Atom Solar 30 site configuration

18 Jan 2023
Solar installation design

SCPU 1 have to be 6 pic of solar connection


SCPU 2 have to be 5 pic of solar connection
© ZTE Corporation. All rights reserved
2
IP setting in laptop

Connect LAN cable CSU and Laptop

Set the IP address as per follow


IP address – 192.168.1.6
Subnet mask – 255.255.255.0
Note - CSU default IP is 192.168.1.2 Gateway – 192.168.1.1
© ZTE Corporation. All rights reserved
3
Brower passing
Open with Brower to login CSU (recommended to use Chrome Brower)

Type 192.168.1.2 at the address bar of Brower

If can not process, Click the Advanced and click Process to 192.168.1.2 (unsafe).
© ZTE Corporation. All rights reserved
4
Login ZTE CSU
Put suggested Username and Password to login the CSU

© ZTE Corporation. All rights reserved


5
Solar Information checking
Check the information, the information can not check and need to configure the CSU.
select Real Data > Solar. The Real Data tab for the solar data is displayed

1
3
2

© ZTE Corporation. All rights reserved


6
Export Parameter file
Select System Maintain > Devices Maintain, and then click the SPCU Parameter Maintain tab,

3
1

Download the parameter file

© ZTE Corporation. All rights reserved


7
Parameter file

Extract the file

© ZTE Corporation. All rights reserved


8
Edit Parameter file with NotePad++ software

Parameter file need to edit by using Notepad++ tool

© ZTE Corporation. All rights reserved


9
Modify Network Parameter for SCPU_1 ( 6 pic solar connection )

Set each SPU serial


number which
connected to SCPU_1

© ZTE Corporation. All rights reserved


10
Modify Network Parameter for SCPU_2 ( 5 pic solar connection )

After configuration
finished, Save the file

Set each SPU serial


number which
connected to SCPU_2

© ZTE Corporation. All rights reserved


11
Import Parameter file
Select System Maintain > Devices Maintain, and then click the SPCU Parameter Maintain tab,

3 4

Click Upload
Parameter File

Choose the file


which edited file

© ZTE Corporation. All rights reserved


12
Checking SPCU_1 information

1
2
3

Check whether the actual number of SPUs is the same as the displayed number. If not, it indicates that there is an
Note address conflict or the communication is interrupted.
In this case, you need to repeat the network configuration operations.
© ZTE Corporation. All rights reserved
13
Checking SPCU_2 information

1
2
3

Check whether the actual number of SPUs is the same as the displayed number. If not, it indicates that there is an
Note address conflict or the communication is interrupted.
In this case, you need to repeat the network configuration operations.
© ZTE Corporation. All rights reserved
14
Related Tasks checking
On the Web portal, select Historical Record. Click the Operate Record tab. The Operate Record tab is displayed.
Set Time Range. Verify that the network parameters are valid.

2
3

© ZTE Corporation. All rights reserved


15
Solar Controller Commissioning Guide

• When replacing an SPCU or SPU, you need to configure the network again. Otherwise, the SPCU or SPU fails to
communicate with others.
• When replacing the slot of an SPCU, you need to configure the network again. Otherwise, the SPCU fails to communicate
with CSU.

For the detail configuration can check the following attached file.

ZXEPS EBD48200 S200 (V1.0R01) Solar Controller Commissioning Guide

© ZTE Corporation. All rights reserved


16
Thank you