LAS 626

TENDER DOCUMENTATION AND PROCEDURE

PROJECT:
PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE
STATEMENT FOR RESIDENTIAL HOUSE AT PERSIARAN PUNCAK
BESTARI 2, PUNCAK ALAM, 42300 BANDAR PUNCAK ALAM,
SELANGOR DARUL EHSAN FOR MESSRS MAJLIS PERBANDARAN
KUALA SELANGOR.

PREPARED BY:

1. SITI NURDIYANA BINTI MUHAMAD ROSMADI (2021124393)


2. NUR FARAH NADJWA BINTI FAARIS (2021382913)
3. NURUL SYAZWANIE AZWA BINTI ABD RAZAK (2021112629)
4. NURUL NADHIRAH BINTI YAHYA (2021511459)
5. SITI HANISAH BINTI NORIZAN (2021100955)

PREPARED FOR:

DR. FARIDATUL AKMA BINTI ABDUL LATIF

1
PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

Cost estimate
BILL 1: PRELIMINARIES

PAGE BQ1 / 1 / 7

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

A BILL NO.1: PRELIMINARIES AND


GENERAL
NOTE: THE CONTRACTOR IS TO
ALLOW A SUM IF ANY FOR THE
FOLLOWING AND ALL OTHERS
NOT LISTED HERE UNDER BUT
MENTIONED IN THE
SPECIFICATIONS FOR WHICH IN
HIS OPINION ARE NECESSARY - - - -
FOR THE PROPER EXECUTION OF
WORKS.

THE PRICE QUOTED IS LUMP SUM


BASIS. ALL QUANTITY
MENTIONED ARE AS A GUIDE
ONLY

IF THE CONTRACTOR DOES NOT


PRICE ANY OF THE ITEM BELOW,
IT IS DEEMED TO BE INCLUDED IN - -
THE RATES OF L/S -
1. Cutting, removing the area of
weeds, roots, and undesired
debris, as well as grass and
other plants. - -
2. The task of using and L/S -
managing machinery and
equipment will fall under the
purview of the contractor.
Before operating, the Project
Management Consultant must

TOTAL CARRIED TO COLLECTION -

2
PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

Cost estimate
BILL 1: PRELIMINARIES

PAGE BQ1 / 2 / 7

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

A 3. grant his/her consent. -


4. A project signboard must be
provided, put up, and kept in
good condition by the -
contractor.
5. The Contractor shall submit to
the S.O. for his approval the
following as specified: -
● Programmed of Works
● Method statements
● Contractor's
organization chart
● Schedules

TOTAL CARRIED TO COLLECTION -

3
PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

Cost estimate
BILL 1: PRELIMINARIES

PAGE BQ1 / 3 / 7

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

2.0 SITE SECURITY L/S - 500 500


a) Up until the full scope of the
specified Works has been
completed, the Contractor shall
supply all people and
illumination required for the
site's security.

SITE CLEARING L/S - 1,500 1,500


a) Removing all grass and
vegetation from the area as
well as any unwanted weeds,
roots, and other objects.
b) Additionally, the contractor is
required to make room for the
evacuation of garbage and
extra materials produced
during his work. After final
cleanup, leave everything neat
and tidy so that the landscape
architect is happy.
c) The contractor's expenses
must account for any new
facilities.

TOTAL CARRIED TO COLLECTION RM 2000.00


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300

4
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

Cost estimate
BILL 1: PRELIMINARIES

PAGE BQ1 / 4 / 7

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

3.0 SITE PREPARATION L/S - - -


a) The Contractor is assumed to
have visited the work site,
looked over the drawings, and
made sure he was aware of
the means of access,
transportation and movement
facilities, storage of materials
and goods, installation of
constructional plant, existing
services, and site conditions,
as well as all other factors that
might have an impact on his
tender. In this instance, no
more payments will be made.

AS BUILT DRAWING
a) A set of "As-Built Drawings" L/S 1 FOC
encompassing all areas
installed following the
completion of the work must
be created by the contractor.
These plans must reflect the
precise position of all installed
planting and be drawn to the
same scale as the original
planting plans. The landscape
architect must give her or his
approval before the managing
director of the contractor signs
and stamps.

TOTAL CARRIED TO COLLECTION -

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300

5
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

Cost estimate
BILL 1: PRELIMINARIES

PAGE BQ1 / 5 / 7

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

4.0 ELECTRICAL SUPPLY FOR WORK L/S 1 By Main Con


a) Provide all temporary
electricity and storage
facilities, as well as all
necessary electrical power for
the project, together with all
associated costs and fees.

SITE AGENT L/S 1 4,000 4,000


a) The site agent must be
competent and able to
supervise and complete the
assignment properly. In order
to properly supervise and
carry out his contractual
obligations, the subcontractor
must also permit constant
presence on the worksites. All
workers on the site must be
able to communicate with the
architect in both English and
Bahasa Malaysia. He will be
working nonstop and
concentrating solely on
managing the project.

MACHINERY L/S 1 2,000 2,000


1. To supply labor, vehicles,
equipment, and tools for lifting
earth, trees, plants, and other
things.

TOTAL CARRIED TO COLLECTION RM6,000.00


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300

6
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate
BILL 1: PRELIMINARIES

PAGE BQ1 / 6 / 7

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

5.0 WATER SUPPLY FOR WORK L/S 1 By Main Con


a) All water required for the
project must be provided,
together with all costs and
taxes related to it, as well as
all temporary pipes and
storage facilities. All water
must be pure and free of
contaminants.

SAFETY, HEALTH AND WELFARE L/S 3 200


a) The Contractor is responsible
for ensuring the stipulated
levels of safety, health, and
welfare at the work site,
including but not limited to:
 First aid kit availability
 L/S -
SAFE WORKING AREA
a) The Contractor is responsible
for providing, erecting,
maintaining, and removing
scaffolding and working platforms
with safety nettings, catch
platforms, safety barricades,
fencing, railing, screen wire
netting, toes boards, guardrails, -
or board fences as well as
enough lighting, all in accordance
with the requirements.

TOTAL CARRIED TO COLLETION RM200.00

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300

7
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

Cost estimate
BILL 1: PRELIMINARIES

PAGE BQ1 / 7 / 7

NO DESCRIPTION PAGE AMOUNT


NUMBER (RM)

6.0 PRELIMINARIES - RM8,200.00

TOTAL FOR PRELIMINARIES RM8,200.00

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

8
Cost estimate
BILL 2: SOFT LANDSCAPE WORKS

PAGE BQ2 / 1 / 9

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

A ALL QUANTITIES GIVEN ARE


PROVISIONAL QUANTITIES AND
SHALL BE SUBJECTED TO - - - -
RE- MEASUREMENT ON SITE.

SOFT LANDSCAPING

NOTES:

1. Specialized landscape contractors


who have been hired and approved
by the contractor may perform the
landscaping.

2. Plant the following trees, palms,


shrubs, and groundcovers in
accordance with the specification
and drawing, with the approval, by
providing all labor, equipment, tools,
and transportation.

3. Rates must cover routine care for


all plants, including watering,
weeding, pest control, pruning,
fertilizing, checking the soil, cleaning
the site, thriving sick plants, replacing
dead plants, and other maintenance
tasks.

TOTAL CARRIED TO COLLETION -


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

9
Cost estimate
BILL 2: SOFT LANDSCAPE WORKS

PAGE BQ2 / 2 / 9

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

Plant trees, shrubs, and turf includes


unloading and handling them on the
job site, digging planting holes,
backfilling and compacting soil - - - -
around the base of trees and shrubs,
watering in, staking, and performing
maintenance as required.

PLANTING WORKS
B 1.0 PLANTING HOLE
PREPARATION
To supply and plant, which includes
digging a planting hole, removing
unwanted earth, and filling it with
enriched fertilized or compost
mixtures. This includes everything
needed for the planting process, as
well as for sitting, tree protection, and
other tasks. Non-conformance or
failure of plants to establish 2 weeks
upon installation shall be subjected
to replacement of plants or species
at contractor's cost.
a) Palm (5000mm x 5000mm x
5000mm) NOS 1 25.00 25.00
b) Tree (3000mm x 3000mm x
3000mm) NOS 2 25.00 50.00
c) Shrub (300mm x 250mm x
100mm)
d) Groundcovers (1000mm x NOS 56 10.00 560.00
1000mm x 1000mm)

TOTAL CARRIED TO COLLETION RM635.00


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

10
Cost estimate
BILL 2: SOFT LANDSCAPE WORKS

PAGE BQ2 / 3 / 9

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

2.0 SOIL MIXTURE

To supply and lay soil mixture of 3


parts topsoil, 2 parts coarse river
sand, 1 parts organic matter and 1kg
of C.I.R.P per cubic meter or other
mix approved by S.O including
loading and unloading, mixing on
site, filling into excavated planting
holes, lightly ramming and all other
works in connection. Medium is to be
well mixed before planting works to
be carried out. The organic matter is
to be clean, well decomposed, free
from smell, debris, refuse or visible
fungus. The topsoil is to be sourced
from “Contractor site” and to be
approved by S.O.

a) Trees and palms : NOS 3 40.00 120.00


1000mm x 1000mm x 1000m

b) Shrubs :
450mm x 450mm x 450mm NOS 0 30.00 60.00

c) Groundcovers :
150mm x 150mm x 150mm m² 17.42 10.00 174.20

TOTAL CARRIED TO COLLETION RM354.20


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

11
Cost estimate
BILL 2: SOFT LANDSCAPE WORKS

PAGE BQ2 / 4 / 9

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

3.0 STAKING AND TYING, GUYING


TREES

To supply all the materials, labors,


equipment, transportation and etc.
for create timber stake and - - - -
tying/guying trees and to provide
stakes for the structure plants as
follows:

a) Trees : Using 2 nos stakes


hardwood (50mm x 50mm x
2700mm)

4.0 MULCHING

To provide labor, tools, equipment,


and transportation to deliver and
mulch the surrounding planted plants
in accordance with planting
instructions and landscape architect
direction.
NOS 1 30.00 30.00
a) Palm NOS 2 30.00 60.00
b) Trees NOS 56 8.00 448.00
c) Shrubs

TOTAL CARRIED TO COLLETION RM538.00


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

12
Cost estimate
BILL 2: SOFT LANDSCAPE WORKS

PAGE BQ2 / 5 / 9

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

5.0 ROOT BARRIER

Supply and install root barriers for


the specified trees. All works should
follow as according to the
specification or to the satisfaction NOS 3 100.00 300.00
and approval of the Landscape
Architect (L.A) and Superintending
Officer.

PLANT MATERIAL
C
1.0 TREES, PALMS & SHRUBS
PLANTING
Provide and plant trees in
accordance with the instructions
provided. All plant materials must be
free of all diseases and infertility, and
their trunks must be straight.

Tree :
a) Plumeria rubra NOS 2

Shrubs :
a) Acalypha siamensis NOS 36
b) Calathea lutea NOS 4
c) Hymenocallis speciosa NOS 16

Palm :
a) Ravenala madagascariensis NOS 1

TOTAL CARRIED TO COLLETION RM300.00


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

13
Cost estimate
BILL 2: SOFT LANDSCAPE WORKS

PAGE BQ2 / 6 / 9

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

2.0 TURF PLANTING

Using a preferred method of


scarification, to loosen the existing
soil to a depth of 5.0 meters and
remove all loose stones, gravel, tree
stumps, and other objects that are
undesirable for turfing. To spread a
soil mixture with a 75 mm thick layer
over the site, use 1/3 composed soil
and 2/3 approved soil. Before turfing
is permitted, all finishes at grades
must receive L.A. approval.

Turfs / groundcovers :
a) Zoysia matrella m² 17.42

TOTAL CARRIED TO COLLETION RM0.00


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

14
Cost estimate
BILL 2: SOFT LANDSCAPE WORKS

PAGE BQ2 / 7 / 9

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

D MAINTENANCE WORKS
NOTES :
After the practical completion of the
contract, allow for the provision of the
upcoming maintenance, which is
listed below, on a monthly basis to all
landscaped areas for a period of
Twelve (12) MONTHS. If the
maintenance listed below is not
completed to the required standards,
deductions will be made from the
- - - -
monthly maintenance.
1. All labor, supplies, equipment,
machinery, tools, transportation,
and administrative support for
these works.
2. Temporarily store the tools, tree
stakes, and materials needed to
finish the project.
3. After receiving the Certificate of
Practical Completion,
maintenance must begin.

1.0 WATERING
Watering all trees, shrubs, planting
beds, and maintaining moisture - - - -
levels of 20% to 30%, with the
exception of certain plants that don't
need a lot of water (twice per day).

TOTAL CARRIED TO COLLETION RM0.00


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

15
Cost estimate
BILL 2: SOFT LANDSCAPE WORKS

PAGE BQ2 / 8 / 9

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

2.0 WEEDING

To keep planting areas free of weeds


and unwelcome grasses, weeding
the entire planting area using a - - - -
method that has been approved by
the S.O.

3.0 FIRMING UP

Firm up plant and tree stakes as


necessary from time to time during - - - -
the period, especially after a lot of
rain or wind.

4.0 FERTILIZING

All fertilizing must be done with


approved organic manure or slow-
release fertilizers, and the method - - - -
must have prior S.O. per month
approval.

5.0 GRASS CUTTING

Grass cutting every two months by


hand or machine in accordance with - - - -
specifications.
Allow for the entire maintenance
period to be allotted for maintaining
all trees, palms, shrubs, and turf,
including watering, edging, fertilizing,
pruning, and other maintenance.

TOTAL CARRIED TO COLLETION MONTH 12 3500 RM30,000.00


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

16
Cost estimate
BILL 2: SOFT LANDSCAPE WORKS

PAGE BQ2 / 9 / 9

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

6.0 A. PLANTING WORKS NOS 1,192.20

NOS 59 0
B. PLANT MATERIAL

C. MAINTENANCE MONTHS 30,000.00

TOTAL CARRIED TO COLLETION RM31,222.20

17
PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate
BILL 3: HARD LANDSCAPE WORKS

PAGE BQ3 / 1 / 4

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

B HARD LANDSCAPE WORKS


(CONCRETE)

1.0 SIGNAGE NOS 1 6,672.87 6,672.87


To build, supply and install signage,
overall size 7000(L)mmx2000(W) for
the R.C site, refer to Drawing.
1700mm(H) X 5000mm(W) X
700mm THK Rectangular Shape
Wall Entrance (UP) W/ Finishing
(Popcorn Texture) and N.P
Weatherbond, while (Down) finishing
is pebble wash color. Aluminum
laser cutting custom shape for
design flower with LED lamp.
Custom 3D letters 'Taman Bestari 2'
aluminum reference font box
attached with steel laser cut.

To supply, ship, build and install a


3300mm (H) X 1300mm (W) X50mm
THK Stainless steel laser cut custom
shape for a design flower with an
LED lamp mounted on concrete
laser cut steel with a c/w backing
powder coated finish and a concrete
base. All connections follow the
details of the landscape architect.

Refer Drawing no:


LAS626/AP2486A/FP-D3-P3
LAS626/AP2486A/FP-D3-P4

TOTAL CARRIED TO COLLETION RM6,672.87

18
PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate
BILL 3: HARD LANDSCAPE WORKS

PAGE BQ3 / 2 / 4

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

2.0 3D LETTER FONT NOS 1 4,536.00 4,536.00


To supply, ship and install ‘Taman
Bestari 2’ 3D lighting boxed letter
with Aluminum frame box and
fonts with PVC foam board,
aluminum fonts into acrylic finish
with color & graphic architectural
details on landscapes.

1.Aluminium Frame Box


5000mm (H) x 1000 mm (W) x 150
THK

2. 3D Lighted Lettering (Custom)


405mm (H) X 70 mm Thk : Arial

Refer Drawing no:


LAS626/AP2486A/FP-D3-P4
LAS626/AP2486A/FP-D3-P5

3.0 BOLLARD & BENCHES - -

Supply, deliver and install 1250mm NOS 2 125.00 250.00


(H) x 150 mm (W) Lighting bollard

Supply, deliver and install 1500mm NOS 1 60.00 60.00


(H) x 450 mm (W) Concrete bench

Refer Drawing no:


LAS626/AP2486A/FP-D4-P6
LAS626/AP2486A/FP-D5-P7

TOTAL CARRIED TO COLLETION RM4,846.00

19
PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate
BILL 3: HARD LANDSCAPE WORKS

PAGE BQ3 / 3 / 4

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

4.0 OTHERS
Any other items or work not specified
but shown on the drawings or
included in the design summary and
specifications, or essential to the - - - -
proper execution and completion of
the upgrade work, please specify

Any deviation from the above (which


will offer cost savings) according to
the tenderer's quotation rate, please
specify:
- - - -
1. Contractor to provide warranty
materials and manufacturer changes
according to shop drawings.

2. The contractor shall provide a


competent person to be responsible
for all safety on installation and
connection. - - - -

TOTAL CARRIED TO COLLETION -

20
PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate
BILL 3: HARD LANDSCAPE WORKS

PAGE BQ3 / 4 / 4

NO DESCRIPTION PAGE NUMBER AMOUNT


(RM)

5.0 HARD LANDSCAPES WORKS

1. SIGNAGE 6,672.87
2. 3D LETTER FONT 19-20 4,536.00
3. BOLLARD & BENCHES 310.00

TOTAL CARRIED TO COLLETION RM11,518.87

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300

21
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate
BILL 4 : ELECTRICAL WORKS

PAGE BQ4 / 1 / 5

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

1.0 ELECTRICAL WORK


Electrical Switchboard Switchboard
(Section 16441)

Supply, install, connect, test and


commission of Main Distribution Boards
with all components as specified and
qualified. Including hooking up of all
incoming and outgoing feeders/cables,
kWH meters, and all necessary,
ancillary works and material required for
complete installation: -

MDB-1 NO. 1
EMDB NO. 1

Electrical Panelboard (Section 16442)

2.0 Supply, install, connect, test and


commission of Distribution Boards &
Panel Boards with all components as
specified of all incoming and outgoing
feeders/cables, kWH meters and
necessary accessories, ancillary works
and material required for complete
installation, for the following panels: -
NO. 1
G-SMDB

TOTAL CARRIED TO COLLECTION -

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate

22
BILL 4 : ELECTRICAL WORKS

PAGE BQ4 / 2 / 5

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

A. Power Supply and Branch


Electrification

1.0 Main Power Distribution Panels


MDB
SITC of 12-way VTPN MCB DB Double
door type/PANEL, with the following
Circuit breakers-

Incomer: - 250 A 4 pole MCCB with


RYB indicator lamps, Ammeter, SET 1
voltmeter with Selector Switches and 2
Amp (Control MCBs.

Outgoings: - 125A TP MCB - 2 No.


(AC DB (2), 63A TPMCB - 4Nos (UPS
Input DBs + LDB + APFC panel). 40
Amps SP MCB - 1 N0 - (Inventor Input
DB), 16A SPMCBs - 4Nos (2 for Sign
Board + 2 Spare). All circuit breakers of
C Series.

2.0 Power Cables (Section 16120)


Supply. Install, connect, test and
commission of multi-core low voltage
XLPE/SWA/LSZH copper cables
(0.6/1kv) installed on cable trays or
consults or trunking including cables,
earth conductor, including consults,
trunking, fixing accessories, cable
glands, cable straps,

TOTAL CARRIED TO COLLECTION -

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate

23
BILL 4 : ELECTRICAL WORKS

PAGE BQ4 / 3 / 5

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

Terminations and accessories, identifications,


all necessary accessories and ancillary works
as specified.

3.0 Cable Trays (Section 16139)


Supply and installation of able cable
trays/ladders with all necessary accessories,
supports and fitting as shown as specified
and as required for proper operation.

Outlets (Section 16130)

B. 1.0 Lighting Bollard


Supply, install, connect, test and commission
lighting outlets including copper wiring from NO. 10
the outlet to the outlet, from outlet to the
switch and from the outlet to the respective
panelboard, conduit, conduit fittings, boxes,
back boxes, termination and all necessary
accessories and fittings to complete the work
as specified

GROUNDING SYSTEM

Complete earthing system:

1. For powering network including main


earthing networks equipotential bars, taps,
bonding, pits, boxes, clamps, rod, covers,
cadwelds, exothermic connections, etc & all
necessary earthing accessories. To verify
earthing

TOTAL CARRIED TO COLLECTION -


PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate
BILL 4 : ELECTRICAL WORKS

24
PAGE BQ4 / 4 / 5

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

resistance according to the


specification.

2. For a clean earthing system


including main earthing networks
equipotential bars, cables, taps, - - - -
bonding, pits, boxes, clamps, rods,
covers, cadwelds, exothermic
connections, etc. To verify earthing
resistance according to the
specification.

TOTAL CARRIED TO COLLECTION RM 45000.00

25
PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate
BILL 4: ELECTRICAL WORKS

PAGE BQ4 / 5 / 5

NO DESCRIPTION PAGE NUMBER AMOUNT


(RM)

3.0 ELECTRICAL WORKKS - RM11,518.87

TOTAL CARRIED TO COLLETION RM11,518.87

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300

26
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

Cost estimate
BILL 5: COMPULSORY MAINTENANCE

PAGE BQ5 / 1 / 5

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

Maintenance Operation and


Schedule - All maintenance must be
performed according to the
maintenance operation and schedule
in Appendix A. When particular
maintenance is necessary but not
specified, the contractor must consult
the S.O. for guidance.

To provide all necessary materials,


machinery, labor, transportation, and
other things for the ongoing
maintenance of the finished work,
including but not limited to the items
listed below. (During working hours, a
minimum of five (5) people will be
stationed at the site to maintain the
finished works.)

Unsatisfactory maintenance - It is the


contractor's obligation to write in at
the end of each month asking for an
inspection, failing which he will not be
entitled to the maintenance claim for
that month.

If the areas are determined to be


unsatisfactorily maintained, the
maintenance claim payable to the
contractor will be deducted with a
recommended amount that S.O
thinks appropriate.
PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE
STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

27
Cost estimate
BILL 5 : COMPULSORY MAINTENANCE

PAGE BQ5 / 2 / 5

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

A SOFTSCAPE WORKS

Watering
The Landscape Contractor shall
water all trees, palms, shrubs,
groundcover, herbaceous plants and
other planting areas as often as
necessary to keep the ground moist
all around and to the full depth of the
roots.

Weeding
All planting beds are to be kept in a
weed free condition with a weeding
operation as per maintenance
schedule or more regularly as
required. All weeds, stones and
rubbish collected from this operation
shall be removed from the site by the
Landscape Contractor.

Pruning
i.Pruning is to be done with the cut
just above and sloping away from an
outward facing healthy bud.
ii. Removal of branches is to be done
by cutting flush with the adjoining
stem and in such a way that no part
of the stem is damaged or torn.
iii. Ragged edges of bark are to be
trimmed with a sharp knife.
iv. Any cuts or wounds over 25mm
diameter are to be painted with an

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate

28
BILL 5 : COMPULSORY MAINTENANCE

PAGE BQ5 / 3 / 5

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

A approved sealant such as Arbrex


after trimming.
v. All pruning are to be cleared up
and removed from operation site after
pruning for Vermi-Composting.

Disease control MONTH 12 3500 42000


The Landscape Contractor shall on
continual basis supervise and attend
to fertilizer needs/disease
control/termite or fungus control as
maintenance operations during the
entire period of contract. An approved
pesticides shall be applied to each
plant at the rate provided in the
maintenance schedule or as
suggested by the Horticulture Advisor
to the Owner. Fertilizer shall apply
the fertilizer evenly spread over the
entire area and lightly forked into the
soils. All areas shall be well watered
immediately after application of
fertilizer.

Mulching
An additional 25m deep mulching
layer is to be spread over all planted
areas (except groundcover and turf),
once every 6 months or as specified
in Maintenance Schedule

TOTAL SOFT LANDSCAPE WORK MAINTENANCE RM 42,000.00

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.
Cost estimate
BILL 5 : COMPULSORY MAINTENANCE

29
PAGE BQ5 / 4 / 5

NO DESCRIPTION UNIT QTY RATE AMOUNT


(RM) (RM)

HARDSCAPE WORKS

Repaint or reapply any damaged,


faded, or flaking paint, wood stain, or
other finishes.

Replace/tightening up all loosen bolts


and nuts

Any other works not mentioned but


deemed necessary

During the maintenance period, the MONTH 6 3500 21000


Contractor will be responsible for
replacing any dying or vandalized
plants to their original sizes and types
at his own expense, and for the safe
custody of all trees, shrubs, and
plants until they are handed over to
the Employer after the maintenance
period has ended.

TOTAL HARD LANDSCAPE WORK MAINTAINANCE RM 21,000.00

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

Cost estimate
BILL 5 : COMPULSORY MAINTENANCE

30
PAGE BQ5 / 5 / 5

NO DESCRIPTION PAGE NUMBER AMOUNT (RM)

A SOFTSCAPE WORKS RM 42,000.00

B HARDSCAPE WORKS RM 21,000.00

TOTAL FOR COMPULSORY RM 63,000.00


MAINTENANCE

PROPOSED DESIGN, BUILT AND COMPLETE FOR THE ENTRANCE SIGNAGE


STATEMENT AT PERSIARAN PUNCAK BESTARI 2, PUNCAK ALAM, 42300
BANDAR PUNCAK ALAM, SELANGOR DARUL EHSAN FOR MESSRS MAJLIS
PERBANDARAN KUALA SELANGOR.

Cost estimate
BILL 2 : FINAL SUMMARY

PAGE BQ6 / 1 / 1

31
NO DESCRIPTION PAGE NUMBER AMOUNT (RM)

A PRELIMINARIES AND GENERAL BQ1 / 8 / 8 RM 8,200.00

B SOFTSCAPES WORKS BQ2 / 9 / 9 RM 31,222.20

C HARD LANDSCAPE WORKS BQ3 / 3 / 3 RM 11,518.87

D ELECTRICAL WORKS BQ4 / 4 / 5 RM 45,000.00

E COMPULSORY MAINTENANCE BQ5 / 5 / 5 RM 63,000.00

TOTAL CARRIED TO FORM OF RM 158,941.07