DAILY ACTIVITY REPORT

JOB NO : 22006 DATE : ###


CUSTOMER : PLTU KUPANG BARU DAY : ( 5th ) Sunday
EQUIPMENT : N/A RATE POWER : 18MW
OEM : N/A TAG No. : Unit #1

DESCRIPTION TARGET ACTUAL REMARKS


Induced Draft Fan A & B Pekerjaan di area TURBIN
1. Disassembly Fan 70% 45% Terkendala Crane masih
Motor Induced Draft Fan A & B dalam perbaikan dan
pengetesan beban.
1. Disassembling Motor 100% 50%
Boiler Feed Pump #2
1. Dismantling Peralatan Instrument 100% 95%
2. Disassembly Pompa 50% 0%
Lube Oil System BFWP #2
1. Dismantling Peralatan Instrument, Kabel Control dan Power 100% 100%
Motor Boiler Feed Pump #1
1. Dismantling Peralatan Instrument, Kabel Control dan Power 100% 95%
Turbine
Cylinder
1. Melepas Upper Casing 100% 95%

PLANNING FOR Monday, 26 September 2022 TARGET


Induced Draft Fan A & B
1. Disassembly Fan 100%
Motor Induced Draft Fan A & B
1. Disassembling Motor 35%
Boiler Feed Pump #2
1. Dismantling Peralatan Instrument 100%
2. Disassembly Pompa 50%
Lube Oil System BFWP #2
1. Pembersihan Tanki Minyak 100%
2. Pembersihan Cooler Pelumas 100%
Motor Boiler Feed Pump #1
1. Dismantling Peralatan Instrument, Kabel Control dan Power 100%
Turbine
Cylinder
1. Melepas Upper Casing 100%
2. Bersihkan dan periksa ruang uap 50%
PREPARED BY APPROVED BY CUSTOMER BY

PT. SURYA SAKTI SUKSES PT. SURYA SAKTI SUKSES PT. SMS ENERGY