


NEAD CLARITY - 120.00 Rft - 40.00 - 4,800

MUD & SLURRY REMOVAL FROM SEPTIC TANK


M/C 2.00 800.00 1,600
F/C 3.00 550.00 1,650
PLASTERING WORK NEAD CLARITY 1 6.75 11.00 74.25 75.00 Sft 40.00 20.00 - 1,500

SUB TOTAL -B 89,280 1,00,690


C OTHER EXTRA WORKS

Page 1 of 3
Measurements Qty Rate (INR) Amount (INR)
Sl.No Item Particulars Location Nos Unit
L B D QS Contractor QS Contractor QS Contractor
1 1" WIDE CROSS GROOVES
F.FLOOR TOILET WALL 1 43.00 43.00 43.00 Rft 20.00 23.50 860.00 1,011

2 KITCHEN WALL BORDER INCLUDED IN BUILT UP AREA RATE - 32.00 Rft 20.00 23.50 - 752

3 BELT BEAM ABOVE TOILET WALL NEAD CLARITY - 8.00 Rft - 120.00 960

4 BRICK PILLAR / BRICK WORK 1 6.00 1.00 NEAD CLARITY 6.00 Sft - 120.00 720
BRICK PILLAR / PLASTER 1 6.00 3.00 NEAD CLARITY 18.00 Sft - 120.00 2,160

5 "S" BORDER IN PARAPET 1 77.50 77.50 77.50 Rft 100.00 140.00 7,750.00 10,850
NEED TO DISCUSS WITH ITEM NO:5A

GRILL FIXING WORKS MASON 1.00 NO 1,050.00 1,050


HELPER TO BE DISCUSSED 1.00 NO 800.00 800
BLADE/MACHINE 1.00 NO 250.00 250

6 4.5" THICK PILLAR IN ELEVATION 8 3.00 24.00 24.00 Rft 100.00 120.00 2,400.00 2,880

7 EXTRA PLASTER ABOVE SIT OUT SUNSHADE 1 9.00 3.00 27.00 35.00 Sft 20.00 20.00 540.00 700

8 2" BORDER
ABOVE SIT OUT SUNSHADE 4 8.50 34.00 34.00 Rft 20.00 20.00 680.00 680
BELOW SIT OUT SUNSHADE 2 8.00 16.00 - Rft 20.00 20.00 320.00 -

9 FLOWER DESIGN ABOVE SIT OUT SUNSHADE 3 3.00 3.00 NOS 300.00 400.00 900.00 1,200

10 PORTICO SUNSHADE BORDER 1 20 20.00 20.00 Sft 30.00 40.00 600.00 800

11 PORTICO PERGOLA DESIGN 6 6.00 6.00 NOS 500.00 400.00 3,000.00 2,400

12 BUTTON MARK FIXING INCLUDED IN MAIN SCOPE/TO BE DISCUSSED 6.00 NOS 500.00 450.00 - 2,700

Page 2 of 3
Measurements Qty Rate (INR) Amount (INR)
Sl.No Item Particulars Location Nos Unit
L B D QS Contractor QS Contractor QS Contractor
13 BEDROOM WINDOW ALROUND WORKS
SIDES 2 4.00 8.00 8.00 Rft 50.00 80.00 400.00 640
BOTTOM 1 4.50 4.50 4.50 Rft 120.00 160.00 540.00 720
CORNER DESIGN 2 2.00 2.00 NOS 100.00 - 200.00 -

14 BORDER BELOW SIT OUT FRONT GRILL 1 10.00 10.00 10.50 Rft 30.00 50.00 300.00 525

15 6" WIDE GROOVES


PILLAR PORTICO 3 5.50 16.50
STAIRCASE BOTTOM 3 7.25 21.75
38.25 51.00 Rft 30.00 30.00 1,147.50 1,530

16 1" WIDE GROOVES


STAIRCASE BOTTOM 11 4.00 44.00
17 1" WIDE GROOVES IN PARKING 5 7.75 38.75
2 9.75 19.50
102.25 133.00 Rft 20.00 23.50 2,045.00 3,126

18 SIT OUT 3' SUNSHADE BORDER 1 20.00 20.00 20.00 Rft 30.00 40.00 600.00 800

SUB TOTAL -C 22,283 37,253


D DEDUCTIONS : TERRACE TILES LAYING
TERRACE FLOORING
PORTION-01 1 17.00 8.83 150.11
PORTION-02 1 21.63 13.75 297.34
-1 11.83 1.00 -11.83
1 2.50 1.00 2.50
PORTION-03 1 15.83 2.00 31.67
PORTION-04 1 27.63 8.38 231.36
701.15 Sft 25 - 17,528.65 17,529
TERRACE SKIRTING 1 122.00 122.00 122.00 Rft 16 - 1,952.00 1,952

SUB TOTAL -D 1524.29 122.00 19,481 19,481

NET TOTAL (A+B+C-D) 6,97,872 7,46,462

Page 3 of 3