Professional Documents
Culture Documents
CPA Master Programme Revised (Updated) PDF
CPA Master Programme Revised (Updated) PDF
A1000 KD-1 Drawing & BIM Submission 0 KD-1 Drawing & BIM Submission,
Project Document Submission Schedule 291 03-Feb-20 07-Jan-21, Project Document Submission Schedule
Health & Safety Plan 28 27-Feb-20 30-Mar-20, Health & Safety Plan
Actual Level of Effort Activity Milestone Page 1 of 5 TASK filter: All Activities
Actual Work Critical Activity summary © Oracle Corporation
Works Programme Rev. G of Contract C19W02 Date: 30-Jun-22
A3120 Review & Approval by HKAA 45 27-Mar-20 Review & Approval by HKAA
A3140 Long-lead items fabrication and delivery 42 10-Jul-20 Long-lead items fabrication and delivery
A2070 Supplementary Fire Engineering Report Submission & Approval & GBP 78 24-Feb-20 Supplementary Fire Engineering Report Submission & Approval & GBP Enquiry Pre-submission at 6/F
Enquiry Pre-submission at 6/F
A2080 Pre-submission Enquiry GBP & Structure at 7/F 42 09-Mar-20 Pre-submission Enquiry GBP & Structure at 7/F
Actual Level of Effort Activity Milestone Page 2 of 5 TASK filter: All Activities
Actual Work Critical Activity summary © Oracle Corporation
Works Programme Rev. G of Contract C19W02 Date: 30-Jun-22
A2187 GBP Submission at 6/F & 7/F - Concurrent Processing Approval & 61 28-Oct-20 GBP Submission at 6/F & 7/F - Concurrent Processing Approval & Consent
Consent
A2228 Form BA10 - 6/F & 7/F Commencement of Work 5 30-Nov-20 Form BA10 - 6/F & 7/F Commencement of Work
Design Development (44 weeks) 437 03-Feb-20 26-Jun-21, Design Development (44 weeks)
A1810 BIM Model (for CAVE) 60 16-Jul-20 BIM Model (for CAVE)
A1855 BIM Model (for CAVE) 60 10-Aug-20 BIM Model (for CAVE)
A1865 Sofeware Development for Gameflow 88 02-Dec-20 Sofeware Development for Gameflow
Construction Phase (34 weeks) 264 03-Feb-20 05-Dec-20, Construction Phase (34 weeks)
A2336 Acquire Quotations for Relevant Materials 30 03-Feb-20 Acquire Quotations for Relevant Materials
A2350 Site Possession & Set-out 12 26-Oct-20 Site Possession & Set-out
A2352 Review benchmarking (on site) 10 25-Nov-20 Review benchmarking (on site)
Construction 0
A1900 Site Survey & Report Submission 5 06-Nov-20 Site Survey & Report Submission
A1999 Metal Subframe - TV Wall/ Rope Course/ Slide/ Bird Cage 30 20-Nov-20 Metal Subframe - TV Wall/ Rope Course/ Slide/ Bird Cage
A2000 Ribbon - Structural & Cladding Finish Fabrication & Installation 30 25-Dec-20 Ribbon - Structural & Cladding Finish Fabrication & Installation
A2020 Egg Shell - Structural & Corian Finish Fabrication & Installation 30 25-Dec-20 Egg Shell - Structural & Corian Finish Fabrication & Installation
A2040 E/M Set-out & Floor Box Installation 30 25-Dec-20 E/M Set-out & Floor Box Installation
Actual Level of Effort Activity Milestone Page 3 of 5 TASK filter: All Activities
Actual Work Critical Activity summary © Oracle Corporation
Works Programme Rev. G of Contract C19W02 Date: 30-Jun-22
A2100 Rope Course Ring & Slide 5 29-Jan-21 Rope Course Ring & Slide
A2250 Bird Head (Installation only) 13 02-Mar-21 Bird Head (Installation only)
A2290 Carpet & Safety Padding 13 31-Mar-21 Carpet & Safety Padding
A2310 BA14 Completion Application 6/F 13 28-Apr-21 BA14 Completion Application 6/F
A2320 BD Inspection & BA14 Acknowledgement 26 03-May-21 BD Inspection & BA14 Acknowledgement
A2790 Site Survey & Report Submission 30 26-Oct-20 Site Survey & Report Submission
A2810 Green Wall - Structure Fabrication & Installation 30 15-Dec-20 Green Wall - Structure Fabrication & Installation
A2820 Turf/Sculpture - Structure Fabrication & Installation 30 15-Dec-20 Turf/Sculpture - Structure Fabrication & Installation
A2830 Ash Try Table Subframe 5 19-Jan-21 Ash Try Table Subframe
A2840 Kerb & Truf Pedestal 13 23-Jan-21 Kerb & Truf Pedestal
A2860 Plant Room Equipment Installation 13 16-Jan-21 Plant Room Equipment Installation
A2870 Green Wall Installation (Except Planter) 13 19-Jan-21 Green Wall Installation (Except Planter)
A2880 Ash Tray Table Installation 13 03-Feb-21 Ash Tray Table Installation
A2912 Raised Floor for Turf Installation (Except Turf/ Planter) 13 12-Feb-21 Raised Floor for Turf Installation (Except Turf/ Planter)
A2916 Raised Tile Floor & Pedestal Installation 13 18-Mar-21 Raised Tile Floor & Pedestal Installation
A2920 BA14 Completion Application 7/F 13 01-Apr-21 BA14 Completion Application 7/F
A2930 BD Inspection & BA14 Acknowledgement 35 16-Apr-21 BD Inspection & BA14 Acknowledgement
A2960 Acquire Certification BSEN 1176-10 For Playground Equipment 22 01-Apr-21 Acquire Certification BSEN 1176-10 For Playground Equipment
Submission & Approval of Training, O&M manual & As-built Drawings 61 02-Apr-21 11-Jun-21, Submission & Approval of Training, O&M manual & As-built Drawings
Actual Level of Effort Activity Milestone Page 4 of 5 TASK filter: All Activities
Actual Work Critical Activity summary © Oracle Corporation
Works Programme Rev. G of Contract C19W02 Date: 30-Jun-22
Actual Level of Effort Activity Milestone Page 5 of 5 TASK filter: All Activities
Actual Work Critical Activity summary © Oracle Corporation