Professional Documents
Culture Documents
MBA-7001-20169108-68 Marks
MBA-7001-20169108-68 Marks
Declaration
I certify that the attached material is my original work. No other person’s work or ideas have been used without
acknowledgement. Except where I have clearly stated that I have used some of this material elsewhere, I have not
presented it for examination / assessment in any other course or unit at this or any other institution
Marks by 1st Assessor Name & Signature of the 1st Assessor Agreed Mark
Strengths
Weaknesses
Comments by the IV
List of Figures
Figure 1 – Gantt Chart Snap (As preview) .................................................................... 14
Figure 2 – Project Milestones snapshot ........................................................................ 17
Figure 3 – Project Change Request Form ..................................................................... 19
Figure 4 - Formal Communication procedure for Project Changes ............................... 20
Figure 5 – Milestone Summary after project Scope Change ......................................... 21
Figure 6 – Difference between Waterfall and Agile/Scrum ............................................ 22
Figure 7 – Agile/Scrum Project Flow ............................................................................. 22
1. Business Case
At the current practice of mold operations in ETD (Manufacturing plant of Camso
Loadstar)
➢ Higher manhour requirement for mold delivery process. Monthly average of 1250
manhours consumed in the last 12 months.
➢ Missing of hard copies of the document and less tractability of records.
➢ Improper last piece data considering in mold releasing a caused average of 50
defect mold deliveries to production. (4% defective mold deliveries)
2. Project Description
Develop software to digitalize the mold quality approval documents in mold delivering to
production both 1st tire approval and last tire approval.
Combine all data available in the SAP system with new software and prepare a common
platform to visualize data.
Install new digital display in the Mold operation department and provide easy access to
track all mold-related data including last tire inspection record, mold volume, and mold
quality information. This allows selecting mold suitable mold for the production plan
within a few seconds.
This system records all historical data and provides 100% tractability.
3. Project Goal(s)
4. Project Milestones
Target Date
Milestone Description
(YYYY-MM-DD)
Blueprint 2021-01-04
5. Project Risks
➢ Incompatibility of software with SAP system
➢ The software is not user friendly (Stakeholder rejection)
➢ Material delivery delay (Schedule delay – Smart TV)
6. Project Stakeholders
This is an operations improvement project and time is not a critical factor for the project.
Cost is a moderate critical factor for the project as the budget amount is allocated at the
beginning of the financial year but 10% of budget exceeding is already authorized. The
scope is very critical as this is software development for a defined operation process.
Whatever changes to the scope must be reviewed by a few departments and officials as
its effects on the other operational activities and operational compliance.
If the change is a minor change Project manager and stakeholders have the authority to
manage the change on their territory. If it is identified as a major risk plant management
or Exco (Business Unit management) involvement and guidance must be required.
Requested by : Date :
Change Analysis
Impact on deliverables :
Impact on schedule :
Impact on risks :
Impact on resources :
Other impacts :
Resource Changes: - Additional 5 working days for networking and 25meters of network
cables added resources apart from a smart TV.
As per the above milestone summary, scope change does not impact the schedule as a
networking activity is a non-critical path activity. But the cost has been increased to Rs.
3,431,620.00 which is 17% increment compared to previous cost (Rs.2,932,870.00).
As per the formal communication procedure of project change management, this change
must be forwarded to pant management. Then Plant Director will decide whether this can
be approved, revised, or escalate to the Exco level.
But the agile methodology is more flexible, and it is delivered results step by step. Every
sprint delivers a part of the project and complete project results are some of the sprint
deliverables where waterfall delivered the total package at once.
Daily scrum meeting is the main communication forum inside the sprint and in the end,
the sprint retrospective is a lesson learn forum for the next sprint. (Agile project
management with Scrum, 2020
Product Backlog
The Team
➢ Scrum Master – Senior Project Engineer (PMP qualified and certified Scrum
master)
➢ Mold Maintenance Senior Engineer
➢ Application Project Consultant
➢ IT Advisor
➢ Quality Assurance Engineer
➢ Patrol QC
Sprint Schedule
Sprint
No. Deliverable Activities Duration Communication
Design software 1. Daily Scrum meeting
Last Tire Development (Daily 15 minutes).
Sprint Inspection Simulation 2. Sprint Review (End of the
1 Sheet Compatibility 3 weeks sprint 1 hour).
(Digitalized) analysis 3. Sprint Retrospective (End
Approval of the sprint 1 hour).
Design software 1. Daily Scrum meeting (Daily
1st Tire Development 15 minutes).
Sprint Inspection Simulation 2. Sprint Review (End of the
3 weeks sprint 1 hour).
2 Sheet Compatibility
(Digitalized) analysis 3. Sprint Retrospective (End
Approval of the sprint 1 hour).
Sprint Design Interface 1. Daily Scrum meeting (Daily
2 weeks
3 Development 15 minutes).
10. References