Estimation: For RSB

 Movable Cover without Drop Basin

1. Vertical - 16 mm dia. x 6.0 meters RSB


1.22 + 1.45(2) + 0.07(2) + 0.01(2) = 4.46 meters
2. Horizontal – 12 mm dia. x 6.0 meters RSB
8 + 4 pieces of 12 mm dia. x 6.0 meters RSB
3. Cover
a. 16 mm dia. RSB
1.22 + 0.07(2) + 0.1(2) = 1.56 meters
b. 12 mm dia. RSB
7 – 12 mm dia. RSB (spaced equally)

 Drop Basin with Movable Cover

4. Vertical - 16 mm dia. x 6.0 meters RSB


1.22 + 1.53(2) + 0.07(2) + 0.01(2) + 0.50(2) + 0.11(2) = 5.84 meters
5. Horizontal – 12 mm dia. x 6.0 meters RSB
10 + 4 pieces of 12 mm dia. x 6.0 meters RSB
6. Cover
c. 16 mm dia. RSB
1.22 + 0.07(2) + 0.1(2) = 1.56 meters
d. 12 mm dia. RSB
7 – 12 mm dia. RSB (spaced equally)
ESTIMATION: For Reinforced Concrete

 Movable Cover
1.30 x 0.15 = 0.195 m2
 Drainage with Movable Cover
(0.15 x (1.53 + 0.15))(2) = 0.504 m2
(1.00 x 0.15) = 0.15 m2
0.654 m2
 Box Cross Drainage
(1.80