Professional Documents
Culture Documents
PMT-TSD-MET 02.1 Rev00 TRANSFORMER HAULING & POSITIONING METHODOLOGY
PMT-TSD-MET 02.1 Rev00 TRANSFORMER HAULING & POSITIONING METHODOLOGY
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.2.1 00
TRANSFORMER HAULING AND EFFECTIVITY:
POSITIONING METHODOLOGY
PROJECT:
Reviewed by:
Signed:
Date:
Rev.No.
A – No Comments
B – Comments as noted
C – Not to be used
TRANSFORMER
HAULING & POSITIONING
METHODOLOGY
Page 1 of 7
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.2.1 00
TRANSFORMER HAULING AND EFFECTIVITY:
POSITIONING METHODOLOGY
I. REFERENCE CODES AND STANDARDS
II. OBJECTIVE
The purpose of this method statement is to ensure the correct materials
are installed and agreed procedures are implemented during execution for
the installation of Transformer in safe manner, standard with the
requirements and serve the intended functions to satisfactory level
Page 2 of 7
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.2.1 00
TRANSFORMER HAULING AND EFFECTIVITY:
POSITIONING METHODOLOGY
IV. TRANSFORMER INSTALLATION
loading and unloading operation, the proposed lifting equipment
location to be ready with the compacted floor for safe positioning of
crane and boom trucks
Page 3 of 7
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.2.1 00
TRANSFORMER HAULING AND EFFECTIVITY:
POSITIONING METHODOLOGY
Lift the transformer and tilt it back a little more before travelling. Keep
the forks 6 to 10 inches above the ground to avoid potential hazards
on the ground.
Page 4 of 7
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.2.1 00
TRANSFORMER HAULING AND EFFECTIVITY:
POSITIONING METHODOLOGY
Page 5 of 7
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.2.1 00
TRANSFORMER HAULING AND EFFECTIVITY:
POSITIONING METHODOLOGY
Transformer shall be lifted with maximum sling angle of 60 degrees as
per manufacturer’s recommendation
Points of attachment shall be check for cracks welds or loose nuts and
bolts before lifting
Guide rope shall be used to prevent twisting or swinging of the
transformer once it has been lifted clear of the ground
Secure the transformer to the foundation after assuring the correct
positioning, by anchor bolts
After the transformer installation and approval substation is securely
lockup and the room place under the permit system and only those have
permit are allowed to enter the room
V. TRANSFORMER CHECKLIST
Check transformer are of correct size, type, and capacity in accordance
with schedule and specification
Check mounting alignment and orientation are correct
Check if there is enough space is available on the surrounded of
transformer for maintenance purposes
Inspect for physical, electrical and mechanical condition of the
transformer, no damage evident
Make sure the transformer is grounded
Page 6 of 7
DOC. NO. REV.
ALTERNATIVEPOWER SOLUTIONS, INC. TSD.MET.2.1 00
TRANSFORMER HAULING AND EFFECTIVITY:
POSITIONING METHODOLOGY
done. (If the power transformer has CT circuits, they should be
closed.)
All windings should be checked for continuity. An insulation resistance
test shall be carried out to make certain that no windings are
grounded.
END
Page 7 of 7