Time Required For ROW
Time Required For ROW
Daily
Quantity of No. of Working No.of Cal. Days
Productvity as
Item No. Description Unit delayed Works days required using Cf=1.68
per RMWP
A B C=A/B D=Cf*C
32.02 Backfilling
32.06(e) Class ''A'' Concrete and Form work (for Box culverts) m³ 1,692.57 21 81 135
32.09 Steel Reinforcement
32.09(b) Grade 60 Reinforcement Steel (for Box culverts) Ton 143.12 13.1 11 18
3300 CURBING,CHANNELLING,OPEN CHUTES,Etc.
33.01 Curbing
51.01 SUBBASE
94.01 Sign faces with painted background,symbols,lettering and Engineering grade retro-reflective material with signboard constructed form: