Sl No Item Description Qty Unit Rate (Qrs) Amount (Qrs)

TENDER NO : 20 FT PAINT CONTAINER STORAGE


DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST

1 Item 2.9, Photos 38 & 39 LS

Manpower

Fitter Day 4.00 - - -

Fabricator Day 4.00 - - -


Helper Day 2.00 - - -
Welder Day 2.00
Rigger Day 2.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 2.00 - - -
consumable for welding works kg 1.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Material Considered is
Handrail(8*2+1*2) kg 67.12 CS STD schedule
Flat Bar Size Considered
Flat Bar(18mts) Kg 70.20 is 100mm Width and
5mm Thickness
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -

Removal Assume - 0.4x0.3x1m M3 0 1 0.00 0.00 0.00 0.00 0.00 - - -

- - -

Reconstruction Assume - 0.4x0.3x1m M3 1 1 0.40 0.30 1.00 1.00 1.00 - - -

- - -
- - -
Total Unit-Price for Item 2.9, Photos 38 & 39 - - - - - - - - -
2 Item 2.11, Photos 54 LS
Manpower
Fitter Day 10.00 - - -
Fabricator Day 10.00 - - -
Helper Day 5.00 - - -
Welder Day 10.00
Rigger Day 5.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 5.00 - - -
consumable for welding works kg 5.00 - - -
- - -
Material - - -
650017719.xlsx Page 2 of 27 03/11/2023
06:43:32
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
2'' pipe kg 0.00 - - -
Handrail(15+15+5+5) kg 149.16
Flat Bar(40mts) Kg 156.00
- - -
Sub-contractor - - -
Painting M2 300.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 1 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.11, Photo 54 - - - - - - - - -
3 Item 2.12,2.13, Photos 76 & 79 LS
Manpower
Fitter Day 0.00 - - -
Fabricator Day 0.00 - - -
Helper Day 3.00 - - -
Welder Day 0.00
Rigger Day 3.00
Mason Day 3.00
Shuttering Carpentor Day 3.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 0.00 - - -
consumable for welding works kg 0.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail kg 0.00
Flat Bar Kg 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 1.6x2.2x0.18m M3 0 1 1.60 2.20 0.18 1.00 1.00 - - -
- - -
Reconstruction Assume - 1.6x2.2x0.18m M3 0 1 1.60 2.20 0.18 1.00 1.00 - - -
- - -
Removal Assume - 1.4x2.2x0.18m M3 0 1 1.40 2.20 0.18 1.00 1.00

Reconstruction Assume - 1.4x2.2x0.18m M3 0 1 1.40 2.20 0.18 1.00 1.00


- - -
Total Unit-Price for Item 2.12,2.13, Photo 76 & 79 - - - - - - - - -

Item 2.15-2.15.6,2.15.8,2.15.12,
4 LS
Photos 90,92,&97
Manpower

650017719.xlsx Page 3 of 27 03/11/2023


06:43:32
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Fitter Day 10.00 - - -
Fabricator Day 10.00 - - -
Helper Day 5.00 - - -
Welder Day 5.00
Rigger Day 5.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 5.00 - - -
consumable for welding works kg 6.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 96.95
Flat Bar(40mts) Kg 156.00
Anchor Bolt Nos 24.00 - - -
CS Plate 8mm Thk M2 27.00
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.40 0.30 1.00 6.00 6.00 - - -
- - -
- - -
Total Unit-Price for Item 2.15-2.15.6,2.15.8,2.15.12, Photo 90,92&97 - - - - - - - - -
5 Item 2.16, Photo 98 LS
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 8.00 - - -
Welder Day 4.00
Rigger Day 4.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 104.41
Flat Bar(14mts) Kg 109.20
L channel Size
L-Channel(10mts) kg 23.00 Condiered is 50*50 and
3mm Thk
Anchor Bolt Nos 48.00
CS Plate 8mm Thk M2 54.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -

650017719.xlsx Page 4 of 27 03/11/2023


06:43:32
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.16, Photo 98 - - - - - - - - -
6 Item 2.22, Photo 127,128&129 LS
Manpower
Fitter Day 6.00 - - -
Fabricator Day 6.00 - - -
Helper Day 3.00 - - -
Welder Day 3.00
Rigger Day 3.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 3.00 - - -
consumable for welding works kg 2.50 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel Mts 0.00
Grating M2 0.00
Anchor Bolt Nos 24.00
CS Plate 8mm Thk M2 27.00
- - -
Sub-contractor - - -
Painting M2 2.25 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 1 0.40 0.30 1.00 1.00 1.00 - - -
- - -
- - -
Total Unit-Price for Item 2.22, Photo 127,128&129 - - - - - - - - -
Item 2.24-
7 2.24.4,2.24.6,2.24.7,2.24.8,2.24.1 LS
1, Photos 152&162
Manpower
Fitter Day 10.00 - - -
Fabricator Day 10.00 - - -
Helper Day 5.00 - - -
Welder Day 5.00
Rigger Day 5.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 5.00 - - -

650017719.xlsx Page 5 of 27 03/11/2023


06:43:32
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
consumable for welding works kg 8.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail((6*2+1*2)*4) kg 208.82
Flat Bar(45 mts) Kg 175.50
L-Channel Mts 0.00
Grating M2 0.00
Anchor Bolt Nos 72.00
CS Plate 8mm Thk M2 40.50
- - -
Sub-contractor - - -
Painting M2 6.25 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 1 0.40 0.30 1.00 1.00 1.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 1 0.40 0.30 1.00 1.00 1.00 - - -
- - -
- - -
Total Unit-Price for Item 2.24-2.24.4,2.24.6,2.24.7,2.24.8,2.24.11, Photo 152&162 - - - - - - - - -
8 Item 2.25, Photo 169 LS
Manpower
Fitter Day 6.00 - - -
Fabricator Day 6.00 - - -
Helper Day 3.00 - - -
Welder Day 3.00
Rigger Day 3.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 3.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel Mts 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -

650017719.xlsx Page 6 of 27 03/11/2023


06:43:32
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Total Unit-Price for Item 2.25, Photo 169 - - - - - - - - -
9 Item 2.26, Photo N/A LS
Manpower
Fitter Day 6.00 - - -
Fabricator Day 6.00 - - -
Helper Day 3.00 - - -
Welder Day 3.00
Rigger Day 3.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 3.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel Mts 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.26, Photo N/A - - - - - - - - -
10 Item 2.28-2.28.3, Photo 181 LS
Manpower
Fitter Day 6.00 - - -
Fabricator Day 6.00 - - -
Helper Day 3.00 - - -
Welder Day 3.00
Rigger Day 3.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 3.00 - - -
consumable for welding works kg 3.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel(5mts) kg 11.50
Grating M2 0.00
Anchor Bolt Nos 24.00
- - -

650017719.xlsx Page 7 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.28-2.28.3, Photo 181 - - - - - - - - -
10 Item 2.28-2.28.5, Photo 187 LS
Manpower
Fitter Day 6.00 - - -
Fabricator Day 6.00 - - -
Helper Day 3.00 - - -
Welder Day 3.00
Rigger Day 3.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 3.00 - - -
consumable for welding works kg 3.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel(5mts) kg 11.50
Grating M2 0.00
Anchor Bolt Nos 24.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.28-2.28.5, Photo 187 - - - - - - - - -
11 Item 2.28-2.28.6, Photo 189 LS
Manpower
Fitter Day 6.00 - - -
Fabricator Day 6.00 - - -
Helper Day 3.00 - - -
Welder Day 3.00
Rigger Day 3.00
- - -
Equipment - - -
air compressor Day 0.00 - - -

650017719.xlsx Page 8 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
welding m/c Day 3.00 - - -
consumable for welding works kg 3.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.28-2.28.6, Photo 189 - - - - - - - - -
12 Item 2.28-2.28.9, Photo 185 LS
Manpower
Fitter Day 6.00 - - -
Fabricator Day 6.00 - - -
Helper Day 3.00 - - -
Welder Day 3.00
Rigger Day 3.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 3.00 - - -
consumable for welding works kg 3.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel(6mts) kg 13.80
Grating M2 0.00
Anchor Bolt Nos 24.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -

650017719.xlsx Page 9 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Total Unit-Price for Item 2.28-2.28.9, Photo 185 - - - - - - - - -
Item 2.28-2.28.15, Photo 190
13 LS
&191
Manpower
Fitter Day 10.00 - - -
Fabricator Day 10.00 - - -
Helper Day 5.00 - - -
Welder Day 5.00
Rigger Day 5.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 5.00 - - -
consumable for welding works kg 5.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail kg 0.00
Flat Bar(80mts) Kg 156.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.28-2.28.15, Photo 190 & 191 - - - - - - - - -
14 Item 2.31-2.31.7, Photo 213 LS
Manpower
Fitter Day 10.00 - - -
Fabricator Day 10.00 - - -
Helper Day 5.00 - - -
Welder Day 5.00
Rigger Day 5.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 5.00 - - -
consumable for welding works kg 8.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail kg 0.00
Flat Bar(80mts) Kg 312.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00

650017719.xlsx Page 10 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.31-2.31.7, Photo 213 - - - - - - - - -
15 Item 2.31-2.31.16, Photo 219 LS
Manpower
Fitter Day 6.00 - - -
Fabricator Day 6.00 - - -
Helper Day 3.00 - - -
Welder Day 3.00
Rigger Day 3.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 3.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 24.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.40 0.30 1.00 1.00 1.00 - - -
- - -
- - -
Total Unit-Price for Item 2.31-2.31.16, Photo 219 - - - - - - - - -
Item 2.31-2.31.16, Photos
16 LS
220,221,222&223
Manpower
Fitter Day 0.00 - - -
Fabricator Day 0.00 - - -
Helper Day 5.00 - - -
Welder Day 0.00
Rigger Day 0.00
Mason Day 10.00

650017719.xlsx Page 11 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Shuterring Carpentor Day 5.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 0.00 - - -
consumable for welding works kg 0.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 0.00
Flat Bar(14mts) Kg 0.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 16.00
A393 Mesh Fabric Mts - - -

Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.40 0.30 1.00 4.00 4.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.40 0.30 1.00 4.00 4.00 - - -
- - -
- - -
Total Unit-Price for Item 2.31-2.31.16, Photos 220,221,222&223 - - - - - - - - -

Item 2.33-2.33.2,2.33.10,2.33.12,
17 LS
Photo N/A

Manpower
Fitter Day 12.00 - - -
Fabricator Day 12.00 - - -
Helper Day 6.00 - - -
Welder Day 6.00
Rigger Day 6.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 6.00 - - -
consumable for welding works kg 6.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 156.62
Flat Bar(80mts) Kg 312.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 72.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -

650017719.xlsx Page 12 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.33-2.33.2,2.33.10,2.33.13, Photo N/A - - - - - - - - -
18 2.34-2.34.8 & 2.35-2.35-3 - Photos 418 & 232- N/A
19 Item 2.36-2.36.2, Photo 239 LS
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 4.00
Mason Day 4.00
Shuttring Carpentor Day 4.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 24.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 1.00 1.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.40 0.30 1.00 1.00 1.00 - - -
- - -
- - -
Total Unit-Price for Item 2.36-2.36.2, Photo 239 - - - - - - - - -
20 Item 2.41-2.41.13, Photo 253 LS
Manpower
Fitter Day 0.00 - - -
Fabricator Day 0.00 - - -
Helper Day 6.00 - - -
Welder Day 0.00
Rigger Day 0.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -

650017719.xlsx Page 13 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
air compressor Day 0.00 - - -
welding m/c Day 0.00 - - -
consumable for welding works kg 0.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail kg 0.00
Flat Bar Kg 0.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.41-2.41.13, Photo 253 - - - - - - - - -
21 Item 2.44-2.44.4, Photo 288 LS
Manpower
Fitter Day 0.00 - - -
Fabricator Day 0.00 - - -
Helper Day 9.00 - - -
Welder Day 0.00
Rigger Day 0.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 0.00 - - -
consumable for welding works kg 0.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail kg 0.00
Flat Bar Kg 0.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
- - -
Sub-contractor - - -
Painting M2 100.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -

650017719.xlsx Page 14 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.44-2.44.4, Photo 288 - - - - - - - - -
22 Item 2.46-2.46.3, Photo 290 LS
Manpower
Fitter Day 10.00 - - -
Fabricator Day 5.00 - - -
Helper Day 15.00 - - -
Welder Day 0.00
Rigger Day 5.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 0.00 - - -
consumable for welding works kg 0.00 - - -
Cutting /Grinding Machine Nos 3.00
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail kg 0.00
Flat Bar Kg 0.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.46-2.46.3, Photo 290 - - - - - - - - -
23 Item 2.46-2.46.4, Photo 291 LS
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 4.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 3.00 - - -
- - -

650017719.xlsx Page 15 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.46-2.46.4, Photo 291 - - - - - - - - -
24 Item 2.47-2.47.1, Photo 292 LS
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 4.00
Mason Day 6.00
Shuttring Carpentor Day 3.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(14mts) Kg 54.60
L-Channel(8mts) kg 18.40
Grating M2 1.50
Anchor Bolt Nos 0.00
A393 Mesh Fabric Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.40 0.30 1.00 6.00 6.00 - - -
- - -
- - -

650017719.xlsx Page 16 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Total Unit-Price for Item 2.47-2.47.1, Photo 292 - - - - - - - - -
25 Item 2.54-2.54.2, Photo 269 LS
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 4.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(6*2+1*2) kg 52.21
Flat Bar(55mts) Kg 214.50
L-Channel(8mts) kg 18.40
Grating M2 0.00
Anchor Bolt Nos 0.00
A393 Mesh Fabric Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.54-2.54.2, Photo 269 - - - - - - - - -
26 Item 2.66-2.66.7, Photo 325 LS
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 4.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(40mts) kg 149.16

650017719.xlsx Page 17 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Flat Bar(40mts) Kg 156.00
L-Channel(8mts) kg 18.40
Grating M2 0.00
Anchor Bolt Nos 0.00
A393 Mesh Fabric Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.66-2.66.7, Photo 325 - - - - - - - - -
Item 2.67-2.67.6,2.67.8 Photos Lifting Frame
27 LS
329 & 330 Overhaul
Manpower
Fitter Day 10.00 - - -
Fabricator Day 10.00 - - -
Helper Day 5.00 - - -
Welder Day 5.00
Rigger Day 10.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 2.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail kg 0.00
Flat Bar Kg 0.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
A393 Mesh Fabric Mts 0.00
2mm CS Sheet(1x1) kg 15.70
- - -
Sub-contractor - - -
Painting M2 100.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -

650017719.xlsx Page 18 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Total Unit-Price for Item 2.67-2.67.6,2.67.8 Photos 329 & 330 - - - - - - - - -
Item 2.71-2.71.1,2.71.3 Photo Self Closing Gate
28 LS
381 Required
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 4.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 3.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(10mts) kg 37.29
Flat Bar(5mts) Kg 19.50
L-Channel(8mts) kg 18.40
Grating M2 0.00
Anchor Bolt Nos 0.00
A393 Mesh Fabric Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.71-2.71.1,2.71.3 Photo 381 - - - - - - - - -
Item 2.71-2.71.5, Photo 384 & Lifting Arm
29 LS
385 Overhaul
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 8.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 5.00 - - -
- - -
Material - - -

650017719.xlsx Page 19 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
2'' pipe kg 0.00 - - -
Handrail kg 0.00
Flat Bar Kg 0.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
A393 Mesh Fabric Mts 0.00
- - -
Sub-contractor - - -
Painting M2 100.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.71-2.71.5, Photo 384 & 385 - - - - - - - - -
Item 2.71-2.71.7,2.71.11 Photos Self Closing Gate
30 LS
386 & 390 Required
Manpower
Fitter Day 12.00 - - -
Fabricator Day 12.00 - - -
Helper Day 6.00 - - -
Welder Day 6.00
Rigger Day 6.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 6.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(10mts) kg 37.29
Flat Bar(5mts) Kg 19.50
L-Channel(8mts) kg 18.40
Grating M2 0.00
Anchor Bolt Nos 0.00
Mesh Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -

650017719.xlsx Page 20 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
- - -
Total Unit-Price for Item 2.71-2.71.7,2.71.11 Photos 386 & 390 - - - - - - - - -
31 Item 2.74-2.74.7, Photo 364 LS
Manpower
Fitter Day 4.00 - - -
Fabricator Day 4.00 - - -
Helper Day 2.00 - - -
Welder Day 2.00
Rigger Day 2.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 2.00 - - -
consumable for welding works kg 0.50 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(1 mt) kg 3.73
Flat Bar(1mt) Kg 3.90
L-Channel(1mt) kg 2.30
Grating M2 0.00
Anchor Bolt Nos 0.00
Mesh Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.74-2.74.7, Photo 364 - - - - - - - - -
Over Head Crane
32 Item 2.75-2.75.7, Photo 376 LS Service To be
discussed
Manpower
Fitter Day 0.00 - - -
Fabricator Day 0.00 - - -
Helper Day 0.00 - - -
Welder Day 0.00
Rigger Day 0.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 0.00 - - -
consumable for welding works kg 0.00 - - -
- - -
Material - - -
650017719.xlsx Page 21 of 27 03/11/2023
06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
2'' pipe kg 0.00 - - -
Handrail(1 mt) kg 0.00
Flat Bar(1mt) Kg 0.00
L-Channel(1mt) kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
Mesh Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.75-2.75.7, Photo 376 - - - - - - - - -
33 Item 2.75-2.75.9, Photo N/A LS
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 4.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(10mts) kg 37.29
Flat Bar(10mts) Kg 39.00
L-Channel(8mts) kg 18.40
Grating M2 0.00
Anchor Bolt Nos 24.00
Mesh Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -

650017719.xlsx Page 22 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Total Unit-Price for Item 2.75-2.75.9 Photo N/A - - - - - - - - -
34 Item 2.78-2.78.11, Photo N/A LS
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 4.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(10mts) kg 37.29
Flat Bar(10mts) Kg 39.00
L-Channel(8mts) kg 18.40
Grating M2 0.00
Anchor Bolt Nos 0.00
Mesh Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.78-2.78.11 Photo N/A - - - - - - - - -
Item 2.78-2.78.13,2.78.14 Photo
35 LS
N/A
Manpower
Fitter Day 0.00 - - -
Fabricator Day 0.00 - - -
Helper Day 4.00 - - -
Welder Day 0.00
Rigger Day 4.00
Mason Day 8.00
Shuttring Carpentor Day 4.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 0.00 - - -
consumable for welding works kg 0.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -

650017719.xlsx Page 23 of 27 03/11/2023


06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Handrail kg 0.00
Flat Bar Kg 0.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
Mesh Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.40 0.30 1.00 2.00 2.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.40 0.30 1.00 2.00 2.00 - - -
- - -
- - -
Total Unit-Price for Item 2.78-2.78.13,2.78.14 Photo N/A - - - - - - - - -
Self Closing Gate
36 Item 2.82-2.82.8, Photo 392 LS Required
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 4.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 4.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(5mts) kg 18.65
Flat Bar(5mts) Kg 19.50
L-Channel(5mts) kg 11.50
Grating M2 0.00
Anchor Bolt Nos 0.00
Mesh Mts 0.00
- - -
Sub-contractor - - -
Painting M2 6.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.82-2.82.8 Photo 392 - - - - - - - - -
650017719.xlsx Page 24 of 27 03/11/2023
06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Gate or Chain
37 Item 2.94-2.94.1, Photo N/A LS Required on top of
tank
Manpower
Fitter Day 8.00 - - -
Fabricator Day 8.00 - - -
Helper Day 4.00 - - -
Welder Day 4.00
Rigger Day 4.00
Mason Day 0.00
Shuttring Carpentor Day 0.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 4.00 - - -
consumable for welding works kg 2.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail(5mts) kg 18.65
Flat Bar(5mts) Kg 19.50
L-Channel(5mts) kg 11.50
Grating M2 0.00
Anchor Bolt Nos 0.00
Mesh Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.00 0.00 0.00 0.00 0.00 - - -
- - -
- - -
Total Unit-Price for Item 2.94-2.94.1 Photo N/A - - - - - - - - -
38 Item 2.95-2.95.19, Photo N/A LS
Manpower
Fitter Day 0.00 - - -
Fabricator Day 0.00 - - -
Helper Day 4.00 - - -
Welder Day 0.00
Rigger Day 4.00
Mason Day 4.00
Shuttring Carpentor Day 4.00
- - -
Equipment - - -
air compressor Day 0.00 - - -
welding m/c Day 0.00 - - -
consumable for welding works kg 0.00 - - -
- - -
Material - - -
2'' pipe kg 0.00 - - -
Handrail kg 0.00
650017719.xlsx Page 25 of 27 03/11/2023
06:43:33
TENDER NO : 20 FT PAINT CONTAINER STORAGE
DRAWING NO : NFXP2-SSG-P1-PLN-00002 REV- 1-1

TOTAL TOTAL
SL NO DESCRIPTIONS BOQ UNIT NO LENGTH WIDTH DEPTH QTY DED. QTY UNIT-PRICE AMOUNT Qr REMARKS M/P E/P MAT. S/C OTHER O/P Total
QTY COST
Flat Bar Kg 0.00
L-Channel kg 0.00
Grating M2 0.00
Anchor Bolt Nos 0.00
Mesh Mts 0.00
- - -
Sub-contractor - - -
Painting M2 0.00 - - -
- - -
- - -
- - -
Civil Works - - -
Removal Assume - 0.4x0.3x1m M3 0 0 0.40 0.30 1.00 1.00 1.00 - - -
- - -
Reconstruction Assume - 0.4x0.3x1m M3 0 0 0.40 0.30 1.00 1.00 1.00 - - -
- - -
- - -
Total Unit-Price for Item 2.95-2.95.19 Photo N/A - - - - - - - - -

650017719.xlsx Page 26 of 27 03/11/2023


06:43:33
In-direct

Description Qty Month


1 Project Engineer 1 3
2 Supervisor - Mech 1 3
3 Supervisor - Civil 0.5 3
4 Safty Officer 1 3
5 Surveyor 0 3

Car - for PE 1 3
Pickup - Safety Officer 1 3
Coaster 1 3
Tipper 1 3

Food for Direct

Food for in- Direct 3.5