Professional Documents
Culture Documents
PMT-TSD-MET 001 Rev00 VFI T&C METHODOLOGY
PMT-TSD-MET 001 Rev00 VFI T&C METHODOLOGY
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.01 00
VFI TESTING AND EFFECTIVITY:
COMMISSIONING METHODOLOGY
PROJECT:
Reviewed by:
Signed:
Date:
Rev.No.
A – No Comments
B – Comments as noted
C – Not to be used
VFI TESTING AND COMMISSIONING
METHODOLOGY
Page 1 of 9
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.01 00
VFI TESTING AND EFFECTIVITY:
COMMISSIONING METHODOLOGY
I. REFERENCE CODES AND STANDARD
II. OBJECTIVE
The purpose of this document is to present and describe the step by step
testing and commissioning procedure of Vacuum Fault Interrupter (VFI) in
safe manner and approved acceptable local, international, manufacturer’s
standard and serves the intended functions to satisfactory level.
Page 2 of 9
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.01 00
VFI TESTING AND EFFECTIVITY:
COMMISSIONING METHODOLOGY
Inspect all bolted electrical connections for high resistance using
one of the following methods:
Client will confirm all completed punch list and/or prepare pictorial
report especially for the concealed items for necessary approval.
Page 3 of 9
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.01 00
VFI TESTING AND EFFECTIVITY:
COMMISSIONING METHODOLOGY
As-Built Drawings
1. Before connecting cable leads to the VFI terminals, internal bus bars
and connections shall undergo a short-time “megger” test. Megger
tests should be made preferably during dry, temperate weather after
cleaning insulation materials with dry cloth. The switchgear must be
dried before going into service if the insulation resistance to ground
fails below the following minimum values
2. Prior to energizing the VFI, all checks, inspections and tests indicated
below shall be carried out:
Page 4 of 9
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.01 00
VFI TESTING AND EFFECTIVITY:
COMMISSIONING METHODOLOGY
4. Check, Test, Operate VFI as per manufacturer’s instructions.
To operate the VFI manual ON and OFF just push the cut
out forward and pull backward
Page 5 of 9
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.01 00
VFI TESTING AND EFFECTIVITY:
COMMISSIONING METHODOLOGY
Test instrument to be uses is a secondary type current
injection tester.
Attached is a calibration certificate.
Standard procedure is to inject 5 amperes capacity rating
to pattern the secondary side of the current transformer.
Test form for attachment.
7. Test breaker operation from all open, close, and trip devices.
Page 6 of 9
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.01 00
VFI TESTING AND EFFECTIVITY:
COMMISSIONING METHODOLOGY
10. Test contact resistance of VFI.
To test the VFI, test prod is pointed to line and load side
terminal of each pole, micro ohms reading of each pole
must not exceed the recommended values of the
manufacturer.
Test instrument to be used is a Low Resistance Tester
(MEGGER brand)
Attached calibration certificate.
Attached test form.
Attached recommended values for reference.
VI. SUMMARY
Page 7 of 9
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.01 00
VFI TESTING AND EFFECTIVITY:
COMMISSIONING METHODOLOGY
CONTINUATION
NO. SUMMARY OF ACTIVITY BY VISUAL AID
04 Hi pot Tester set to 5KV capacity and testing to be done on a FOREMAN AND
one minute time frame. Continue the process up to 60KV ELECTRICIAN
capacity.
Page 8 of 9
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.01 00
VFI TESTING AND EFFECTIVITY:
COMMISSIONING METHODOLOGY
VII. VISUAL
Page 9 of 9
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.01 00
VFI TESTING AND EFFECTIVITY:
COMMISSIONING METHODOLOGY
VFI WITH OPTIONAL COMPONENTS
END
Page 10 of 9