FOUNDATION: F3A/ST

TIME DIM QTT DESCRIPTION UNIT


SING
EXCAVATION

1/ Excavation of top soil:


1.050
1.050
1.103 1.103m2 of top soil m²

Excavation depth of trench < 1.5


1/ Depth = 1.050
1.050 (-) top soil = 0.150
1.050 (+) lean concrete= 0.050
0.950 0.950
1.047 1.047m3 m³

CONCRETE
Pad Footing
0.125
0.075 B C B
0.225
A

1.050

A
2/
1.05 0.15
1.05 1.05
0.15 1.05
0.331

B (1.050 - 0.125)/2 = 0.463

2/2/ 0.5
0.075
0.075 1.05
0.463 0.463
1.05
0.073
C
2/
0.075
0.125 1.05
0.075 0.125
1.05
0.020
Total concrete = 0.331 + 0.073 +0.020
= 0.424 m3

0.424 m3 concrete grade 25 m³

Stump

2/ Depth = 1.050
0.125 (-) Ground Beam = 0.188
0.225 (-) Pad Footing = 0.225
0.637 0.637
0.036
0.036 m3 concrete grade 25 m³

LEAN CONCRETE
Lean concrete thickness = 0.05m
2/
1.05
1.05
0.05
0.110
0.110 m3 lean concrete m³

REINFORCEMENT
Pad Footing

8Y10 bothway

Length = 1.05
(-)2 cover = 0.05
(+)2bend = 2 x 5.5 x0.01 = 0.11
1.11
2/2/8
1.11
35.52
35.52m Y10 m
Stump (6Y12)

Length = 1.050
(-) Ground Beam = 0.188
(-) Cover = 0.025
(-) 2Y10 = 2(0.010 ) = 0.020
(+) Lapping = 45(0.012) = 0.540
2/6/ (+) Bend = 5.5(0.012) = 0.066
1.423 1.423
17.076
17.076m Y12 m

Link Stump

6Y12
a= 0.225m
R6-125

b= 0.125m

Length a = 0.225
(-)2Cover = 2(0.025)= 0.05
0.175
(0.175) x 2 sides = 0.35

Length b = 0.125
(-)2Cover = 2(0.025)= 0.05
0.075
(0.175) x 2 sides = 0.15

(+) anchorage, 24d = 24(0.006) = 0.144


0.644

No. of link

Length = 1.050
(-) Ground Beam = 0.188
(-) Cover = 0.025
(-) 2Y10= 2(0.010 ) = 0.02
0.817

(0.817/0.125) + 1 = 7.536
≈8
2/8/
0.644
10.304 10.304m R6 m

FORMWORK
Pad Footing
Length = 1.050

Height = 0.225
(+) Lean concrete = 0.050
0.275
2/4/
1.050
0.275
2.310
2.310 m2 sawn timber 38mm thickness m²

Stump
Length = 1.050
(-)Ground Beam = 0.188
(-) Pad Footing = 0.225
0.637
2/2/ 0.125
0.637
0.319 0.319m2 sawn timber 38mm thickness m²

2/2/ 0.225
0.637
0.573 0.573m2 sawn timber 38mm thickness m²

BACKFILLING

0.125m
0.225m
1.05m
2/
1.075
0.637 1.05m
1.370 Area = (1.05m x 1.05m) - (0.125m x 0.225m)
= 1.075m2 m²
Total backfilling= 1.370 m³
FOUNDATION: F4/CB

TIME DIM QTT DESCRIPTION UNIT


SING
EXCAVATION

1/ Excavation of top soil:


1.200
1.200
1.440 1.440m2 of top soil m²

Excavation depth of trench < 1.5


1/ Depth = 1.050
1.200 (-) top soil = 0.150
1.200 (+) lean concrete= 0.050
0.950 0.950
1.368 1.368m3 m³

CONCRETE
Pad Footing
0.125
0.075 B C B
0.300
A

1.200

A
1/
1.200 0.225
1.200 1.200
0.225 1.200
0.324

B (1.200 - 0.125)/2 = 0.534

1/2/ 0.500
0.075
0.075 1.200
0.534 0.534
1.200
0.048
C
1/
0.075
0.125 1.200
0.075 0.125
1.200
0.011
Total concrete = 0.324 + 0.048 + 0.011
= 0.383 m3

0.383 m3 concrete grade 25 m³

Stump

1/ Depth = 1.050
0.125 (-) Ground Beam = 0.188
0.225 (-) Pad Footing = 0.225
0.637 0.637
0.018
0.018 m3 concrete grade 25 m³

LEAN CONCRETE
Lean concrete thickness = 0.05m
1/
1.200
1.200
0.05
0.072
0.072 m3 lean concrete m³

REINFORCEMENT
Pad Footing

9Y10 bothway

Length = 1.200
(-)2 cover = 0.050
(+)2bend = 2 x 5.5 x0.01 = 0.110
1.260
1/2/9
1.260
22.680
22.680m Y10 m
Stump (10Y12)

Length = 1.200
(-) Ground Beam = 0.188
(-) Cover = 0.025
(-) 2Y10 = 2(0.010 ) = 0.020
(+) Lapping = 45(0.012) = 0.540
1/6/ (+) Bend = 5.5(0.012) = 0.066
1.573 1.573
9.438
9.438m Y12 m

Link Stump

6Y12
a= 0.900m
R6-125

b= 0.225m

Length a = 0.900
(-)2Cover = 2(0.025)= 0.050
0.85
(0.175) x 2 sides = 1.7

Length b = 0.225
(-)2Cover = 2(0.025)= 0.050
0.175
(0.175) x 2 sides = 0.35

(+) anchorage, 24d = 24(0.006) = 0.144


2.194

No. of link

Length = 1.200
(-) Ground Beam = 0.188
(-) Cover = 0.025
(-) 2Y10= 2(0.010 ) = 0.02
0.967

(0.967/0.175) + 1 = 6.526
≈7
1/7/
2.194
15.358 15.358m R6 m

FORMWORK
Pad Footing
Length = 1.200

Height = 0.300
(+) Lean concrete = 0.050
0.350
1/4/
1.200
0.350
1.680
1.680 m2 sawn timber 38mm thickness m²

Stump
Length = 1.050
(-)Ground Beam = 0.188
(-) Pad Footing = 0.300
0.562
1/2/ 0.900
0.562
2.0232 0.281 m2 sawn timber 38mm thickness m²

1/2/ 0.225
0.562
0.253 0.253 m2 sawn timber 38mm thickness m²

BACKFILLING

0.225m
0.900m
1.2m
1/
1.238
0.562 1.2m
2.783 Area = (1.2m x 1.2m) - (0.225m x 0.900m)
= 1.238m2 m²
Total backfilling= 2.783 m³
FOUNDATION: F4A/C1

TIME DIM QTT DESCRIPTION UNIT


SING
EXCAVATION

1/ Excavation of top soil:


1.350
1.350
1.823 1.823 m2 of top soil m²

Excavation depth of trench < 1.5


1/ Depth = 1.050
1.350 (-) top soil = 0.150
1.350 (+) lean concrete= 0.050
0.950 0.950
1.731 1.731 m3 m³

CONCRETE
Pad Footing
0.125
0.075 B C B
0.300
A

1.500

A
5/
1.350 0.225m
1.350 1.35m
0.225 1.35m
2.050

B (1.35 - 0.125)/2 = 0.613

5/2/ 0.500
0.075m
0.075 1.35m
0.613 0.613m
1.350
0.310 1/2 x 0.075 x 0.613 x 1.35
= 0.310
C
5/
0.075m
0.125 1.35m
0.075 0.125m
1.350
0.063
Total concrete = 2.050+0.310+0.063
= 2.423 m3

2.423 m3 concrete grade 25 m³

Stump

5/ Depth = 1.050
0.125 (-) Ground Beam = 0.188
0.225 (-) Pad Footing = 0.300
0.562 0.562
0.079
0.079 m3 concrete grade 25 m³

LEAN CONCRETE
Lean concrete thickness = 0.05m
5/
1.350
1.350
0.050
0.456
0.456 m3 lean concrete m³

REINFORCEMENT
Pad Footing

10Y10 bothway
Length = 1.350
(-) 2 cover = 2 x 0.025 = 0.050
(+) 2bend = 2 x 5.5x0.01 = 0.110
1.410
5/2/10/
1.410
141.000
141.000m Y10 m
Stump

Length = 1.050
(-) Ground Beam = 0.188
(-) 2 Cover = 0.050
(-) 2Diameter Bar = 2(0.010 ) = 0.020
(+) Lapping = 45(0.012) = 0.540
(+) Bend = 5.5(0.012) = 0.066
1.398

5/6/ 1.398
41.94 41.940 m Y12 m

Link Stump

6Y12
a= 0.225m
R6-125

b= 0.125m

Length a = 0.225
(-)2Cover = 2(0.025)= 0.05
0.175
(0.175) x 2 sides = 0.35

Length b = 0.125
(-)2Cover = 2(0.025)= 0.05
0.075
(0.175) x 2 sides = 0.15

(+) anchorage, 24d = 24(0.006) = 0.144


0.644

No. of link

Length = 1.050
(-) Ground Beam = 0.188
(-) Cover = 0.025
(-) 2Y10 = 2(0.010 ) = 0.020
0.817

(0.817/0.125) + 1 = 7.536
≈8
5/8/
0.644
25.760 25.760 m R6 m

FORMWORK
Pad Footing
Length = 1.350

Height = 0.300
(+) Lean concrete = 0.050
0.350
5/4/
1.350
0.350
9.450
9.450 m2 sawn timber 38mm thickness m²

Stump
Length = 1.050
(-)Ground Beam = 0.188
(-) Pad Footing = 0.300
0.562
5/2/ 0.125
0.562
0.703 0.703 m2 sawn timber 38mm thickness m²

5/2/ 0.225
0.562
1.265 1.265 m2 sawn timber 38mm thickness m²

BACKFILLING

0.125m
0.225m
1.35m
5/
1.794
0.562 1.5m
5.041 Area = (1.35m x 1.35m) - (0.125m x 0.225m)
= 1.794 m2 m²
Total backfilling= 5.041 m³
FOUNDATION: F5/C1

TIME DIM QTT DESCRIPTION UNIT


SING
EXCAVATION

1/ Excavation of top soil:


1.500
1.500
2.250 2.250m2 of top soil m²

Excavation depth of trench < 1.5


1/ Depth = 1.050
1.500 (-) top soil = 0.150
1.500 (+) lean concrete= 0.050
0.950 0.950
2.138 2.138m3 m³

CONCRETE
Pad Footing
0.125
0.075 B C B
0.300
A

1.500

A
8/
1.5 0.225m
1.5 1.5m
0.225 1.5m
4.050

B (1.50 - 0.125)/2 = 0.688

8/2/ 0.5
0.075m
0.075 1.5m
0.688 0.688m
1.5
0.619 1/2 x 0.075 x 0.688 x 1.50
= 0.0387
C
8/
0.075m
0.125 1.5m
0.075 0.125m
1.5
0.113
Total concrete = 4.050+0.619+0.113
= 4.782m3

4.782m3 concrete grade 25 m³

Stump

8/ Depth = 1.050
0.125 (-) Ground Beam = 0.188
0.225 (-) Pad Footing = 0.300
0.562 0.562
0.126
0.126m3 concrete grade 25 m³

LEAN CONCRETE
Lean concrete thickness = 0.05m
8/
1.5
1.5
0.05
0.900
0.900m3 lean concrete m³

REINFORCEMENT
Pad Footing

11Y12 bothway
Length = 1.500
(-) 2 cover = 0.100
(+) 2 bend = 2(5.5)(0.012)
1.532
8/2/11/
1.532
269.632
269.632m Y12 m
Stump

Length = 1.050
(-) Ground Beam = 0.188
(-) Cover = 0.025
(-) 2Diameter Bar = 2(0.012 ) = 0.024
(+) Lapping = 45(0.012) = 0.540
8/6/ (+) Bend = 5.5(0.012) = 0.066
1.419 1.419
68.112
68.112m Y12 m

Link Stump

6Y12
a= 0.225m
R6-125

b= 0.125m

Length a = 0.225
(-)2Cover = 2(0.025)= 0.05
0.175
(0.175) x 2 sides = 0.35

Length b = 0.125
(-)2Cover = 2(0.025)= 0.05
0.075
(0.175) x 2 sides = 0.15

(+) anchorage, 24d = 24(0.006) = 0.144


0.644

No. of link

Length = 1.050
(-) Ground Beam = 0.188
(-) Cover = 0.025
(-) 2Y12= 2(0.012 ) = 0.024
0.813

(0.813/0.125) + 1 = 7.504
≈8
8/8/
0.644
41.216 41.216m R6 m

FORMWORK
Pad Footing
Length = 1.500

Height = 0.300
(+) Lean concrete = 0.050
0.350
8/4/
1.500
0.350
17
17m2 sawn timber 38mm thickness m²

Stump
Length = 1.050
(-)Ground Beam = 0.188
(-) Pad Footing = 0.300
0.562
8/2/ 0.125
0.562
1.124 1.124m2 sawn timber 38mm thickness m²

8/2/ 0.225
0.562
2.023 2.023m2 sawn timber 38mm thickness m²

BACKFILLING

0.125m
0.225m
1.5m

1.5m
8/ Area = (1.5m x 1.5m) - (0.125m x 0.225m)
2.222 = 2.222m2 m²
0.562
9.990 9.990 m3 backfilling m³
FOUNDATION: F5A/C1

TIME DIM QTT DESCRIPTION UNIT


SING
EXCAVATION

1/ Excavation of top soil:


1.650
1.650
2.723 2.723m2 of top soil m²

Excavation depth of trench < 1.5


1/ Depth = 1.050
1.650 (-) top soil = 0.150
1.650 (+) lean concrete= 0.050
0.950 0.950
2.586 2.586m3 m³

CONCRETE
Pad Footing
0.125
0.075 B C B
0.300
A

1.050

A
1/
1.650 0.15
1.650 1.650
0.15 1.650
0.408

B (1.650 - 0.125)/2 = 0.763

1/2/ 0.5
0.075
0.075 1.650
0.763 0.763
1.65
0.094
C
1/
0.075
0.125 1.650
0.075 0.125
1.650
0.015
Total concrete = 0.408 + 0.094 +0.015
= 0.517 m3

0.517 m3 concrete grade 25 m³

Stump

1/ Depth = 1.050
0.125 (-) Ground Beam = 0.188
0.225 (-) Pad Footing = 0.300
0.562 0.562
0.016
0.016 m3 concrete grade 25 m³

LEAN CONCRETE
Lean concrete thickness = 0.05m
1/
1.650
1.650
0.05
0.136
0.136 m3 lean concrete m³

REINFORCEMENT
Pad Footing

12Y12 bothway

Length = 1.650
(-)2 cover = 0.05
(+)2bend= 2 x 5.5 x0.012= 0.132
1.732
1/2/12
1.732
41.568
41.568m Y12 m
Stump (6Y12)

Length = 1.050
(-) Ground Beam = 0.188
(-) Cover = 0.025
(-) 2Y12 = 2(0.012 ) = 0.024
(+) Lapping = 45(0.012) = 0.540
1/6/ (+) Bend = 5.5(0.012) = 0.066
1.419 1.419
8.514
8.514m Y12 m

Link Stump

6Y12
a= 0.225m
R6-125

b= 0.125m

Length a = 0.225
(-)2Cover = 2(0.025)= 0.05
0.175
(0.175) x 2 sides = 0.35

Length b = 0.125
(-)2Cover = 2(0.025)= 0.05
0.075
(0.175) x 2 sides = 0.15

(+) anchorage, 24d = 24(0.006) = 0.144


0.644

No. of link

Length = 1.050
(-) Ground Beam = 0.188
(-) Cover = 0.025
(-) 2Y12 = 2(0.012 ) = 0.024
0.813

(0.813/0.125) + 1 = 7.504
≈8
1/8/
0.644
5.152 5.152m R6 m

FORMWORK
Pad Footing
Length = 1.650

Height = 0.300
(+) Lean concrete = 0.050
0.350
1/4/
1.650
0.350
2.310
2.310 m2 sawn timber 38mm thickness m²

Stump
Length = 1.050
(-)Ground Beam = 0.188
(-) Pad Footing = 0.300
0.562
1/2/ 0.125
0.562
0.562 0.562 m2 sawn timber 38mm thickness m²

1/2/ 0.225
0.562
1.012 1.012 m2 sawn timber 38mm thickness m²

BACKFILLING

0.125m
0.225m
1.65m
1/
2.694
0.562 1.65m
1.514 Area = (1.65m x 1.65m) - (0.125m x 0.225m)
= 2.694m2 m²
Total backfilling= 1.514 m³
B
E
A
M
GROUND FLOOR BEAM: G13 ( 125 x 375 )

TIME DIM QTT DESCRIPTION UNIT


SING

CONCRETE
Length = 2.438
(+) 2x1/2column= 0.125
2.313
1/
2.313
0.125
0.375
0.108
0.108 m3 concrete grade 25 m³

REINFORCEMENT

Reinforcement (top)

2.438m
2Y10

Length = 2.438
(+) 2x1/2column= 0.125
(-) 2 Cover = 0.050
(+) 2bend = 2x5.5 x0.010= 0.110
2.623
1/2
2.623
5.246
5.246m of 2Y10 m
Reinforcement (bottom)

2Y16
2.438m

Length = 2.438
(+) 2x1/2column= 0.125
(-) 2 Cover = 0.050
(+) 2bend = 2x5.5 x0.010= 0.110
2.623
1/2
2.623
5.246
5.256m of 2Y10 m

Link (R6-225)

R6 225 c/c
0.375m

0.125m

Length = 0.375
(-) 2 Cover = 0.050
0.325

Length = 0.125
(-) 2 Cover = 0.050
0.075

Total = 2 x (0.325 + 0.075)= 0.800


(+)anchorage,24d=24x0.006= 0.144
0.944
No. of Links

Length = 2.438
(+) 2x1/2column= 0.125
2.313
length req.link
+1
spacing

(2313/225) +1 = 11.280
≈ 11
1/11
1.394
15.334
15.334m link R6-225 m

FORMWORK
Outer side
Length = 2.438
(+) 2x1/2column= 0.125
1/ 2.563
2.563
0.375
0.961 0.961m2 sawn timber 38mm thickness m²

Inner side
Length = 2.438
(+) 2x1/2column= 0.125
2.313
1/
2.313
0.375
0.867
0.867m2 sawn timber 38mm thickness m²
Soffit
Length = 2.438
(+) 2x1/2column= 0.125
2.313
1/
2.313
0.125
0.289
0.289m2 sawn timber 38mm thickness m²
GROUND FLOOR BEAM: TB (125 x 375)

TIME DIM QTT DESCRIPTION UNIT


SING

CONCRETE
Length = 2.738
(-) Column CZ = 0.125
2.613
1/
2.613
0.125
0.375
0.122
Length = 2.364
(-) Column CC, CA = 0.225
2.139

CC & CA, 2(2.139) = 4.278


2/
4.278
0.125
0.375
0.401
0.524
0.524 m3 concrete grade 25 m³
REINFORCEMENT

Reinforcement (top & bottom)

2Y10

Length = 2.738
(1) - (+) Beam G10 = 0.125
(+) Column CZ = 0.125
(-) 2 Cover = 0.050
(+) 2 Bend 2x5.5(0.010) = 0.110
3.048
1/2/2
3.048
12.192

Length = 2.364
(2) & (3) (+) Column C1 = 0.125
(+) Column CA = 0.225
(-) 2 Cover = 0.050
(+) 2 Bend 2x5.5(0.010) = 0.110
2.774
2/2/2
2.774
22.192
34.384
34.384kg of Y10 kg

Link (R6 - 225)

R6-225 c/c
0.375m

0.125m

Length = 0.125
(-) 2 Cover = 0.050
0.075

Length = 0.375
(-) 2 Cover = 0.050
0.325

Total : 2 x (0.075 + 0.075)= 0.800


(+) 2 Hooks, 12d=2x12x0.006= 0.144
0.944

No. of Links

(1) - Length = 2.738


(-) Column CZ = 0.125
2.613
length req.link
+1
spacing

(2613/225) +1 = 12.613
≈ 13
1/13
0.944
12.272

(2) & (3) Length = 2.364


(-) Column CZ = 0.225
2.139
length req.link
+1
spacing

(2139/225) +1 = 10.506
≈ 11
2/11
0.944
20.768
33.04
33.04 m link R6

FORMWORK
Outer side
Length = 2.738
(1) - (+) Column CZ = 0.125
1/ 2.863
2.863
0.45
1.288

1/
2.863
0.375
1.074
2.36200
2.362 m2 sawn timber 38 mm thickness m²

Length = 2.364
(2) & (3) (+) Column CC & CA = 0.225
2.589

Total both CC & CA, 2(2.589) = 5.178


2/
5.178
0.45
4.660
2/
5.178
0.375
3.8835 m²
8.54400
8.544 m2 sawn timber 38 mm thickness m²

Inner side

Length CZ = 2.613
Length CC + CA = 4.278
Total = 6.891
1/
0.375
6.891
2.584
2.584 m2 sawn timber 38 mm thickness m²

Soffit
Length = 3.048
(-)2x1/2Column = 0.125
2.923
1/
2.923
0.125
0.365
0.365 m2 sawn timber 38mm thickness m²
FIRST FLOOR BEAM: FASCIA (125 x 450)

TIME DIM QTT DESCRIPTION UNIT


SING

CONCRETE
Length = 4.268
(-)2x1/2beam = 0.125
4.143
1/
4.143
0.125
0.600
0.311
0.311 m3 concrete grade 25 m³

REINFORCEMENT

Reinforcement (top)

4.268m
2Y12

Length = 4.268
(+) 2x1/2 beam = 0.125
(-) 2 Cover = 0.050
(+) 2bend = 2x5.5 x0.012= 0.132
4.475
1/2
4.475
8.950
8.950 of 2Y16 m
Reinforcement (bottom)

2Y12
4.268m

Length = 4.268
(+) 2x1/2 beam = 0.125
(-) 2 Cover = 0.050
(+) 2bend = 2x5.5 x0.012= 0.132
4.475
1/2
4.475
8.950
8.950m of 2Y16 m

Link (R6-225)

R6 225 c/c
0.450m

0.125m

Length = 0.450
(-) 2 Cover = 0.050
0.400

Length = 0.125
(-) 2 Cover = 0.050
0.075

Total = 2 x (0.400 + 0.075)= 0.950


(+)anchorage,24d=24x0.006= 0.144
1.094
No. of Links

Length = 4.268
(-) 2x1/2 beam = 0.125
4.143
length req.link
+1
spacing

(4143/225) +1 = 19.413
≈ 19
1/19
1.094
20.786
20.786m link R6-225 m

FORMWORK
Outer side
Length = 4.268
(+)2x1/2 beam = 0.125
1/ 4.393
4.393
0.45
1.977 1.977m2 sawn timber 38mm thickness m²

Inner side
Length = 4.268
(-)2x1/2 beam = 0.125
4.143
1/
4.143
0.45
1.864
1.864m2 sawn timber 38mm thickness m²
Soffit
Length = 4.268
(-)2x1/2 beam = 0.125
4.143
1/
4.143
0.125
0.518
0.518m2 sawn timber 38mm thickness m²
FIRST FLOOR BEAM: FASCIA (125 x 600)

TIME DIM QTT DESCRIPTION UNIT


SING

CONCRETE
Length = 6.096
(-)2x1/2 beam = 0.125
5.971
1/
5.971
0.125
0.600
0.448
0.448 m3 concrete grade 25 m³

REINFORCEMENT

Reinforcement (top)

6.096m
2Y16

Length = 6.096
(+) 2x1/2 beam = 0.125
(-) 2 Cover = 0.050
(+) 2bend = 2x5.5 x0.016= 0.176
6.347
1/2
6.347
12.694
12.694 of 2Y16 m
Reinforcement (bottom)

2Y16
6.096m

Length = 6.096
(+) 2x1/2 beam = 0.125
(-) 2 Cover = 0.050
(+) 2bend = 2x5.5 x0.016= 0.176
6.347
1/2
6.347
12.694
12.694m of 2Y16 m

Link (R6-225)

R6 225 c/c
0.600m

0.125m

Length = 0.600
(-) 2 Cover = 0.050
0.550

Length = 0.125
(-) 2 Cover = 0.050
0.075

Total = 2 x (0.550 + 0.075)= 1.250


(+)anchorage,24d=24x0.006= 0.144
1.394
No. of Links

Length = 6.096
(-) 2x1/2 beam = 0.125
5.971
length req.link
+1
spacing

(5971/225) +1 = 27.540
≈ 28
1/28
1.394
39.032
39.032m link R6-225 m

FORMWORK
Outer side
Length = 6.096
(+)2x1/2 beam = 0.125
1/ 6.221
6.221
0.6
3.733 3.733m2 sawn timber 38mm thickness m²

Inner side
Length = 6.096
(-)2x1/2 beam = 0.125
5.971
1/
5.971
0.6
3.583
3.583m2 sawn timber 38mm thickness m²
Soffit
Length = 6.096
(-)2x1/2 beam = 0.125
5.971
1/
5.971
0.125
0.746
0.746m2 sawn timber 38mm thickness m²
ROOF BEAM: UB (125 x 450)

TIME DIM QTT DESCRIPTION UNIT


SING

CONCRETE
Length = 3.048
(-)2x1/2Column = 0.125
2.923
1/
2.923
0.125
0.450
0.164
0.164 m3 concrete grade 25 m³

REINFORCEMENT

Reinforcement (top)

3.048m
2Y12

Length = 3.048
(+) 2x1/2Column= 0.125
(-) 2 Cover = 0.050
(+) 2bend = 2x5.5 x0.012= 0.132
3.255
1/2
3.255
6.510
6.510m of Y12 m
Reinforcement (bottom)

2Y12
3.048m

Length = 3.048
(+) 2x1/2Column= 0.125
(-) 2 Cover = 0.050
(+) 2bend = 2x5.5 x0.012= 0.132
3.255
1/2
3.255
6.510
6.510m of Y12 m

Link (R6-150)

R6 150 c/c
0.450m

0.125m

Length = 0.450
(-) 2 Cover = 0.050
0.400

Length = 0.125
(-) 2 Cover = 0.050
0.075

Total = 2 x (0.4 + 0.075)= 0.950


(+)anchorage,24d=24x0.006= 0.144
1.094
No. of Links

Length = 3.048
(-) 2x1/2Column= 0.125
2.923
length req.link
+1
spacing

(2923/150) +1 = 20.480
≈ 20
1/20
1.094
21.88
21.880m link R6-150 m

FORMWORK
Outer side
Length = 3.048
(+)2x1/2Column = 0.125
1/ 3.173
3.173
0.45
1.428 1.428m2 sawn timber 38mm thickness m²

Inner side
Length = 3.048
(-)2x1/2Column = 0.125
2.923
1/
2.923
0.45
1.315
4.102m2 sawn timber 38mm thickness m²
Soffit
Length = 3.048
(-)2x1/2Column = 0.125
2.923
1/
2.923
0.125
0.365
4.102m2 sawn timber 38mm thickness m²
S
L
A
B
FIRST FLOOR SLAB: FS2 (Section 1-1)

TIME DIM QTT DESCRIPTION UNIT


SING

Lyy = 3.048
Lxx = 3.048
Thickness = 0.125

CONCRETE

Length Lyy = 3.048


(-) 2 half beam= 2(0.125/2)= 0.125
2.923

Length Lxx = 3.048


(-) 2 half beam= 2(0.125/2)= 0.125
2.923
1/ 2.923
2.923
0.125
1.068 1.068 m3 concrete grade 25 m³

FORMWORK
Soffit

ly = 2.923
lx = 2.923

Length,Lyy = 3.048
(-) 2 half beam= 2(0.125/2) = 0.125
2.923
1/ Length,Lxx = 3.048
2.923 (-) 2 half beam= 2(0.125/2) = 0.125
2.923 2.923
8.544 8.544 m2 sawn timber 38mm thickness m²
REINFORCEMENT

Reinforcement bar support on top:


(y-direction Y10-225)

Length = 0.750
(+) half beam= (0.125/2) = 0.063
(-) covers, (0.025) = 0.025
Total length = 0.788

Number of bar,Y10-225

Length,Lyy = 0.750
(-) 2 half beam= 2(0.125/2) = 0.125
Length required steel = 0.625

No. of steel = (length req. steel / spacing) +1

(625 / 225) + 1 = 3.779


≈4
2/4/
0.788
6.304
6.304m Y10-225 m

Reinforcement bar support on top :


(x-direction Y10-225)

Length = 0.750
(+) half beam= (0.125/2) = 0.063
(-) covers, (0.025) = 0.025
Total length = 0.788

No of steel, Y10-225

Length = 0.750
(-) 2 half beam= 2(0.125/2) = 0.125
Length required steel = 0.625

No. of steel = (length req. steel / spacing) +1

(625 / 300) + 1 = 3.778


≈4
2/4/
0.788
6.304
6.304m of Y10-225 m

Reinforcement bar on bottom :


(x-direction Y10-225)

Length = 3.048
(+) 2 half beam= 2(0.125/2) = 0.125
(-) 2covers, (0.025) = 0.050
Total length = 3.123

No of steel, Y10-225

Length = 3.048
(-) 2 half beam= 2(0.125/2) = 0.125
Length required steel = 2.923

No. of steel = (length req. steel / spacing) +1

(2923 / 300) + 1 = 10.743


≈ 11
2/11/
3.123
68.706
68.706 m Y10-225 m

Reinforcement bar on bottom :


(y-direction Y10-225)

Length = 3.048
(+) 2 half beam= 2(0.125/2) = 0.125
(-) 2covers, (0.025) = 0.050
Total length = 3.123

No of steel, Y10-225

Length = 3.048
(-) 2 half beam= 2(0.125/2) = 0.125
Length required steel = 2.923

No. of steel = (length req. steel / spacing) +1

(2923 / 300) + 1 = 10.743


≈ 11
2/11/
3.123
68.706
68.706 m Y10-225 m
FIRST FLOOR SLAB: FS3 (Section 1-1)

TIME DIM QTT DESCRIPTION UNIT


SING

Lyy = 4.267
Lxx = 3.048
Thickness = 0.125

CONCRETE

Length Lyy = 4.267


(-) 2 half beam= 2(0.125/2)= 0.125
4.142

Length Lxx = 3.048


(-) 2 half beam= 2(0.125/2)= 0.125
2.923
1/ 4.142
2.923
0.125
1.513 1.513 m3 concrete grade 25 m³

FORMWORK
Soffit

1/ 4.142 ly = 4.142
2.923 lx = 2.923
12.107 m2
Length,Lyy = 4.267
(-) 2 half beam= 2(0.125/2) = 0.125
4.142
Length,Lxx = 3.048
(-) 2 half beam= 2(0.125/2) = 0.125
2.923
REINFORCEMENT

Reinforcement
(y-directionbar
Y10support
– 200)on right top:

Length = 1.100
(+) half beam = (0.125/2) = 0.063
(+) bend = 5.5 (0.01) = 0.055
(-) covers, (0.025) = 0.025
Total length = 1.193

Number of bar,Y10-200

Length, = 1.100
(-) 2 half beam= 2(0.125/2) = 0.125
Length required steel = 0.975

No. of steel = (length req. steel / spacing) +1

(975 / 200) + 1 = 5.875


≈6
1/6/
1.193
7.158
7.158m Y10-200 m

Reinforcement bar support on left top:


(y-direction Y10 – 200)

Length = 1.100
(+) half beam = (0.125/2) = 0.063
(-) covers, (0.025) = 0.025
Total length = 1.138

No. of steel, Y10 – 200

Length,Lxx = 1.100
(-) 2 half beam= 2(0.125/2) = 0.125
Total length = 0.975

(975 / 200) + 1 = 5.875


≈6
1/6/ 1.138
6.828 6.828m 0f Y10-200 m
Reinforcement bar support on top:
(x-direction Y10 – 300)

Length = 1.100
(+) half beam = (0.125/2) = 0.063
(+) bend = 5.5 (0.01) = 0.055
(-) covers, (0.025) = 0.025
Total length = 1.193

No. of steel, Y10 – 300

length = 1.100
(-) 2 half beam =2 (0.125/2) = 0 0.125
Total length = 0.975

(975 / 300) + 1 = 4.250


2/4/ 1.193 ≈4
9.544
9.544m 0f Y10-300 m

Reinforcement bar bottom:


(x-direction Y10 – 200)

Length = 3.048
(+)2 half beam = 2(0.125/2) =0. 0.125
(+) bend = 2 x 5.5 (0.01) = 0.11
(-) 2 covers, 2 (0.025) = 0.05
Total length = 3.233

No. of steel, Y10 – 200

length = 4.267
(-) 2 half beam =2 (0.125/2) = 0 0.125
Total length = 4.142

(4142 / 200) + 1 = 21.710


≈ 22
1/22/ 3.233
71.126 71.126m 0f Y10-200 m
Reinforcement bar bottom
(y-direction Y10 – 200)

Length = 4.267
(+)2 half beam = 2(0.125/2) =0. 0.125
(+)2 bend = 2 x 5.5 (0.01) = 0.11
(-) 2 covers, 2 (0.025) = 0.05
Total length = 4.452

No. of steel, Y10 – 200

length = 3.048
(-) 2 half beam =2 (0.125/2) = 0 0.125
Total length = 2.923

(2923 / 200) + 1 = 15.62


≈ 16
1/16/ 4.452
71.232 71.232m 0f Y10-200 m
FIRST FLOOR SLAB: FS4 (Section 4-4)

TIME DIM QTT DESCRIPTION UNIT


SING

Lyy = 5.486
Lxx = 4.191
Thickness = 0.175

CONCRETE

Length Lyy = 5.486


(-) 2 half beam= 2(0.125/2)= 0.125
5.361

Length Lxx = 4.191


(-) 2 half beam= 2(0.125/2)= 0.125
4.066
1/ 5.361
4.066
0.175
3.815 3.815 m3 concrete grade 25 m³

FORMWORK

1/ 5.361 ly = 5.361
4.066 lx = 4.066
21.798 m2
Length,Lyy = 5.486
(-) 2 half beam= 2(0.125/2) = 0.125
5.361
Length,Lxx = 4.191
(-) 2 half beam= 2(0.125/2) = 0.125
4.066
REINFORCEMENT

Reinforcement
(y-direction bar
Y10support
– 300)on top:

Length = 1.050
(+) half beam = (0.125/2) = 0.063
(-) covers, (0.025) = 0.025
Total length = 1.088

Number of bar,Y10-300

Length, = 1.050
(-) 2 half beam= 2(0.125/2) = 0.125
Length required steel = 0.925

No. of steel = (length req. steel / spacing) +1

(925 / 300) + 1 = 4.083


≈4
2/4/
1.088
8.704
8.704m Y10-300 m

Reinforcement bar support on top:


(x-direction Y10 – 175)

Length = 1.050
(+) half beam = (0.125/2) = 0.063
(-) covers, (0.025) = 0.025
Total length = 1.088

No. of steel, Y10 – 175

length = 1.050
(-) 2 half beam =2 (0.125/2) = 0 0.125
Total length = 0.925

(925 / 175) + 1 = 6.286


2/6/ 1.088 ≈6
13.056
13.056m 0f Y10-175 m
Reinforcement bar bottom:
(x-direction Y10 – 175)

Length = 4.191
(+)2 half beam = 2(0.125/2) =0. 0.125
(+)2bend = 2 x 5.5 (0.01) = 0.11
(-) 2covers, 2(0.025) = 0.05
Total length = 4.376

No. of steel, Y10 – 175

length = 5.486
(-) 2 half beam =2 (0.125/2) = 0 0.125
Total length = 5.361

(5361 / 175) + 1 = 31.634


≈ 32
1/32/ 4.376
140.032 140.032m 0f Y10-175 m

Reinforcement bar bottom


(y-direction Y10 – 200)

Length = 5.486
(+)2 half beam = 2(0.125/2) =0. 0.125
(+)2bend = 2 x 5.5 (0.01) = 0.11
(-) 2covers, 2(0.025) = 0.05
Total length = 5.671

No. of steel, Y10 – 200

length = 4.191
(-) 2 half beam =2 (0.125/2) = 0 0.125
Total length = 4.066

(4066 / 175) + 1 = 24.234


≈ 24
1/24/ 5.671
136.104 136.104m 0f Y10-175 m
ROOF SLAB: RS2 (Section 6-6)

TIME DIM QTT DESCRIPTION UNIT


SING

Y10-225c/c Lxx =

Y10-225c/c
1.905m

Lyy= 2.742m

Lyy = 2.742
Lxx = 1.905
Thickness = 0.100

CONCRETE

Length Lyy = 2.742


(-) 2 half beam= 2(0.125/2)= 0.125
2.617

Length Lxx = 1.905


(-) 2 half beam= 2(0.125/2)= 0.125
1.780
1/ 2.617
1.780
0.100
0.466 0.466 m3 concrete grade 25 m³
REINFORCEMENT

Reinforcement bar support on top right and left:


(Y-direction Y10 – 225)
Length = 0.700
(+) half beam = (0.125/2) = 0.063
(+) 2bend = 2x5.5 (0.01) = 0.110
(-) covers, (0.025) = 0.025
Total length = 0.848

Number of bar,Y10-225

Length, = 0.700
(-) half beam= (0.125/2) = 0.063
Length required steel = 0.638

No. of steel = (length req. steel / spacing) +1

(2.617/0.225) + 1 = 3.833
≈4
2/4/
0.848
6.784
6.784m Y10-225 m

Reinforcement bar support on top right and left:


(X-direction Y10 – 225)
Length = 0.700
(+) half beam = (0.125/2) = 0.063
(+) 2bend = 2x5.5 (0.01) = 0.110
(-) covers, (0.025) = 0.025
Total length = 0.848
Number of bar,Y10-225

Length (0.700) = 0.700


(-) half beam= (0.125/2) = 0.063
Length required steel = 0.638

No. of steel = (length req. steel / spacing) +1

(0.638/0.225) + 1 = 3.833
≈4
2/4/
0.848
6.784
6.784m Y10-225 m

Reinforcement Bar Bottom Y-direction-(Y10)

Length,Lyy = 2.742
(+) 2 half beam= 2(0.125/2) = 0.125
(+) 2 bend = 2 x 5.5 (0.01) = 0.100
(-) 2 covers, 2(0.025) = 0.050
Total length of one Y10 = 2.917

Number of bar,Y10

Length,Lxx = 1.905
(-) 2 half beam= 2(0.125/2) = 0.125
Length required steel = 1.780

No. of steel = (length req. steel / spacing) +1

(1.780 / 0.225) + 1 = 8.911


≈9
1/9/
2.917
26.253
26.253m Y10 m
Reinforcement Bar Bottom X-direction-(Y10)

Length,Lxx = 1.905
(+) 2 half beam= 2(0.125/2) = 0.125
(+) 2 bend = 2 x 5.5 (0.01) = 0.100
(-) 2 covers, 2(0.025) = 0.050
Total length of one Y10 = 2.080

Number of bar,Y10

Length,Lyy = 2.742
(-) 2 half beam= 2(0.125/2) = 0.125
Length required steel = 2.617

No. of steel = (length req. steel / spacing) +1

(2.617 / 0.225) + 1 = 12.631


≈ 13
1/13/
2.080
27.040
27.040m Y10 m

FORMWORK
Soffit

ly = 2.617
lx = 1.780

Length,Lyy = 2.742
(-) 2 half beam= 2(0.125/2) = 0.125
2.617
Length,Lxx = 1.905
1/ (-) 2 half beam= 2(0.125/2) = 0.125
1.780 1.780
2.617
4.658 4.658m2 sawn timber 38mm thickness m²
ROOF SLAB: RS1 (Section 7-7)

TIME DIM QTT DESCRIPTION UNIT


SING

Lyy = 3.658
Lxx = 1.190
Thickness = 0.100

CONCRETE

Length Lyy = 3.658


(-) 2 half beam= 2(0.125/2)= 0.125
3.533

Length Lxx = 1.190


(-) 2 half beam= 2(0.125/2)= 0.125
1.065
1/ 3.533
1.065
0.100
0.376 0.376 m3 concrete grade 25 m³

FORMWORK
Soffit

ly = 3.533
1/ 3.533 lx = 1.065
1.065
3.763 Length,Lyy = 3.658 m2
(-) 2 half beam= 2(0.125/2) = 0.125
3.533
Length,Lxx = 1.190
(-) 2 half beam= 2(0.125/2) = 0.125
1.065
REINFORCEMENT

Reinforcement
(y-direction bar
Y10support
– 300)on top:

Length = 0.450
(+) half beam = (0.125/2) = 0.063
(+) bend = 5.5 (0.01) = 0.055
(-) covers, (0.025) = 0.025
Total length = 0.543

Number of bar,Y10-300

Length = 0.450
(-) 2 half beam= 2(0.125/2) = 0.125
Length required steel = 0.325

No. of steel = (length req. steel / spacing) +1

(325 / 300) + 1 = 2.083


≈2
2/2/
0.543
2.172
2.172m Y10-300 m

Reinforcement bar support on top:


(x-direction Y10 – 225)

Length = 0.450
(+) half beam = (0.125/2) = 0.063
(+) bend = 5.5 (0.01) = 0.055
(-) covers, (0.025) = 0.025
Total length = 0.543

No. of steel, Y10 – 225

length = 0.450
(-) 2 half beam =2 (0.125/2) = 0 0.125
Total length = 0.325

(325 / 225) + 1 = 2.444


2/2/ 0.543 ≈2
2.172
2.172m 0f Y10-225 m
Reinforcement bar bottom:
(x-direction Y10 – 225)

Length = 1.190
(+)2 half beam = 2(0.125/2) =0. 0.125
(+) 2 bend = 2 x 5.5 (0.01) = 0.110
(-)2 covers, 2(0.025) = 0.050
Total length = 1.375

No. of steel, Y10 – 225

length = 3.658
(-) 2 half beam =2 (0.125/2) = 0 0.125
Total length = 3.533

(3533 / 225) + 1 = 16.702


≈ 17
1/17/ 1.375
23.375 23.375m 0f Y10-225 m

Reinforcement bar bottom


(y-direction Y10 – 300)

Length = 3.658
(+)2 half beam = 2(0.125/2) =0. 0.125
(+) 2 bend = 2 x 5.5 (0.01) = 0.110
(-)2 covers, 2(0.025) = 0.050
Total length = 3.843

No. of steel, Y10 – 300

length = 1.190
(-) 2 half beam =2 (0.125/2) = 0 0.125
Total length = 1.065

(1065 / 300) + 1 = 4.550


≈5
1/5/ 3.843
19.215 19.215m 0f Y10-200 m