Anx~A~

Bahira Hills, Islamabad

Bahira Grand Mosque Bahria hills ,Islamabad

Mosque Hall Roof slab Concrete pouring Schedule

Sr.No Activty Start Date Finish Date Duration

1 Mosque Main Building

1 Roof Beam and slab steel fixing 30-Apr-18 6-May-18 6

1.1 Remaining formwork 6-May-18 7-May-18 1

1.2 Roof Beam and slab Concrete pouring 8-May-18 9-May-18 1

C.M Hassan and Company


Anx~A~
Bahira Grand Mosque Bahria hills ,Islamabad
Work schedule during Ramzan

Sr.No Activty Start Date Finish Date Duration R.E Inspection

1 Mosque Main Building

1.1 Dome 1st step steel fixing 20-May-18 25-May-18 5 25/5/2018

1.2 Dome 1st step formwork fixing 26-May-18 31-May-18 5 31/5/2018

1.3 Dome 1st step concrete pouring 1-Jun-18 2-Jun-18 1 1/6/2018

1.4 Dome 2nd step steel fixing 3-Jun-18 8-Jun-18 5

1.5 Dome 2nd step formwork fixing 9-Jun-18 13-Jun-18 4

1.6 Top slab formwork removing 1-Jun-18 10-Jun-18 9

Minaret
2

2.2 Steel fixing upto +40.00 24-May-18 27-May-18 3 27/5/2018

2.3 formwork fixing upto +40.00 28-May-18 31-May-18 3

2.4 Concrete pouring upto +40.00 1-Jun-18 2-Jun-18 1 1/6/2018

2.5 Steel fixing upto +50.00 5-Jun-18 8-Jun-18 3


2.6 formwork fixing upto +50.00 9-Jun-18 13-Jun-18 4
Retaining wall-15
3

3.1 Wall steel fixing 19-May-18 21-May-18 2

3.2 Wall formwork fixing 22-May-18 31-May-18 9

3.3 Concrete pouring 1-Jun-18 2-Jun-18 1 1/6/2018


Retaining wall-10
4

4.1 Wall steel fixing 25-May-18 26-May-18 1

4.2 Wall formwork fixing 27-May-18 31-May-18 4

4.3 Concrete pouring 1-Jun-18 2-Jun-18 1 1/6/2018


Retaining wall-3,9
5

5.1 Backfilling (upto 20 layer) 15-May-18 13-Jun-18 29


Follow Equipment / Labour will be arrange for month of Ramzan
1 Labour
a Steel Fixing
3 x Steel fixers
3 x Helpers
b Form Work
3 x Carpenter
3 x Scafolder
3 x Helpers
c Labour for Concrete
2 x Masons
2 x Carpenter+Folder
4 x unskilled labourers
2 Machinery
1 x Concrete pump
3 x Concrete T.M
3 x Vibrators
3 Temperature
32 Centigrade contractor will be maintain at plant .
Contractor arrange ice insted.
R.E Bahria Hills
Farooq Ahmed
Bahira Grand Mosque Bahria hills ,Islamabad
Super Structure Construction

Sr.No Activty Start Date Finish Date Days


1 Mosque Main Building

a Main Hall 15-Jun-22 30-Jun-22 15


Floor P.C.C 15-Jun-22 30-Jun-22 15 P.c.c work start after B.Work &
M.E.P
a.1 Leveling Dressing 15-Jun-22 22-Jun-22 7

a.2 P.C.C 23-Jun-22 30-Jun-22 7


b Perapit wall 23-May-22 20-Jun-22 28
Detail-3 (Height 8' L=360)

b.1 Steel fixing 23-May-22 3-Jun-22 11

b.2 Formwork fixing 26-May-22 15-Jun-22 20

b.3 Concrete pouring 30-May-22 20-Jun-22 21


Brick Masnory step 21-Aug-22 5-Sep-22 15

lean 21-Aug-22 22-Aug-22 1

Brick Masnory 23-Aug-22 5-Sep-22 13


3 Ablution area 16-Jun 9-Sep 85
a Excavation 16-Jun-22 20-Jun-22 4

b foundation 21-Jun-22 5-Jul-22 14

b.1 Lean Concrete 21-Jun-22 23-Jun-22 2

b.2 Footing steel fixing 24-Jun-22 30-Jun-22 6

b.3 Footing formwork fixing 1-Jul-22 3-Jul-22 2

b.4 Footing concrete pouring 4-Jul-22 5-Jul-22 1

c Column under plinth beam 6-Jul-22 15-Jul-22 9

sc.1 Steel fixing 6-Jul-22 8-Jul-22 2


c.2 Formwork fixing 9-Jul-22 12-Jul-22 3

c.3 Concrete pouring 13-Jul-22 15-Jul-22 2

d Plinth beams 16-Jul-22 28-Jul-22 12

d.1 Base formwork 16-Jul-22 18-Jul-22 2

d.2 Steel fixing 19-Jul-22 23-Jul-22 4

d.3 Side formwork fixing 24-Jul-22 26-Jul-22 2

d.4 Concrete pouring 27-Jul-22 28-Jul-22 1


e columns 29-Jul-22 13-Aug-22 15

e.1 Steel fixing 29-Jul-22 4-Aug-22 6

e.2 Formwork fixing 5-Aug-22 10-Aug-22 5

e.3 Concrete pouring 11-Aug-22 13-Aug-22 2

f roof slab 14-Aug-22 9-Sep-22 26

f.1 Base formwork 14-Aug-22 24-Aug-22 10

f.2 Steel fixing 25-Aug-22 2-Sep-22 8

f.3 Side formwork fixing 3-Sep-22 7-Sep-22 4

f.4 Concrete pouring 8-Sep-22 9-Sep-22 1

4 Retaining wall-13

Backfilling 29-Jul-22 20-Aug-22 22


6 Retaining wall-15

Backfilling 25-May-22 15-Jun-22 21

8 R.Wall 7/5/2022 8/5/2022 31 R. Wall started after floor P.C.C


(entrance)Length 25'
a Excavation 5-Jul-22 7-Jul-22 2

b foundation 8-Jul-22 19-Jul-22 11

b.1 Lean Concrete 8-Jul-22 10-Jul-22 2


b.2 Steel fixing 11-Jul-22 16-Jul-22 5

b.3 Formwork fixing 17-Jul-22 18-Jul-22 1

b.4 Concrete pouring 18-Jul-22 19-Jul-22 1


c Wall 20-Jul-22 5-Aug-22 16

c.1 Wall steel fixing 20-Jul-22 23-Jul-22 3

c.2 1st step formwork fixing 24-Jul-22 28-Jul-22 4

c.3 1st step Concrete pouring 28-Jul-22 29-Jul-22 1

c.4 2nd step formwork fixing 30-Jul-22 3-Aug-22 4

c.5 2nd step concrete pouring 4-Aug-22 5-Aug-22 1

NOTE:
Bahira Grand Mosque Bahria hills ,Islamabad
Gray Structure Construction

Sr.No Activty Start Date Finish Date Duration


1 Mosque Main Building

a Arches (03 No,s) 1-May-19 31-May-19 30


a.1 Base formwork 1-May-19 10-May-19 9

a.2 Steel fixing 11-May-19 16-May-19 5

1st step formwork fixing(arch start


a.3 to 7'-10") 17-May-19 20-May-19 3

a.4 1st step Concrete pouring 21-May-19 22-May-19 1

a.5 Arch top beam steel fixing 23-May-19 25-May-19 2

a.6 Arch top beam formwork fixing 26-May-19 30-May-19 4

a.7 Arch top beam concrete pouring 30-May-19 31-May-19 1


b Main Dome Construction 15-Apr-19 5-May-19 20
b.1 Dome steel fixing 15-Apr-19 30-Apr-19 15

b.2 Outer formwork fixing 1-May-19 4-May-19 3

b.3 Dome concrete pouring 4-May-19 5-May-19 1


c Samll Domes (04 No,s) 10-May-19 15-Jun-19 36

c.1 Base formwork 10-May-19 30-May-19 20


c.2 Steel fixing 20-May-19 5-Jun-19 16

c.3 Outer formwork fixing 30-May-19 12-Jun-19 13

c.4 Concrete pouring 13-Jun-19 15-Jun-19 2


d Perapit wall 20-May-19 17-Jul-19 58
Detail-1 (Height 3' L=147)

d.1 Steel fixing 20-May-19 23-May-19 3

d.2 Formwork fixing 25-May-19 5-Jun-19 11

d.3 Concrete pouring 6-Jun-19 7-Jun-19 1


Detail-2 (Height 3' L=385)

d.1 Steel fixing 10-Jun-19 16-Jun-19 6

d.2 Formwork fixing 17-Jun-19 2-Jul-19 15

d.3 Concrete pouring 25-Jun-19 5-Jul-19 10


Detail-3 (Height 8' L=360)

d.1 Steel fixing 20-Jun-19 1-Jul-19 11

d.2 Formwork fixing 25-Jun-19 15-Jul-19 20

d.3 Concrete pouring 7-Jul-19 17-Jul-19 10

2 Minaret 4/15/2019 7/31/2019 107


a Construction upto + 88.50 15-Apr-19 26-Apr-19 11

a.1 Formwork fixing 20-Apr-19 25-Apr-19 5


a.2 Concrete pouring 25-Apr-19 26-Apr-19 1

b Construction upto + 107.00 30-Apr-19 13-Jun-19 44

b.1 Steel fixing 30-Apr-19 7-May-19 7

b.2 1st step Formwork fixing 8-May-19 15-May-19 7

b.3 1st step Concrete pouring 15-May-19 16-May-19 1

b.4 2nd step formwork fixing 18-May-19 25-May-19 7

b.5 2nd step concrete pouring 26-May-19 27-May-19 1

b.6 (+107) level shed formwork fixing 28-May-19 5-Jun-19 8

b.7 (+107) level shed steel fixing 6-Jun-19 11-Jun-19 5

b.8 (+107) level shed concrete pouring 12-Jun-19 13-Jun-19 1


c Construction upto + 130 14-Jun-19 31-Jul-19 47

c.1 Steel fixing 14-Jun-19 21-Jun-19 7

c.2 1st step Formwork fixing 22-Jun-19 29-Jun-19 7

c.3 1st step Concrete pouring 29-Jun-19 30-Jun-19 1

c.4 2nd step formwork fixing 1-Jul-19 6-Jul-19 5

c.5 2nd step concrete pouring 7-Jul-19 8-Jul-19 1

c.6 3rd step formwork fixing 10-Jul-19 18-Jul-19 8

c.7 3rd step steel fixing 19-Jul-19 25-Jul-19 6


c.8 3rd step outer formfork 26-Jul-19 30-Jul-19 4

c.9 3rd step concrete pouring 30-Jul-19 31-Jul-19 1


3 Ablution area
a Excavation 25-May-19 30-May-19 5

b foundation 26-May-19 2-Jun-19 7

b.1 Lean Concrete 26-May-19 28-May-19 2

b.2 Footing steel fixing 29-May-19 1-Jun-19 3

b.3 Footing formwork fixing 2-Jun-19 4-Jun-19 2

b.4 Footing concrete pouring 4-Jun-19 5-Jun-19 1

c Column under plinth beam 6-Jun-19 12-Jun-19 6

sc.1 Steel fixing 6-Jun-19 8-Jun-19 2

c.2 Formwork fixing 9-Jun-19 11-Jun-19 2

c.3 Concrete pouring 11-Jun-19 12-Jun-19 1

d Plinth beams 13-Jun-19 23-Jun-19 10

d.1 Base formwork 13-Jun-19 15-Jun-19 2

d.2 Steel fixing 16-Jun-19 19-Jun-19 3

d.3 Side formwork fixing 20-Jun-19 22-Jun-19 2


d.4 Concrete pouring 22-Jun-19 23-Jun-19 1
e columns 24-Jun-19 6-Jul-19 12

e.1 Steel fixing 24-Jun-19 29-Jun-19 5

e.2 Formwork fixing 30-Jun-19 5-Jul-19 5

e.3 Concrete pouring 5-Jul-19 6-Jul-19 1

f roof slab 7-Jul-19 31-Jul-19 24

f.1 Base formwork 7-Jul-19 17-Jul-19 10

f.2 Steel fixing 18-Jul-19 25-Jul-19 7

f.3 Side formwork fixing 26-Jul-19 30-Jul-19 4

f.4 Concrete pouring 30-Jul-19 31-Jul-19 1

4 Retaining wall-13

Backfilling 20-Apr-19 25-May-19 35


5 Retaining wall-3

Backfilling 15-Apr-19 25-Apr-19 10


6 Retaining wall-15

Backfilling 1-May-19 25-May-19 24


6 Retaining wall-01

Backfilling 20-Jun-19 25-Jul-19 35


7 R.Wall (Mosque ~ Ablution) 5/1/2019 6/17/2019 47
Ablution area wall(56')
a Excavation 1-May-19 4-May-19 3

b foundation 6-May-19 17-May-19 11

b.1 Lean Concrete 6-May-19 7-May-19 1

b.2 Steel fixing 8-May-19 11-May-19 3

b.3 Formwork fixing 12-May-19 15-May-19 3

b.4 Concrete pouring 16-May-19 17-May-19 1


c Wall 18-May-19 9-Jun-19 22

c.1 Wall steel fixing 18-May-19 20-May-19 2

c.2 1st step formwork fixing 21-May-19 28-May-19 7

c.3 1st step Concrete pouring 29-May-19 30-May-19 1

c.4 2nd step formwork fixing 31-May-19 7-Jun-19 7

c.5 2nd step concrete pouring 8-Jun-19 9-Jun-19 1


Mosque hall level wall(53')
a Excavation 4-May-19 7-May-19 3

b foundation 6-May-19 20-May-19 14

b.1 Lean Concrete 8-May-19 9-May-19 1

b.2 Steel fixing 12-May-19 15-May-19 3


b.3 Formwork fixing 16-May-19 18-May-19 2

b.4 Concrete pouring 19-May-19 20-May-19 1


c Wall 21-May-19 13-Jun-19 23

c.1 Wall steel fixing 21-May-19 24-May-19 3

c.2 1st step formwork fixing 25-May-19 1-Jun-19 7

c.3 1st step Concrete pouring 2-Jun-19 3-Jun-19 1

c.4 2nd step formwork fixing 4-Jun-19 11-Jun-19 7

c.5 2nd step concrete pouring 12-Jun-19 13-Jun-19 1


Mosque hall stair wall(19')
a Excavation 8-May-19 9-May-19 1

b foundation 10-May-19 25-May-19 15

b.1 Lean Concrete 10-May-19 11-May-19 1

b.2 Steel fixing 16-May-19 19-May-19 3

b.3 Formwork fixing 21-May-19 23-May-19 2

b.4 Concrete pouring 24-May-19 25-May-19 1


c Wall 27-May-19 20-Jun-19 24

c.1 Wall steel fixing 27-May-19 30-May-19 3

c.2 1st step formwork fixing 1-Jun-19 7-Jun-19 6

c.3 1st step Concrete pouring 8-Jun-19 9-Jun-19 1


c.4 2nd step formwork fixing 12-Jun-19 18-Jun-19 6

c.5 2nd step concrete pouring 19-Jun-19 20-Jun-19 1


R.Wall (Minaret ~ Mosque
8 entrance)Length 83' 6/14/2019 7/31/2019 47

a Excavation 14-Jun-19 18-Jun-19 4

b foundation 19-Jun-19 4-Jul-19 15

b.1 Lean Concrete 19-Jun-19 21-Jun-19 2

b.2 Steel fixing 22-Jun-19 27-Jun-19 5

b.3 Formwork fixing 28-Jun-19 2-Jul-19 4

b.4 Concrete pouring 3-Jul-19 4-Jul-19 1


c Wall 5-Jul-19 31-Jul-19 26

c.1 Wall steel fixing 5-Jul-19 9-Jul-19 4

c.2 1st step formwork fixing 10-Jul-19 18-Jul-19 8

c.3 1st step Concrete pouring 19-Jul-19 20-Jul-19 1

c.4 2nd step formwork fixing 21-Jul-19 29-Jul-19 8

c.5 2nd step concrete pouring 30-Jul-19 31-Jul-19 1

NOTE:

We submit 4 No,s of I.P.C More