NLNG TRAIN7

Project

INSTALLATION WORK PACKAGE (IWP)


Concrete Works for Equipment Foundation

IWP-A01-WP2.5-010-FI-LC-101-CV02-101
Concrete Works for Equipment Foundation (7-V-1432) - Lean Concrete

1 08-11-2022 Noel Talo Seokwon Yoon Cheolhwan Kim ISSUE FOR INFORMATION

ISSUE DATE PREPARED CHECKED BY(WFP APPROVED DESCRIPTION


BY(WFP) Lead) BY((Supt/Supv))

CWA: A01-WP2.5-010 CWA Description: New Complete Train

UNIT: 1400 UNIT Description: New Complete Train

DISCIPLINE: Civil-General Level 3 Activity ID:CA01-2.5LC10-1050

Planned Start Date: 2023-01-26 Forecast Start Date:2022-11-14

Planned Finish Date: 2023-01-31 Forecast Finish Date: 2022-11-15

Key Quantity: 1.54 - UOM: M3 Planned Manhours:


NLNG TRAIN7
Project

Concrete Works for Equipment


Foundation
IWP-A01-WP2.5-010-FI-LC-101-CV02-101
Page 2 of 2

IWP Checklist

Checklist

Item Description Included (Y/N) Remarks

1 Working Area Summary Y

2 List of detail items to be installed Y

3 List of Drawings for Construction Y

4 Supply for Concrete by JV Y

5 Constraints Check Sheet Y

6 Special Requirement, if required N

7 Construction Drawings Y

Powered by TCPDF (www.tcpdf.org)


NLNG TRAIN7
Project

Concrete Works for Equipment


Foundation
IWP-A01-WP2.5-010-FI-LC-101-CV02-101
1 of 7

1. Working Area Summary :

Powered by TCPDF (www.tcpdf.org)


NLNG TRAIN7
Project

Concrete Works for Equipment


Foundation
IWP-A01-WP2.5-010-FI-LC-101-CV02-101
2 of 7

2. List of detail items to be installed :

Powered by TCPDF (www.tcpdf.org)


NLNG TRAIN7
Project

Concrete Works for Equipment


Foundation
IWP-A01-WP2.5-010-FI-LC-101-CV02-101
3 of 7

3. List of Drawings for Construction :

Powered by TCPDF (www.tcpdf.org)


NLNG TRAIN7
Project

Concrete Works for Equipment


Foundation
IWP-A01-WP2.5-010-FI-LC-101-CV02-101
4 of 7

4. Supply for Concrete by JV :

Powered by TCPDF (www.tcpdf.org)


NLNG TRAIN7
Project

Concrete Works for Equipment


Foundation
IWP-A01-WP2.5-010-FI-LC-101-CV02-101
5 of 7

5. Constraints Check Sheet :

Powered by TCPDF (www.tcpdf.org)


NLNG TRAIN7
Project

Concrete Works for Equipment


Foundation
IWP-A01-WP2.5-010-FI-LC-101-CV02-101
6 of 7

6. Special Requirement, if required :

Powered by TCPDF (www.tcpdf.org)


NLNG TRAIN7
Project

Concrete Works for Equipment


Foundation
IWP-A01-WP2.5-010-FI-LC-101-CV02-101
7 of 7

7. Construction Drawings :

Powered by TCPDF (www.tcpdf.org)


NLNG TRAIN7
Project

Concrete Works for Equipment


Foundation
IWP-A01-WP2.5-010-FI-LC-101-CV02-101
Page 1 of 2

Close Out:

Planned Finish Date 2023-01-31 Actual Finish Date

Punch list / Item not installed

Component Identifier Description Reason not installed

Lessons Learned

Comments and Suggestions for Improvement (related to general Construction activities or WFP process)

Superintendent / Supervisor Signature: ________________________________________

Date: _____________/_____________/______________
NLNG TRAIN7
Project

Concrete Works for Equipment


Foundation
IWP-A01-WP2.5-010-FI-LC-101-CV02-101
Page 2 of 2

NOTES