Activity ID Activity Name Planned Start Finish Total Float 2020 2021
Duration Oct
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
580 21-Aug-19 27-Jun-21 0 27-Jun-21, Hong Kong International Airport Contract C19W02 Children Play Area &
Hong Kong International Airport Contract C19W02 Children Play Area & Roof Garden at T1
Schedule of Key Date 368 23-Jun-20 27-Jun-21 0 27-Jun-21, Schedule of Key Date
A1000 KD-1 Drawing & BIM Submission 0 23-Jun-20* 191 KD-1 Drawing & BIM Submission,
Project Document Submission Schedule 291 21-Aug-19 25-Jul-20 289 25-Jul-20, Project Document Submission Schedule
Design Quality Plan 28 14-Sep-19 16-Oct-19 531 16-Oct-19, Design Quality Plan
Management Quality Plan 28 14-Sep-19 16-Oct-19 531 16-Oct-19, Management Quality Plan
Construction Quality Plan 28 13-Sep-19 15-Oct-19 532 15-Oct-19, Construction Quality Plan
Sub-contract Managment Plan 28 13-Sep-19 15-Oct-19 532 15-Oct-19, Sub-contract Managment Plan
Health & Safety Plan 28 14-Sep-19 16-Oct-19 531 16-Oct-19, Health & Safety Plan
Actual Level of Effort Activity Milestone Page 1 of 5 TASK filter: All Activities
Actual Work Critical Activity summary © Oracle Corporation
Works Programme Rev. G of Contract C19W02 Date: 16-Aug-22
Activity ID Activity Name Planned Start Finish Total Float 2020 2021
Duration Oct
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A1300 Prepare 14 14-Sep-19 30-Sep-19 531 Prepare
Environment Management Plan 28 13-Sep-19 15-Oct-19 532 15-Oct-19, Environment Management Plan
Waste Management Plan 28 13-Sep-19 15-Oct-19 532 15-Oct-19, Waste Management Plan
Risk Management Plan 28 14-Sep-19 16-Oct-19 531 16-Oct-19, Risk Management Plan
Interface Management Plan 28 14-Sep-19 16-Oct-19 531 16-Oct-19, Interface Management Plan
Site Management Plan 28 14-Sep-19 16-Oct-19 531 16-Oct-19, Site Management Plan
A3120 Review & Approval by HKAA 45 14-Oct-19 04-Dec-19 382 Review & Approval by HKAA
A3140 Long-lead items fabrication and delivery 42 25-Jan-20 14-Mar-20 382 Long-lead items fabrication and delivery
A2070 Supplementary Fire Engineering Report Submission & Approval & GBP 78 11-Sep-19 10-Dec-19 142 Supplementary Fire Engineering Report Submission & Approval & GBP Enquiry Pre-submission at 6/F
Enquiry Pre-submission at 6/F
A2080 Pre-submission Enquiry GBP & Structure at 7/F 42 25-Sep-19 12-Nov-19 289 Pre-submission Enquiry GBP & Structure at 7/F
Actual Level of Effort Activity Milestone Page 2 of 5 TASK filter: All Activities
Actual Work Critical Activity summary © Oracle Corporation
Works Programme Rev. G of Contract C19W02 Date: 16-Aug-22
Activity ID Activity Name Planned Start Finish Total Float 2020 2021
Duration Oct
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A2148a GBP First Submission L7 21 13-Nov-19 06-Dec-19 289 GBP First Submission L7
A2160 GBP First Submission L6 25 02-Jan-20 31-Jan-20 289 GBP First Submission L6
A2187 GBP Submission at 6/F & 7/F - Concurrent Processing Approval & 61 15-May-20 25-Jul-20 289 GBP Submission at 6/F & 7/F - Concurrent Processing Approval & Consent
Consent
A2228 Form BA10 - 6/F & 7/F Commencement of Work 5 17-Jun-20 23-Jun-20 317 Form BA10 - 6/F & 7/F Commencement of Work
Design Development (44 weeks) 579 21-Aug-19 26-Jun-21 1 26-Jun-21, Design Development (44 weeks)
A1796 Comments and Re-submit 14 15-Nov-19 30-Nov-19 379 Comments and Re-submit
A1810 BIM Model (for CAVE) 60 01-Feb-20 10-Apr-20 379 BIM Model (for CAVE)
A1840 Comments and Re-submit 14 10-Dec-19 25-Dec-19 142 Comments and Re-submit
A1855 BIM Model (for CAVE) 60 26-Feb-20 05-May-20 142 BIM Model (for CAVE)
A1865 Sofeware Development for Gameflow 88 19-Jun-20 29-Sep-20 142 Sofeware Development for Gameflow
Construction Phase (34 weeks) 406 21-Aug-19 05-Dec-20 174 05-Dec-20, Construction Phase (34 weeks)
A2336 Acquire Quotations for Relevant Materials 30 21-Aug-19 24-Sep-19 335 Acquire Quotations for Relevant Materials
A2350 Site Possession & Set-out 12 26-Oct-20 07-Nov-20 1 Site Possession & Set-out
A2352 Review benchmarking (on site) 10 25-Nov-20 05-Dec-20 174 Review benchmarking (on site)
A2360 Temp. works set up 7 09-Nov-20 16-Nov-20 191 Temp. works set up
Construction 0 0
Construction at 6/F CPA 231 30-Sep-20 25-Jun-21 1 25-Jun-21, Construction at 6/F CPA
A1900 Site Survey & Report Submission 5 06-Nov-20 11-Nov-20 1 Site Survey & Report Submission
A1999 Metal Subframe - TV Wall/ Rope Course/ Slide/ Bird Cage 30 20-Nov-20 24-Dec-20 1 Metal Subframe - TV Wall/ Rope Course/ Slide/ Bird Cage
A2000 Ribbon - Structural & Cladding Finish Fabrication & Installation 30 25-Dec-20 28-Jan-21 128 Ribbon - Structural & Cladding Finish Fabrication & Installation
A2020 Egg Shell - Structural & Corian Finish Fabrication & Installation 30 25-Dec-20 28-Jan-21 1 Egg Shell - Structural & Corian Finish Fabrication & Installation
A2040 E/M Set-out & Floor Box Installation 30 25-Dec-20 28-Jan-21 128 E/M Set-out & Floor Box Installation
Actual Level of Effort Activity Milestone Page 3 of 5 TASK filter: All Activities
Actual Work Critical Activity summary © Oracle Corporation
Works Programme Rev. G of Contract C19W02 Date: 16-Aug-22
Activity ID Activity Name Planned Start Finish Total Float 2020 2021
Duration Oct
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A2060 Material approval 14 13-Jan-21 28-Jan-21 1 Material approval
A2100 Rope Course Ring & Slide 5 29-Jan-21 03-Feb-21 1 Rope Course Ring & Slide
A2250 Bird Head (Installation only) 13 02-Mar-21 16-Mar-21 1 Bird Head (Installation only)
A2290 Carpet & Safety Padding 13 31-Mar-21 14-Apr-21 1 Carpet & Safety Padding
A2310 BA14 Completion Application 6/F 13 28-Apr-21 12-May-21 1 BA14 Completion Application 6/F
A2320 BD Inspection & BA14 Acknowledgement 26 03-May-21 01-Jun-21 1 BD Inspection & BA14 Acknowledgement
Construction at 7/F RTG 186 26-Oct-20 29-May-21 24 29-May-21, Construction at 7/F RTG
A2790 Site Survey & Report Submission 30 26-Oct-20 28-Nov-20 26 Site Survey & Report Submission
A2810 Green Wall - Structure Fabrication & Installation 30 15-Dec-20 18-Jan-21 13 Green Wall - Structure Fabrication & Installation
A2820 Turf/Sculpture - Structure Fabrication & Installation 30 15-Dec-20 18-Jan-21 120 Turf/Sculpture - Structure Fabrication & Installation
A2830 Ash Try Table Subframe 5 19-Jan-21 23-Jan-21 120 Ash Try Table Subframe
A2840 Kerb & Truf Pedestal 13 23-Jan-21 06-Feb-21 120 Kerb & Truf Pedestal
A2860 Plant Room Equipment Installation 13 16-Jan-21 30-Jan-21 126 Plant Room Equipment Installation
A2870 Green Wall Installation (Except Planter) 13 19-Jan-21 02-Feb-21 13 Green Wall Installation (Except Planter)
A2880 Ash Tray Table Installation 13 03-Feb-21 17-Feb-21 13 Ash Tray Table Installation
A2912 Raised Floor for Turf Installation (Except Turf/ Planter) 13 12-Feb-21 26-Feb-21 42 Raised Floor for Turf Installation (Except Turf/ Planter)
A2916 Raised Tile Floor & Pedestal Installation 13 18-Mar-21 01-Apr-21 13 Raised Tile Floor & Pedestal Installation
A2920 BA14 Completion Application 7/F 13 01-Apr-21 15-Apr-21 13 BA14 Completion Application 7/F
A2930 BD Inspection & BA14 Acknowledgement 35 16-Apr-21 26-May-21 13 BD Inspection & BA14 Acknowledgement
A2960 Acquire Certification BSEN 1176-10 For Playground Equipment 22 01-Apr-21 26-Apr-21 53 Acquire Certification BSEN 1176-10 For Playground Equipment
Submission & Approval of Training, O&M manual & As-built Drawings 61 02-Apr-21 11-Jun-21 13 11-Jun-21, Submission & Approval of Training, O&M manual & As-built Drawings
Actual Level of Effort Activity Milestone Page 4 of 5 TASK filter: All Activities
Actual Work Critical Activity summary © Oracle Corporation
Works Programme Rev. G of Contract C19W02 Date: 16-Aug-22
Activity ID Activity Name Planned Start Finish Total Float 2020 2021
Duration Oct
Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep
A3210 Approval 14 03-Apr-21 19-Apr-21 59 Approval
Actual Level of Effort Activity Milestone Page 5 of 5 TASK filter: All Activities
Actual Work Critical Activity summary © Oracle Corporation