Professional Documents
Culture Documents
Guidance On The Protection of Land Under The PPC Regime
Guidance On The Protection of Land Under The PPC Regime
Guidance On The Protection of Land Under The PPC Regime
IPPC H7
Guidance on the
PPC Regime:
Programme
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
CONTENTS Page
BACKGROUND
1.0 Introduction 1
4.1 Introduction 8
5.1 I ntroduction 29
5.2.1 Introduction
5.2.2 Review Conceptual Site Model
5.2.3 Designing Intrusive Investigations To Collect Reference Data
5.3.1 Introduction
5.3.2 Designing the Environmental Monitoring Programme
5.3.2.1 Define Objectives
5.3.2.2 Designing the Environmental Monitoring Infrastructure
5.3.2.3 Designing the Environmental Monitoring Schedules and
Protocols
5.3.3 Designing the Infrastructure Monitoring Programme
Reporting Programme 37
6.1 Introduction
39
6.2 Step 1 – Implementing the First Phase of the Site Protection and
6.3 Step 2 – Implementing the Remaining Part of the Site Protection and
Monitoring Programme 40
References 42
Appendices
Figures
Figure 1 Summary of the Key Stages of the Protection of Land through PPC
Figure 2 Assessing the Likelihood of Pollution
Figure 3 Development and Implementation of the Site Protection and Monitoring
Programme
Tables
Boxes
BACKGROUND
1. Introduction
This technical guidance supports the Environment and Heritage Service (EHS) policy on the
requirements for site reports in the PPC regime. The policy is designed to improve the overall
level of protection of the land on a PPC site and protect it from degradation.
A site report is required to be submitted as part of a Permit application (Application Site Report
or ASR) to operate a Part A installation under the PPC regime. The principal objective of the
ASR is to provide information on the ground conditions of the site to enable the EHS to set
appropriate conditions to protect the land. These conditions may include a requirement on the
Operator to submit a Site Protection and Monitoring Programme (SPMP). In addition the report
will be essential at Permit surrender in the establishment of restoration requirements.
This approach applies to all sites that fall into the PPC regime including new and existing
installations, with the exception stated below.
This guidance is not applicable to areas of a landfill installation which form the stationary
technical unit for the landfill activity. However, there may be directly associated activities
included in the installation. For all the areas of the landfill installation which do not consist of
permanent deposits of waste forming part of the stationary technical unit, the requirements of
this guidance do apply.
Guidance on the surrender of existing specified waste management activities and for landfill will
be provided by the Waste and Contaminated Land Unit of the EHS in due course.
1
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
This guidance has been produced to provide an indication to Applicants of the EHS
requirements for an ASR and, if required, an SPMP. It is not intended to be a substitute for the
use of or advice from suitably qualified and competent professionals or the PPC Regulations
themselves.
Purpose
Where this guidance refers to an “installation” this means both a Part A Installation and also a
Part A Mobile Plant where regulated by the EHS.
To support this guidance reporting templates are available to help Applicants and Operators
with the submission of the correct information in a suitable format to the EHS. The templates
are:
H7 Reporting Template 1 –
H7 Reporting Template 2 –
H7 Reporting Template 3 –
Design of a Site Protection and Monitoring Programme for Installations that DO NOT
H7 Reporting Template 4 –
First Phase Reporting of the Site Protection and Monitoring Programme for Installations
H7 Reporting Template 5 –
First Phase Reporting of the Site Protection and Monitoring Programme for Installations
Direct cross referencing to the applicable sections in the relevant template is provided in each
section of this guidance.
2
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
The framework for the protection of land under PPC is illustrated in Figure 1. This demonstrates
the actions required at pre- and post-Permit determination stages and the link to eventual
Permit surrender. All these stages are described in more detail in the following section.
Figure 3 illustrates the key decision points and data collection requirements during the
preparation of the ASR and the SPMP.
Much of the information on substances used and pollution prevention measures at the
installation will be required elsewhere in the PPC Permit application. The Applicant is not
required to repeat any data collection exercise and should cross reference documents provided
in other parts of the application wherever possible.
The key objectives of the Application Site Report are to collect and collate (normally) desk
based information on the activities and substances used at the installation that could present a
pollution risk to the land now or in the future.
b) Identify any substance in, on or under the land that could have arisen from materials
currently used or produced by the activities under the Permit (or are likely to be used or
produced in the future).
d) Be sufficient to form the basis of the Operator’s Site Protection and Monitoring
Programme of impact to land to be conducted during the life of the Permit.
The EHS will not normally require intrusive site investigations to be undertaken before it
determines an application provided that a)-d) above are satisfied. However the Applicant must
state within the ASR whether there is either:
• little likelihood that pollution or leaks to land will occur during the future life of the
installation.
or there is:
• a reasonable possibility of current or future pollution of the land from the installation.
The EHS will review the information provided in the ASR and assess whether it agrees with the
assessment of the likelihood of pollution. The EHS will consider the case the Applicant has
− the quality, engineering and maintenance of tanks, pipework and other items which could
give rise to pollution and the associated control measures such as bunds;
− the testing, monitoring and maintenance procedures in place; and
− the quality of operator management and competence, including past record of incidents,
non-compliance and enforcement action.
The EHS will use this assessment in deciding whether to apply Permit conditions requiring the
collection of Reference Data as part of the SPMP. Reference Data are defined in detail in
Appendix A but will normally involve the collection and analysis of soil and groundwater
samples and reporting of contaminant concentrations in the land.
3
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
As noted above intrusive investigations would not normally be required at the application stage.
However, in certain situations it may be the case that the site’s environmental setting cannot be
established adequately and intrusive investigations will be necessary, the results of which
should be reported in the ASR. For example where desk study information is inadequate or of
such poor quality that the site’s condition cannot be described. Further details on this issue are
provided in Box 2.
The Permit will normally have conditions requiring the Operator to implement a SPMP to
ensure the protection of the land throughout the lifetime of the installation this will be
undertaken in the following phases:
Six Months after Permit Issue - where Reference Data is required the reporting of these
results to the EHS
During the life of the installation - collection and reporting of data in accordance with the
SPMP
The detail and scope of the required SPMP will be based on the assessment of pollution
prevention measures undertaken in the ASR and will be proportionate to the risks posed by the
installation.
• little likelihood that pollution or leaks to land will occur during the future life of the
installation.
The SPMP will only require a testing, inspection and maintenance programme to ensure that
the site’s pollution prevention measures are maintained and continue to be effective.
However, where this case has not been made by the Applicant, or the EHS disagrees with the
Applicants assessment, and it is considered that there is:
• a reasonable possibility of current or future pollution of the land from the installation.
then the required SPMP will need to be far broader in its scope and, in addition, must include
the collection of Reference Data and where the potential for ongoing pollution has not been
removed the undertaking of long term environmental monitoring.
An example of the scope of an SPMP where there is a reasonable possibility that there is a
potential for current or future pollution is provided in Box 1.
4
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Figure 1 Summary of the Key Stages of the Protection of Land through PPC
PERMIT ISSUED
PERMIT
SUBSISTENCE • Design monitoring programme to
ensure pollution prevention
measures are effective
PERMIT
SURRENDER
Permit Surrender
Report
5
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Box 1
An installation includes a series of activities that produce liquid effluents that are transferred to an on-
site treatment plant (prior to discharge to foul sewer) via a below ground effluent system. The
drainage system consists of brick lined catch pits drained by single-butted clay pipes which in turn
connect to a main brick-lined conduit to the treatment plant. The system is gravity drained.
The installation lies within a river valley and is underlain by 2 to 4 meters of alluvial gravel overlying
low permeability clays. A shallow water table exists within the gravel perched upon the clay.
A CCTV survey is conducted as part of the investigations to collect Reference Data which does not
identify any major breaks in the drainage system. However due to its age and construction its integrity
cannot be assured. Replacing the drainage system along with improved effluent treatment and reuse
within the activities have been identified as improvement conditions. Due to high capital costs and
major disruption to operations this work is to be phased in over a number of years.
The SPMP should include investigations of groundwater quality beneath and down groundwater
gradient of the drainage system to collect Reference Data for those polluting substances in the
effluent. Proposals to monitor groundwater quality during the life of the installation should be included
in the SPMP until such time that the system is replaced and testing and inspection procedures are
developed and implemented to demonstrate its continued integrity.
Conditions may require that within two months after the Permit has been issued the Operator
must submit to the EHS a design document of the required SPMP.
The purpose of the SPMP is to demonstrate that the pollution prevention measures designed to
protect the land at the site are effective throughout the life of the installation.
If there is a reasonable possibility of pollution, which will be established before the Permit is
determined, then the first stage of the SPMP must establish Reference Data for substances in
use or produced or likely to be in the future at the installation that could be emitted to land or
groundwater.
Intrusive sampling may form part of the SPMP and will always be required where there are:
• bulk storage facilities for liquid chemicals or other potentially polluting substances; and
• no preventative measures e.g. lack of hard standing or use of sub-surface pipework for
transport of substances; or
• inadequate preventative measures e.g. cracked or inappropriately maintained hard
standing or bunding or where the delivery pipework or valves are located outside of such
bunding; or
• a history of pollution incidents or spillages at the site; or
• no, or in adequate, proposals to conduct integrity testing of preventative measures.
Such sampling would not normally be necessary as part of the SPMP at installations where it
can be demonstrated that there is little likelihood of pollution. To achieve this the following
criteria must be met:
• adequate preventative measures are in place e.g. above ground pipework or other
equipment, the leakage from which could lead to pollution, is over an impermeable
6
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
surface, bunded and surfaced in accordance with the standards set out in general sector
guidance and, where available, sector specific guidance; and
• integrity testing continues to demonstrate that the preventative measures are intact; and
• the site does not have a history of pollution incidents or spillages; and
• adequate management systems are in place.
At installations that require Reference Data to be collected these results must be submitted to
the EHS within six months from the date of Permit issue. At installations where Reference Data
does not need to be collected the undertaking and reporting of monitoring will be set out in the
SPMP. The submitted results and implemented SPMP must meet the requirements as laid out
in this guidance and relevant reporting template.
The SPMP will normally require the Operator to continually monitor the site during the life of the
Permit to assess the continued effectiveness of the pollution prevention measures. This could
be via the collection and analysis of samples and/or the inspection of site infrastructure.
Monitoring will require the review and assessment of data and if it indicates that a pollution
incident has or is occurring the Operator will be required to undertake remediation. Further
details on what would be required in these situations is provided in Appendix C.
7
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
4.1 Introduction
• Desk based review of all available reports, site plans, operational records, material
inventories, records of pollution incidents, etc.
• Site reconnaissance (or walk over) to make site based observations;
• Assessment of the adequacy of pollution prevention measures;
• Reporting.
The completion of these activities will need to be undertaken in the following steps:
Step 1 – Site Environmental Setting and Pollution History – collection of information about
the environmental setting and history of any land or groundwater pollution at the site of the
installation.
Step 2 – Identify Potentially Polluting Substances – identify the areas where potentially
polluting substances are to be used, produced or stored. Where are the potential “emission”
points? Identify what substances could already be in the land from past pollution events or
activities (analysis and concentrations of contaminants is not normally required).
Step 3 – Identify Preventative Measures – for all the potential emission points what pollution
prevention measures are in place.
Step 4 – Assessment of Pollution Prevention Measures – for all the emission points assess
whether the pollution prevention measures are adequate to protect the land from pollution.
Step 5 – Development of Conceptual Site Model – using the information gathered in the
earlier steps construct a Conceptual Site Model of the site’s environmental setting and potential
for pollution. This model will be an important reporting tool and will be essential when
designing and implementing any subsequent SPMP.
Further details on the requirements of each stage are outlined in the following sections of this
guidance and direct cross reference to the applicable sections in the ASR Template are also
provided.
8
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Key Task
The first stage in the process of preparing an ASR is to collect existing information about the
site, the site reconnaissance or site walk over should also form part of this activity and Table 1
outlines examples of what information is required.
This information is required to start the understanding of the condition of the site and will be
essential in the production of the Conceptual Site Model (CSM) and the design of any
subsequent monitoring programmes to ensure that they are as efficient and effective as
possible.
Information Requirements
− Historical uses of the site that could present a potential source of land contamination
− Authorisations for Part A and B prescribed processes on site or in surrounding area
− Waste management licences on site or in surrounding area
− Local geology (drift and solid)
− Local surface water and groundwater hydrology and surface/groundwater water quality, pollution
− History of pollution incidents to land or groundwater
− Surface water and groundwater catchment and source protection zones, groundwater vulnerability
− Water abstraction details
− Topography
− Proximity of protected or “sensitive” habitats or species
− Existing site investigation, assessment and remediation records if available
− Details of the operation of the proposed installation, including review of chemical inventory for the
installation
− Existing operational records, environmental audit etc. (for installations which are already operating)
− Emergency response records (e.g. explosion, fire, spillages etc.)
− Effluent discharge consents / trade effluent agreements
− Access arrangements
− Site layout including presence and condition of above and below-ground buildings/structures etc.
− Evidence of disturbed land, discoloured soil or water, subsidence, above ground deposits etc.
− Vegetation type and signs of distress or absence where it might be expected
− Significant odours from the land
− Liquid discharges from the site
− Direction and flow of surface water run-off and presence of ponding
− Land uses in the vicinity of the site
− Presence and condition of surface water features
− Evidence of any accidental/uncontrolled releases at the site (previous or current)
− Identify potential access constraints e.g. overhead cables, location of machinery, operations at the
site.
9
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Completion of this stage will be achieved by the collection of desk based information and the
EHS will not normally require intrusive site investigations before determining the application.
However, there may be cases where the desk study information is incomplete or particularly
poor and intrusive investigations would be required prior to the Permit being issued. The
Applicant will need to consider whether an intrusive investigation is required to support the data
collected via the desk study. Situations where intrusive investigations may be required is
presented in Box 2.
References 6 to 10 provide further technical guidance on undertaking a desk study and site
reconnaissance.
Applicants may of course collect intrusive site investigation data for their own purposes and the
EHS would not wish to restrict this activity, provided that it was carried out in an appropriate
manner.
Box 2
Situations where intrusive investigations would be required as part of the Permit application
It is considered extremely unlikely that intrusive investigations would be required before a Permit is
determined as long as an Applicant can adequately describe the condition of the site with desk
based information. However, there may be exceptional cases where this is not the case, an
example could be the lack of important geological information that without it other relevant permit
conditions to prevent pollution cannot be identified.
It is expected that in the majority of cases information from the British Geological Survey (BGS)
would be adequate to describe the geology of a site. However, where:
• This data is insufficient or not available from BGS or other sources; and
• The actual geology at the site would significantly effect the impact of a pollution incident due to:
- the differing mobility of contaminants in different geological strata; and
- the particular circumstances at the site, large volume and type of substances stored
produced or used.
then it is likely that the Applicant would need to undertake intrusive investigations to fully understand
the site's environmental setting.
It is important to remember that data collected during other site investigation works for other
purposes, such as geo-technical design, may be used in the ASR.
3.0 Site Setting and Sources of Desk Introduces the sources of information used in the
Based Research Information report.
4.0 Site Reconnaissance Outlines the findings of the site reconnaissance or
walk over.
6.1 Geology and Hydrogeology Presents and interprets the detailed findings of the
6.2 Surface Water Feature desk based research and site reconnaissance
6.3 Results of Previous Investigations using a Conceptual Site Model.
6.4 Other Receptors
6.5 Pollution History
6.6 Site Zoning
10
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Key Task
• Identify any substance in, on or under the land which may constitute a pollution risk
The Applicant needs to identify all the substances at the installation that, if released to land, have
the potential to pollute soil and groundwater. Whether alone or in combination with other
substances already in the land or groundwater. This could be as a result of spills, leaks, failure of
tanks or pipe lines or deliberate discharges.
Substances may include raw materials, fuels, intermediates, products, wastes and effluents. In
addition, the Applicant needs to identify substances that are used or produced at the installation
that may have already polluted the land. However no quantification is required at this stage.
Pollution potential will be determined not only by the volume and manner in which a substance is
stored but also the chemical properties of that substance. Therefore it is important that the
Applicant considers the toxicity, environmental fate, behaviour and transport characteristics of
each substance.
The Applicant should therefore confirm what substances are used or produced at the installation,
including volume, noting where they are stored or used, what activity they are used in, key
environmental properties and whether, if released, they would pollute land or groundwater.
Substances that have similar environmental behaviour and/or toxicity may be grouped together.
The Applicant will also need to identify potentially polluting substances that may already be in the
land as a result of past activities or use of the site. This historic information will be gathered
during the desk study exercise in Step 1.
Information on the past uses of a site can often be found on old ordnance survey maps or other
historic records. Lists of potentially polluting substances associated with different types of
industry can be found in the DoE Industry Profiles series, ref 10. This information should be
presented in tabular form clearly illustrating the possible contamination at the site. The applicant
is not required to quantify historic contaminants in the ground, rather all that is expected is a desk
based assessment/identification of potential historic pollutants in order to describe the condition
of the site of the installation.
The Applicant must also consider how to split the site of the installation into zones. This will
assist the later stages of the process enabling targeted and effective (ie risk based) monitoring
and sampling. Zoning should be based on the identification of “emission points” of where
substances are stored, transported, produced or handled. Site zones must be illustrated on a
suitable drawing included in the ASR. Further explanation of site zoning is provided in Box 3.
Reference concentrations will need to be set only for those zones where it has been
demonstrated that there is a reasonable possibility of pollution.
Sources of information should be referenced and detailed information should be included in the
appendices of the ASR.
The Applicant may have undertaken intrusive surveys previously and may include such
information as part of a site report if they are relevant. However, the Applicant is not obliged to
include the results of previous intrusive surveys as a part of the ASR . The findings of this step
will need to be fed into the assessment of the pollution prevention measure as outlined in Step 4
Section 4.5.
11
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Key Task
• For all the potential emission points identify what pollution prevention measures are in place to
protect the land.
For each of the operational activities (that could result in pollution of the land ie “emission
points”) and associated substances the Applicant needs to identify and record what pollution
prevention measures are in place to protect soil and groundwater
The principal means of pollution prevention is the careful handling and storage of potentially
polluting substances. In the majority of cases for the protection of land this is determined by
the level of containment of a particular substance, ie spill prevention. Three levels of
containment can be considered and will need to be identified:
• Primary : For example, a drum, vessel, pipe, bag, etc. containing the substance
• Secondary : For example, a bund, double wall vessel or pipe, vent pipe, catch-pit, etc.
designed to retain the substance in the event of a failure of primary containment.
• Tertiary : Additional measures provided to contain a spillage (e.g. an oil interceptor in a
surface water drain, a concrete hardstanding for road-tankers offloading to a bulk storage
tank, etc.).
The findings of this step will need to be fed into the assessment of the pollution prevention
measures as outlined in Step 3 Section 4.5.
12
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Box 3
Zoning of a site
The Applicant will need to split the site into zones to assist in the assessment of whether there is a
reasonable possibility of pollution and, where required subsequently, with the design of any intrusive
investigations required to collect Reference Data. Zoning a site allows for a targeted and risk based
approach to be adopted and is based on two factors:
To split a site into zones the Applicant must first determine what are the sites “relevant systems” that
could contain contaminant sources, and for each system whether there are smaller “relevant
activities” that should be considered separately. The division of the site into these component parts is
essential when the Applicant assesses the effectiveness of pollution prevention measures.
Within this site operation there are a number of “Relevant Activities” that could be considered to be
potential “emission” points of the potentially polluting substance should there be a failure of
containment or spill.
In the example of the Factory Heating System the Relevant Activities could be:
The Applicant will need to assess the likelihood of pollution as outlined in Section 4.5 for each of the
Relevant Activities at the site. Tables 2A and 2B illustrates how the splitting of the site fits into this
assessment process.
After completing the assessment of the effectiveness of pollution prevention measures the Applicant
will have determined which parts of the site represent potential emission points to land (where there is
reasonable possibility of pollution occurring) and will be required to collect reference concentrations.
13
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
To complete the zoning of the site the Applicant must set a spatial zone around each of the potential
emission points for which reference levels, will be set. The size and shape of this zone will be based on
the extent to which a pollutant can spread away from the emission point and is a function of:
The schematic drawings below show how a site zone is developed. Drawing 1 shows the relevant
system with its relevant activities and results of the pollution prevention assessment. This information is
superimposed on to data of the site’s geology and hydrogeology. Based on the pollution prevention
assessment, properties of the potential pollutants and site environmental setting the Applicant has
defined the extent of zones around each potential emission point, Drawing 2.
Reference concentrations will be required to be set for each of the defined zones. Note also that zones
can overlap.
Drawing 1
Schematic Plan of a Relevant System, Assessment Results and Information on Site
Environmental Setting Required to Develop Appropriate Site Zones.
Information on differing underlying geology and groundwater flow direction and depth is also indicated on
the plan.
River Gravels
Clay
Relevant Activity: Pipeline Pipeline
Assessment: Reasonable
Possibility of Pollution
Reference Data Required
14
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Drawing 2
Schematic Site Plan Illustrating Appropriate Site Zones
Information on differing underlying geology and groundwater flow direction and depth is also
indicated on the plan.
Zone A
Tank
River Gravels
Zone B
Clay
Pipeline
Zone C
Boiler
15
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Key Task
• Assess the effectiveness of the pollution prevention measures and provide a statement of the
likelihood of pollution of the land.
The objective of this stage is to bring together all the data collected to enable an assessment to
be made on the potential for land pollution from the activities at the installation. For each
relevant activity at the installation the Applicant will need to assess whether:
• There is little likelihood that pollution or leaks to land will occur during the future life of the
installation;
or:
• There is a reasonable possibility that there is potential for current or future pollution of
the land from the installation.
The outcome of this assessment will inform whether intrusive sampling and the collection of
Reference Data in the first phase of the SPMP will be required. The definitions of “likelihood”
and “reasonable possibility” are presented in Box 4 and an illustration of the questions to be
answered in making this assessment is presented in Figure 2.
Box 4
The terms “little likelihood” and “reasonable possibility” are explained in greater detail in Section 4.5,
however they can be summarised as follows:
Then there is the possibility of pollution. However, there also needs to be an assessment of whether
a) Do preventative measures exist for each of the relevant activities at the installation?
b) Are the preventative measures adequate to prevent the emission of potentially polluting
substances to land?
c) Does the Applicant have NO record of pollution incidents or spills from the relevant activities to be
permitted? *See Note*
16
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
To satisfy the criteria that there is little likelihood that pollution will occur during the future life of the
installation the Applicant will have to have answered YES to ALL five of the above questions.
If the answer is NO to ANY of the above five questions then there is the reasonable possibility that
there is potential for current or future pollution of the land from the installation.
*Note* Question c) can be ignored if the Applicant can demonstrate appropriate measures have been
undertaken to ensure that further pollution incidents or spills do not occur. This could include
necessary improvements to management systems, equipment, plant or processes.
The criteria by which the key questions in this assessment should be answered is presented
below.
To assist the Applicant in the collection and presentation of data that is required to make this
assessment a specific template table has been prepared. An example of how to complete this
section of the ASR template is presented in Tables 2A and 2B.
Question ?
This question is answered by the Applicant following the requirements outlined in Section 4.4
(Step 3) of this guidance.
Question ?
To answer this question the Applicant must undertake an assessment of the pollution control
measures at its installation. Indicative requirements for the control of emissions to land are
presented in Box 5. The Applicant will need to demonstrate that it is applying these indicative
requirements or other equally applicable site specific measures to control potential emissions to
land in order to answer yes to question b).
Question ?
c) Does the Applicant have NO record of pollution incidents or spills from the
relevant activities to be permitted?
Data collected during the desk study and site reconnaissance, Section 4.2 (Step1) will enable
the Applicant to answer this question. At existing installations the Applicant needs to
demonstrate that they do not have a past record of pollution incidents or spills from those
activities that are to be permitted.
This question can be ignored if the Applicant can demonstrate appropriate measures have
been undertaken to ensure that further pollution incidents or spills do not occur. This could
include necessary improvements to management systems, equipment, plant or processes.
Question ?
The criteria to assess integrity testing should in the first instance be whether there is any
proposed or currently undertaken. If it is then it will need to satisfy the following:
17
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Question ?
The effectiveness of the pollution prevention measures identified in Step 3 are directly
related to operator competence. The following criteria should be considered to
demonstrate operator competence with the pollution prevention measures:
The above criteria are integral to environmental management systems. An externally certified
or verified EMS is a useful tool to demonstrate operator management and competence
Other relevant Pollution Prevention Guidelines (PPGs) produced by the Environment Agency
include:
All the Pollution Guidance Notes are available on the Environment Agency’s web site at:
www.environment-agency.gov.uk/business/444251/444731/ppg
18
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Notes: The need for Reference Data should be assessed on a relevant activity basis.
Question c) This question can be ignored if the Applicant can demonstrate appropriate measures have been undertaken to ensure that further pollution
incidents or spills do not occur. This could include necessary improvements to management systems, equipment, plant or processes.
19
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Box 5
Indicative Requirements
• establish and record the routing of all installation drains and subsurface pipework;
• identify all subsurface sumps and storage vessels;
• engineer systems to ensure leakages from pipes and the like are minimised and are easily detected if
they do occur, particularly where potentially polluting substances are involved;
• provide, in particular, secondary containment and/or leakage detection for such subsurface pipework,
sumps and storage vessels;
• establish an inspection and maintenance programme for all subsurface structures, for example,
pressure tests, leak tests, material thickness checks or CCTV.
• describe the design(#), and condition of the surfacing of all operational areas;
• have an inspection and maintenance programme of impervious surfaces and containment kerbs;
• justify where operational areas have not been equipped with:
- an impervious surface;
- spill containment kerbs;
- sealed construction joints;
- connection to a sealed drainage system.
(# Relevant information may include as appropriate: capacities; thicknesses; falls; material; permeability;
strength/reinforcement; resistance to chemical attack; inspection and maintenance procedures; and quality
assurance procedures.)
All tanks containing liquids whose spillage could be harmful to the environment should be bunded. Bunds
should:
20
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Table 2A Assessment of the likelihood of pollution
Site Operation Substance Relevant Activity Potential for 1. Records of pollution 2. Existence of Nature of Primary Testing and Inspection Nature of Columns
or Site Zone Pollution from the pollution Containment of Primary Secondary continue
relevant activity prevention Containment Containment on to
measures table 2B
Name Unit Name substance, Detail the relevant Detail the failure Detail any incidents of Do pollution Detail the nature of the Provide details of a Detail the nature of
Ope ration and provide CAS RN if activity for each mechanism and pollution or s pills from prevention storage vessel, including testing and ins pection the secondary
refer to the appropriate as well substance where potential pollution the relevant activity. measure exist for volume, location and programme or containment.
relevant as manufacturers the location, arising from the This can be based on each element of provide unique reference reference to a separate
section of the product name. pollution risk or loss of primary visual assessment during the relevant number and indicate which document, e.g. pressure
Permit Site Volume stored. For pollution containment site reconnaissance, activity ? site plan it is shown on tests, leak tests,
Report mixtures provide prevention installation or other material thickness
containing its breakdown of measures differ records and data sources. checks etc.
description polluting substances Have measures been put
and percentage by in place to ensure no
volume. further pollution
incidents?
A) Factory Kerosene 1. Delivery by Spillage from road No evidence/records of Yes Road Tanker Compliant to British Site drains
heating and road tanker tanker on spills or leaks Standard and DOT discharge to oil
steam to installation installation roads Regulations interceptors prior
generation by entering road to soakaways
boiler using drainage and
fuel oil hence soakaways
2. Road tanker Spillage from road Visual inspection Yes Road Tanker Compliant to British Tankers park
off-loading tanker or delivery indicates land impacted Standard and DOT when filling tank
pipework to land with heating oil Regulations on Impermeable
pavement with
kerbs and falls to
underground
sealed tank of 30
cubic metre
capacity
Storage Failure of No evidence/records of Yes 200 cubic metre floating None Earth Bund
containment spills or leaks roof tank (ref A1 figure 3) containing tank
leading to spillage and fill point
to land
Fuel supply to Failure of Leaking underground No Underground steel Annual pressure test None
boiler plant underground pipe discovered during pipeline (ref A2 figure 3)
pipeline between general maintenance
the oil storage works in service trench
tank and boiler in 1999, pipe repaired.
plant leading to
loss of product to
land
Boiler plant Spillage within No evidence/records of Yes Boiler Plant (ref A3 figure 6 monthly Kerbed concrete
boiler room to land spills or leaks 3) maintenance and floor with no
or site drainage inspection programme surface drainage
21
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Table 2B Assessment of the likelihood of pollution, continued
Continued Testing and Inspection of Nature of Tertiary Testing and Inspection of 3. Adequacy of pollution 4. Are the 5. Is there an The assessment on the likelihood of pollution
from table Secondary Containment Containment Tertiary Containment prevention measures proposed adequate and hence the need to collect reference samples
2A Yes/No Integrity documented will be made on the questions set in the
testing of manage ment GREEN columns on this table and supported
pollution system to by the information provided.
prevention demonstrate To make the case that there is little likelihood
measures operator of pollution the Applicant will need to provide
Adequate manage ment and the following ans wers:
Yes/No competence with Green Column 1 - No past pollution incidents
the relevant or spillages
activity? Green Column 2 - Yes pollution prevention
Provide details of a testing and Detail the nature of Provide details of a Do the pollution prevention measures exist for each relevant activity
inspection programme or reference the tertiary testing and ins pection measures and testing and Green Column 3 - Yes pollution prevention
to a separate document, e.g. Containment programme or reference inspection programme measures are adequate
pressure tests, leak tests, material to a separate document, comply with the indicative Green Column 4 - Yes adequate integrity
thickness checks etc. e.g. pressure tests, leak require ments set out in Box testing undertaken or proposed
tests, material thickness 5? Green Column 5 – Yes there is an adequate
checks etc. If yes then justify how. manage ment system
IF THE ABOVE CRITERIA CAN NOT BE
SATISFIED THEN THERE IS THE
REASONABLE POSSIBILITY OF
POLLUTION AND THE OPERATOR WILL
NEED TO COLLECT REFERENCE DATA
IN THE SITE PROTECTION AND
MONITORING PROGRAMME
Little Likelihood of Reasonable Possibility
pollution ? of Pollution ?
1. Interceptors visually None None Yes Yes Yes
inspected monthly and
following any notified spill as
part of EMS ref x.x a -
2. High level alarm to notify None None No Yes No
need for emptying. No
Integrity testing
- a
3. None None None No No No
- a
4. None None None N/A Yes No
- a
5. Design quality assurance and None None Yes: Requirements of Yes Yes
inspection and monitoring surfacing in section 2.2.5
programme as part of EMS
ref x.x
of the Sector Guidance
complied with as part of a -
EMS
22
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Key Task
• Collation and interpretation of data in the form of a Conceptual Site Model.
By undertaking the activities outlined in Steps 1, 2, 3 and 4 the Applicant will have
gathered a significant amount of site specific data. This information now needs to be
combined to form a Conceptual Site Model (CSM) of the site.
The CSM is required to describe the condition of the site. This is a fundamental
objective of the ASR and is required in all cases regardless of whether the Applicant
has made the case that there is little likelihood of pollution or not. It will describe the
site’s environmental setting, help understand ground conditions and it will be
impossible to design an adequate SPMP, if one is required, without the completion of a
satisfactory CSM.
Therefore the presence, nature and risk of adverse effects to other receptors are not
primary considerations in the context of the protection of land under PPC, although
potential sensitive receptors must be reported in the ASR. The CSM within a ASR
should therefore consider the land as a receptor in its own right and should
concentrate on the source and pathway terms as these will define the
distribution of pollutants in the subsurface if there is an accidental emission.
The CSM developed and presented within the ASR will be used as the basis of the
design of any investigations to collect Reference Data as part of the SPMP. The CSM
must therefore clearly state what are known facts and what are assumptions. Assumed
parameters that can significantly affect the distribution and fate and transport of
pollutants in the subsurface may need to be determined through site investigation.
An example of a graphical CSM for a zone of the site where the assessment of
pollution undertaken in Step 4 indicates that there is a reasonable possibility of
pollution of the land is presented in Box 6.
23
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Box 6
ZONE 1
Sands and
Gravel
Clay
On 15 June 2002 a valve failed on number 1 fuel oil tank leading to the loss of 80 cubic
metres of fuel oil to the land. The failure caused a slow leak and the oil was lost over night.
The tank was decommissioned until the valve was repaired. The tank farm is surrounded by
earth bunds but the ground beneath the tanks is sufficiently permeable to allow fuel oil to
seep through. On the basis of the published geological data for the area and the known
characteristics of the pollutant the above graphical description of the likely nature and extent
of pollutant distribution in the subsurface has been produced.
Uncertainties in the preliminary conceptual model that could affect the distribution of
pollutants in the subsurface.
A GEOLOGY: Thickness of sand and gravel (S&G) horizon, nature of S&G / Clay
interface, particle size distribution of S&G, fraction of organic carbon, clay mineral
content, bulk density - heterogeneity of these geological parameters.
24
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
6.0 Conceptual Site Model The whole of section 6.0 presents the CSM,
6.7 Summary of Conceptual Site Model however summary information and
importantly uncertainties in the model should
be presented in section 6.7
25
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Key Task
By following this guidance the Applicant will be able to submit a PPC site report that
satisfies the requirements of the EHS.
A Template for the ASR has been produced and is designed to help the Applicant by
clearly setting out reporting requirements.
In preparing the ASR for the Permit application the Operator should consider the
following issues:
• The ASR is factual in its nature and consideration should be given to the
presentation of this data. The use of tables, drawings and graphics can be very
effective in summarising and communicating large amounts of data and
information.
• A site plan must be submitted clearly indicating the relevant systems or activities
that have been assessed to have a reasonable possibility of pollution. This plan
must also show the zone around each system or activity for which reference
concentrations will be set in the SPMP.
• A site plan showing the historic past uses of the site and areas of potential
historic contamination.
• Site plans submitted should be marked with a scale, compass bearing, date and
version number. They should cover the whole (or relevant part of) the installation
and incorporate key features, such as buildings or other structures that are to
remain in place. Key features should be labelled clearly and a key / legend
should be provided.
• The ASR will be used in the design of the SPMP and any subsequent monitoring
programmes, if required, it is therefore important to ensure that the ASR is
complete and detailed enough to ensure that any future monitoring is targeted,
effective and efficient.
26
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
This next section covers the requirements after a Permit has been issued and details the
activities the Operator must follow to ensure compliance with any specific conditions relating
to the submission and implementation of a Site Protection and Monitoring Programme.
This covers Stages 2 and 3 of the protection of land under PPC as detailed in Figure 1,
however Figure 3 presents the activities in these stages in greater detail.
• Stage 2 – Submit a design of a Site Protection and Monitoring Programme to the EHS
within 2 months from the date of Permit issue; and
• Stage 3 – Where Reference Data is required to be collected this must be submitted to
the EHS within 6 months from the date of Permit issue.
The EHS will take enforcement action in line with its Enforcement Policy if the conditions in
the Permit to protect land are not complied with.
+ If necessary
# PPC is a preventative regime and deals purely with any additional pollution since the
issue of a Permit, or for a Specified Waste Management Activity the date of issue of the
Waste Management Licence. It does not consider the risks associated with this
pollution, and any additional pollution must be cleaned up to pre-permit levels before
the Permit can be surrendered.
* The SPMP would not apply in respect of any pollution which might arise from activities
on the site of the installation which are not covered by the Permit.
27
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
STEP 2
• Design the testing, inspection and maintenance
programme
• Design the environmental monitoring
infrastructure +
STEP 3
• Design the information and data management
systems
28
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
5.1 Introduction
The objective of this Stage is to use the ASR as a basis in the design of the SPMP.
The output of this stage will be a design report outlining what monitoring the Operator
will undertake, this report must be submitted to the EHS within two months from the
date of Permit issue.
Step 4 – Reporting
The design of the SPMP, submitted in pursuance of a Permit condition, must contain
the level and scope of information as indicated by this guidance and relevant template.
29
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Box 7
• To ensure (as far as is practicable) that pollution prevention measures are sufficient to prevent
the emission of pollutants to land.
• To demonstrate and maintain the effectiveness of the pollution prevention measures at the site
throughout the life of the installation.
• Where necessary to collect Reference Data for substances in use at the installation for which
pollution is ongoing or where there is a reasonable possibility of such pollution occurring.
• Where necessary to monitor land and/or groundwater to ensure pollution prevention measures
are effective and to provide warning of the failure of pollution prevention measures.
• To record the results of the above to demonstrate the land at the installation is in a satisfactory
state for the purposes of surrendering a permit.
Key Tasks
• Review the CSM and describe the fate and transport of pollutants in the subsurface for
each potentially polluting activity of the installation identified in Stage 1.
• Review any existing site investigation reports and data for the area of the installation.
5.2.1 Introduction
The Operator can omit this step where the assessment of the likelihood of pollution
indicates that there is “little likelihood of pollution”.
The setting of Reference Data will require the collection of soil and groundwater
samples and subsequent chemical analysis. The Operator will be required to provide
actual quantified concentrations of polluting substances in the land that could be
released by the installation. At Permit surrender this information, along with other
monitoring data, will be used to assess whether pollution of the land has occurred and
will provide information on appropriate restoration levels. A full definition of what is
required by way of Reference Data can be found in Appendix A
30
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
If intrusive investigations are to be undertaken then this is likely to be the most cost-
effective time to install long term environmental monitoring facilities, avoiding as much
as possible, the costs of re-mobilisation of people and plant. Section 5.3 discusses the
design of environmental monitoring facilities and programmes.
The location of potential (or actual) sources of emissions will be identified in the ASR.
In order to design a suitable and robust investigation and monitoring programme the
likely fate and behaviour of the substances in the ground must be understood. Box 8
contains factors that could affect the distribution of pollutants in the ground arising from
a point source emission.
It is also important at this stage to identify any uncertainties or assumptions within the
initial CSM provided as part of the ASR that may have a bearing on the pollutant
distribution at the installation.
¾ For instance the CSM may have assumed that a clay layer exists beneath the
site which would act as a barrier to the downward migration of pollutants to the
water table. If this is a significant factor in the potential contaminant distribution
beneath a site then investigations may need to include determining the
existence, thickness, nature and extent of the clay layer.
The importance of a thorough and robust CSM as part of the ASR cannot be stressed
enough.
From this review the potential distribution of pollutants in the subsurface beneath the
installation can be described. This should not only include the likely extent but also the
phase the pollutant is in, e.g. dissolved in groundwater, attached or sorbed to soil
particles, as a free-phase liquid floating on the water table or pooling at the bottom of
an aquifer
Box 8
31
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
• Solubility in water;
• Vapour pressure;
• Viscosity;
• Density;
• Affinity to soil particles, organic matter (sorption);
• Propensity to undergo biological, chemical and thermal breakdown.
• Porosity;
• Permeability;
• Depth to groundwater, groundwater table orientation, seasonal variation
• Natural or man-made barriers to contaminant migration (e.g. clay layers, foundations)
• Natural or man-made preferential pathways for contaminant migration (e.g. gravel layers,
gravel backfill around underground services, fractures);
• Sorptive capacity (e.g. clay content, organic content, geochemical characteristics);
• pH and redox potential.
It is not the intention of this document to provide technical guidance on designing and
undertaking land contamination investigations. Relevant guidance is referenced within
this document. This Section and Section 3 of Reporting Template 2 provide a
framework for the design of intrusive investigations to collect Reference Data. This
Section should be considered with the guidance on designing monitoring programmes
in Section 5.3 below.
It may be necessary to phase the investigation with a view to collecting the most
relevant and cost effective data for a site. Phasing of an investigation is more likely to
be required on large complex sites with a history of pollution incidents and numerous
potentially polluting activities.
The use of on-site testing and analysis tools providing real-time data during an
investigation is encouraged. Using a tiered investigation in such a way can lead to
lower overall investigation costs, but provide higher quality investigations. (Ref 18
and 29)
Quality assurance and quality control are key to collecting robust, reliable data.
Chemical analysis of samples should preferably be undertaken by laboratories that are
accredited under the Monitoring Certification Scheme (MCERTS). The Design SPMP
Template has been formatted so that the QA/QC requirements for the investigations,
analyses and reporting of results are properly designed and recorded.
32
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Design SPMP
3.0 Intrusive Investigation to Collect Sets out and justifies the design of the
Reference Data required intrusive investigations for the EHS
3.1 Investigation and Sampling Strategy to approve.
3.2 Sample Locations
3.3 Analytical Strategy
Key Tasks
5.3.1 Introduction
The objectives for monitoring land and groundwater at an installation are shown in
Box 9.
33
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Box 9
Objectives of monitoring land and groundwater at an installation
34
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
The infrastructure monitoring programme must also include a system for the regular
assessment, recording and reporting of monitoring results. Reference 32 contains
examples of check-lists and logs for the inspection, maintenance and repair of
infrastructure and is available from the DEFRA website.
Systems may already be in place at an installation that cover some or all of the
requirements of an SPMP. These may include:
If a condition requiring the collection of Reference Data IS NOT included in the Permit
then a case has been made that existing or proposed testing, maintenance and
monitoring procedures are sufficient to ensure there is little likelihood that pollution or
leaks to land will occur during the future life of the installation.
In this case the Design SPMP should contain a statement to the effect that:
1 Such procedures will continue during the life of the Permit, and
2 That procedures will be subject to review and modification following changes to
infrastructure, working practices or any guidance /statutory requirement the
procedure was based upon.
3 The SPMP should also include systems for the regular assessment, recording
and reporting of monitoring results for the purposes of demonstrating continued
compliance with Permit conditions and for the purposes of applying to surrender
a Permit.
If a condition requiring the collection of Reference Data IS included in the Permit (i.e. a
reasonable possibility exists for current or future pollution of the land from the
installation) then the following needs to be taken into consideration within the Design
SPMP:
A written scheme describing how techniques relied on for protection of the land are to
be monitored and maintained shall be prepared and should contain:
35
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
- Interceptors
- Alarms
Examples:
- Security arrangements
- Accident responses
- Inventory control
- Environmental Management Systems
- OFTEC Standards
- CIRIA Standards
- CEN Standards
- ISO Standards
- Manufacturers Recommendations
- Manufacturers recommendations
- Installation inspection schemes
36
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Design SPMP
Template 2 – Collection of Reference Data Required
Template 3 – Collection of Reference Data NOT Required
4.0 Monitoring Programme Sets out and justifies the required Monitoring
4.1 Objectives of the Monitoring Programme Programme for the site
4.2 Environmental Monitoring Infrastructure
4.3 Environmental Monitoring Programme
Monitoring results will form a major part of the assessment that has to be submitted
with an application to surrender a PPC Permit. The operation of a robust SPMP is likely
to generate large volumes of data in the form of routine infrastructure monitoring and
analytical records.
The purpose of the Information and Data Management System and Reporting
Programme is to record this data, or to record summaries of the data.
• The data is easy to understand and it is obvious what the data recorded relates
to and means;
• It is easy to query (having regard to data queries that are likely to be run during
operations and for the purposes of applying for surrender);
• It is easy to maintain and update (data entry);
• Where feasible, automatic data quality checks occur and non-compliant data is
flagged up for quality control checks and action.
37
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Design SPMP
Template 2 – Collection of Reference Data Required
Template 3 – Collection of Reference Data NOT Required
4.0 Monitoring Programme Sets out and justifies the monitoring and
4.5 Assessment and Reporting Procedures reporting procedures
The Design SPMP document must be submitted to the EHS within two months from the
date of the Permit issue and should provide a framework for any investigations to
collect Reference Data.
Templates for the production of the SPMP design report are available. These templates
have been designed to help the Operator by clearly setting out the EHS's expectations
for reporting.
Where Reference Data is required to be collected this must be reported to the EHS
within six months from the date of permit issue. For other monitoring the design
document must include a timetable and schedule for the implementation and reporting.
Two separate templates have been provided, one for those installations that require
Reference Data to be collected:
H7 Reporting Template 2 –
The other is for those installations that do not require Reference Data to be collected:
H7 Reporting Template 3 –
38
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
6.1 Introduction
This stage describes the implementation of the SPMP submitted to the EHS.
At installations where Reference Data does not need to be collected the timescale for
the implementation of the SPMP will be set out in the design document of the
programme.
To complete this stage the Operator will be required to undertake the following steps:
Key Tasks
• Identify sources of any pollution, and state uncertainties and unknown sources
The investigations to collect Reference Data should take place in full accordance with
the design in the SPMP document. The EHS recognises, however, that conditions at
the site may necessitate amendments, for instance difficult ground and obstructions.
Reporting of the implemented SPMP should only contain the results of the
investigations and any amendments to the investigations and should not reproduce the
procedures, protocols, etc agreed in the Design SPMP.
39
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
6.3 Step 2 – Implementing the Remaining Part of the Site Protection and
Monitoring Programme
Key Tasks
The purpose of this step is to finalise the ongoing Monitoring Programme following the
first phase of implementation for formal agreement with the Agency.
There may be a number of reasons to amend the design of the Monitoring Programme
following any investigations:
At some sites pollution may be identified in the collected Reference Data, if this is the
case further actions maybe required. Guidance on what to do in these situations is
provided in Appendix B.
In addition, pollution may also be identified in the data collected during the undertaking
of long term monitoring as part of an SPMP. Further guidance for these situations is
provided in Appendix C.
Two templates are available for the reporting of the first phase of the SPMP.
40
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Box 10
It should be noted that Reference Data is more than just the summary statement contained in
Appendix G2 of the Final SPMP Template. Reference Data include the revised conceptual site model,
borehole and trial pit logs etc, observations and other physical ground condition records as well as the
full data set for all analyses.
Whist monitoring of ground and groundwater may occur during the life of the permit, it is predominantly
against the Reference Data that the installation will be judged at surrender to determine satisfactory
state. It is therefore vital that all investigation, sampling and analysis methods are clearly documented in
the relevant appendices of either the scoping or completed SPMP Template so that valid comparisons
can be made to any investigations at surrender.
The following bullet points provide further guidance on reporting the results of investigations
and reporting Reference Data:
• A Statement of Reference Data (SRD) is required for each zone of the site identified in the ASR as
having a reasonable possibility of being polluted by the installation now or in the future. It:
¾ Must describe the condition of all soils / subsoils and associated groundwaters (where
¾ Need only consider those substances identified as being potentially polluting that are stored,
handled, transferred, used or produced within that zone; and
¾ Should be accompanied by relevant analytical data that has been collected using appropriate
techniques.
• PPC does not consider whether the condition of the site is acceptable, it seeks to establish a
reference against which any deterioration in condition can be assessed. Therefore:
¾ Undertaking an assessment of the risk from any identified pollution is not required within an
SPMP.
¾ Quantification of levels of pollution is required for those substances that may be added to by the
operation of the installation at the site.
41
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
References
1 Department of the Environment, Transport and the Regions, “The Pollution Prevention
and Control (England and Wales) Regulations 2000, Statutory Instruments 2000
No. 1973
14 ISO FDIS 10381-1 Soil Quality Part 1: Guidance on the Design of Sampling
Techniques
42
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
17 ISO FDIS 10381-4 Soil Quality Part 4: Guidance on the Procedure for the Investigation
of Soil Contamination of Urban and Industrial Sites.
23 Health and Safety Executive (1991), “Protection of workers and the general public
during development of contaminated land”, HS(G) 66.
24 Construction Industry Research and Information Association (1996), “A guide for safe
working practices on contaminated sites”, Report 132.
25 Department for Environment, Food and Rural Affairs & the Environment Agency,
“Handbook of Model Procedures for the Management of Contaminated Land” CLR 11
(in preparation)
32 Department for Environment, Food and Rural Affairs (2002) “Code of Practice for Use
of Solvents”
43
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
44
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
APPENDICES
Appendix D Glossary
45
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
APPENDIX A
An Operator of a Part A Installation or Part A Mobile Plant may be required, as part of the
SPMP, to determine Reference Data for the installation.
In conjunction with long term monitoring data, the Reference Data will be used to set the
condition of the installation against which the restoration requirements at Permit surrender will
be established. Any additional pollution must be remediated back to the levels shown in the
Reference Data.
• Reference Data describe the quality of the land at and beneath the installation with
respect to the substances used, manufactured, stored or transported under the terms
of a PPC Permit.
¾ Land in this document refers to both soils (including made ground and natural
geological strata) and any groundwaters.
• Due to the inherent variability of soils and groundwater and the spatial variability of the
distribution of pollutants in environmental media it would be normal to present the
results of a statistically valid number of samples to describe Reference Data for an
installation, unless Reference Data are zero.
• Pollution at a site is likely to relate to point source discharges and the variation of
pollutant concentration across the site will reflect this. It will be a function of the location
of the source, the environmental fate and behaviour of the substance and the
environmental setting of the installation.
• As Reference Data are set to provide a comparison for surrender they must be of a
standard to make such a comparison possible and meaningful. The site should be split
up into a series of relevant activities or zones where conditions at the installation are
likely to be similar.
• Reference Data can be based upon intrusive investigation and subsequent sample
analysis or upon desk study information.
• Reference Data must be set only for those zones of the installation that have
demonstrated a reasonable possibility of pollution. Within each zone concentrations
must be set for each different environmental media encountered.
• Although a summary of Reference Data should be produced, the full data set,
investigation / inspection (etc) observations and interpretations and the conceptual site
model are all part of the Reference Data. They all provide data on the condition of the
land and will be used to assess trends in long term monitoring and satisfactory state by
the Agency upon receipt of an application to surrender a Permit.
46
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
APPENDIX B
Should the intrusive investigations to collect Reference Data, (including the first round of
monitoring) identify pollution then the emergency monitoring plan (as part of the
Environmental Monitoring Programme) may have to be enacted. This Appendix and Boxes B1
to B3 provide the rationale and justification for enacting Emergency Monitoring Plan under
such circumstances.
It is reiterated that only those potentially polluting substances used or produced (or are likely
to be used or produced in the future) at the installation will have to be investigated. At
locations where it has been assessed that there is a reasonable possibility of releases
occurring. Box B2 details the categories of sources of pollution that may be found at an
installation.
The PPC Regulations only relate to additional pollution and not to that existing when
Reference Data is collected, i.e. only a Type D source is regulated under the PPC Permit.
The emergency monitoring plan should be enacted unless the Operator could demonstrate to
the Agency's satisfaction that the source is not from currently permitted operations.
The ASR and investigations to collect Reference Data may have provided sufficient
information to identify a source or the Operator may wish or need to amend the SPMP by
augmenting it with additional intrusive or other investigations.
The Operator may have to make a further decision as to how to respond to pollution identified
when collecting Reference Data:
¾ They can rely upon the Infrastructure and Environmental Monitoring (including the
Emergency Monitoring Plan) in the SPMP to determine the source or prove the integrity
of their infrastructure, or
¾ They could undertake additional investigations to determine the source of the pollution.
47
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Box B1
If pollution exists within land or groundwater then the proposed method(s) of assessing monitoring data will
have to take this into account. Even if no further releases occur since collecting Reference Data, the
environmental monitoring results will vary between monitoring events at the same location.
Differences in concentrations of pollutants in soil between different sample locations can be great even
over small distances. There can also be changes in soil concentrations at the same location over time,
caused by leaching of pollutants down through the unsaturated zone, sorbtion-desorbtion processes or
biodegradation of organic substances as well as additional emissions.
The concentration of pollutants in groundwater at an environmental monitoring location can similarly vary
due to a number of reasons as well as additional emissions. Migration of contaminants within groundwater
(a plume of pollution) could bring groundwater with a higher concentration to the monitoring borehole.
Rising groundwater can flush additional pollutants from the unsaturated zone.
Sampling and analytical procedures can introduce bias and "errors" in to environmental monitoring results
(so called uncertainty).
For these reasons the frequency of environmental monitoring may have to increase to that
identified in the emergency monitoring plan within the Design SPMP in order to determine
whether ongoing pollution is occurring, or whether increases in concentrations are due to
processes other than the release of substances to land.
Box B2
Potential types of sources of pollution identified during investigations to collect Reference Data for
an Installation
A) The source of the pollution was historic activities undertaken at the site of the installation that do
not occur under the terms of the permit.
B) The source of the pollution is outside the area of the installation and has migrated to beneath the
installation. The source could be an on-going or historic activity.
C) The source of the pollution was from activities that occur under the terms of the permit, but due to
changes or improvements to management practices or infrastructure the emissions have ceased.
D) The source of the pollution is from permitted activities and that source is on-going leading to
pollution of ground or groundwater in contravention of the PPC Regulations.
48
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Box B3
A bulk storage tank's contents are transferred to process areas via an underground pipe
system. The tank sits within a suitably sized bund that also encompasses the fill points. The
tank is filled by road tanker that parks upon a concrete apron draining to a sealed sump.
Testing and inspection of the bund, sump, tank and pipe occurred during investigations to
collect Reference Data. Pressure testing of the underground pipe system and stock
reconciliation could only provide an accuracy of >10 litres per day of product. Intrusive
investigations of the land were undertaken in suitable locations to set Reference Data for the
substance in the tank and pipe work and elevated levels of that substance were identified
in the soil and groundwater.
During the intrusive investigation boreholes were finished with groundwater monitoring
installations and regular monitoring was instigated within the SPMP. However the ASR's
conceptual site model identified that the concrete apron and sump for the tanker parking had
only been installed 6 months before applying for a Permit and that there were records of
several spills to land from tankers prior to this.
The CSM was reviewed and it was recognised that the groundwater level beneath the site
would fluctuate significantly throughout the year. This would lead to fluctuating levels of the
substance in the groundwater and hence concentrations in the monitoring results even
without any further emissions. It would therefore take a number of monitoring events, possibly
over a year, to establish whether trends in the monitoring data indicated an ongoing pollution.
By that time a large volume of the substance could be released which, under the PPC
Regulations, would need to be remediated.
The Operator could either wait to see if the monitoring identified increasing levels of pollution
or they could instigate further investigations to identify the source at the time Reference Data
was collected.
The PPC Regulations cannot be used to require the Operator to undertake investigations to
identify the source unless or until ongoing, additional pollution is identified. The Regulations
require that any additional pollution is remedied as soon as practicable, and the presumption
is against waiting to deal with it upon surrender. There may be major costs involved
remediating >12 months of pollution, not only remedial costs but also in terms of lost
production through any disruption such works may cause and damage to corporate image.
49
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
APPENDIX C
Introduction
Should pollution be identified during the implementation of the SPMP that has occurred or
been added to since collecting Reference Data for an installation then additional works are
necessary to:
• Identify the source, or prove the source is not from the currently permitted installation;
• Remediate to levels shown in the Reference Data .
Operators are required to inform the EHS immediately of any breach of Permit condition. The
EHS would require Operators under such conditions to facilitate a prompt and satisfactory
resolution to a pollution problem. The guidance in this Appendix is included to assist
Operators to comply with these obligations. The EHS would be involved in discussions and
consultations if this situation arises.
When additional investigations are undertaken the EHS expects the same level of quality
assurance and quality control as is inherent in the SPMP. Any document produced would
form an addendum to the SPMP. It would be used as part of the assessment by the EHS
upon receipt of an application to surrender a PPC Permit.
Potentially polluting substances may already exist in the ground at background concentrations
if they are naturally occurring substances. Man-made, organic substances should not exist in
the land at any concentration except as a result of pollution.
For naturally occurring substances, the first step is to identify the concentration range
expected if there were no human activity impacts (i.e. background levels) and compare that to
levels found at the installation. Background levels could be determined from the analysis of
environmental media in areas of the installation where those substances were never used
and could not have migrated to, or through the use of literature sources. Background
concentrations will vary for different strata, made ground and groundwaters and so careful
consideration must be given to the relevance of literature sources to conditions at the
installation.
Box B2 in Appendix B details the potential types of sources of land or groundwater pollution at
an installation.
Ideally investigations and assessments undertaken to collect Reference Data will have been
sufficient to identify the source of any elevated levels and this step may simply consist of:
• Reporting the source along with the reasoned assessment and supporting data for those
cases described by A), B), and C) in Box B2.
• Identifying the source and reason for the emission from the permitted activity (D) in Box
B2) - In this instance all such sources should be considered.
50
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
However if the source cannot be attributed then additional investigations will be required as
detailed in the following Sections.
Key Tasks
Whilst the PPC Regulations do not control any pollution existing before a Permit was issued
or pollution arising from a non-permitted activity outside the installation boundary, any
increase in pollution identified since the collection of Reference Data will be attributed to the
installation. Unless the Operator can demonstrate to the EHS's satisfaction that the source is
not from the installation.
If it is known that the source is as a result of the permitted activity then additional
investigations may still be required in order to characterise the extent of the pollution and
collect data to design an effective remediation scheme.
Investigations additional to that undertaken to collect Reference Data may include for
instance:
The additional data collected should be assessed against the scenarios contained in Box B2.
If a source is confirmed as not coming from the currently permitted activities then the results
of the investigations and assessments should be reported within the SPMP. The Reference
Data for the site should be updated with this information.
If a source is confirmed as coming from the installation then the Operator shall move
immediately to remediation design and implementation. This additional information shall
not amend or update the Reference Data for the installation.
51
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Key Tasks
If activities at the installation are causing pollution then actions must be taken, as soon as is
reasonably practicable, to prevent any further emissions and remediate to Reference Data
levels.
Any additional pollution caused between the collection of Reference Data and the end of
emissions to the land must be remediated. The timing, extent and nature of this remediation
must be agreed with the EHS on a case-by-case basis.
The Practical Guide to Integrated Pollution Prevention and Control [Reference 16] sets out a
hierarchy of approaches to remediation under PPC as follows:
Note that the EHS also has powers to require any pollution from permitted activities
(where contravention of a Permit condition has occurred) to be remedied
(Regulation 26). Remedying the effects of pollution could, for example, involve
restocking a river which has received discharges of polluted groundwater or the
replanting of landscape areas that have been damaged through the airborne deposition
of polluted soil or dust.
Ideally, remediation should aim to treat or remove pollutants to achieve the levels identified in
the Reference Data for the installation. Only if it can be shown that it is not reasonable or
practicable to treat or remove the pollution should immobilisation techniques be considered.
Similarly, actions to mitigate the effect of the pollution (i.e. reduce the degree or severity of
impact) should only be considered if it is not reasonable or practicable to fully achieve
Reference Data levels using treatment/removal techniques. In the event that it is not feasible
to apply any of the above approaches, Operators should implement monitoring measures to
track the condition of the land until it is reasonable and practicable to implement remediation
52
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
The overriding objective is to return the land to the same state as it was when the Permit was
issued. This broad objective should be translated into a series of substance-specific
remediation objectives typically expressed in terms of the concentration (or amount) of the
substance(s) that should not be exceeded in soil or groundwater following remediation.
Note that for some remediation methods (typically those involving the containment or
immobilisation of polluted material), objectives may be better expressed in terms of the
physical or other characteristics of components of the method. For example, it might be
appropriate to define limits on the permeability of an in-ground barrier system or the leaching
behaviour of a solidification agent such that the quality of groundwater in contact with the in-
ground barrier or solidified material achieves the levels identified in the Reference Data.
More detailed information on the technical and scientific basis of different remedial methods,
applicability to particular substances and key limitations can be found in References 13, 17,
20 and 21. Advice on monitoring techniques can be found in References 7, 22 and 23.
Note that additional work (e.g. supplementary site investigation or treatability studies) may be
needed to fully evaluate potential remediation methods. Supplementary investigations may be
required to develop and cost a detailed design and to check whether and to what extent site
specific factors may reduce effectiveness (e.g. permeability of the ground, presence of
substances inhibitory to biological action).
Treatability studies may be required for collecting information prior to making a final selection
of options. They may be used to:
Once sufficient information is available to make an informed selection, Operators should carry
out a structured analysis of options against clearly defined technical criteria, and estimate
53
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
costs and benefits. The aim is to establish which method (or combination of methods)
represents the best overall balance between technical effectiveness, practicability, durability,
costs and benefits.
Key Tasks
• Implement the agreed remediation strategy and undertake verification work to show
that it has been effective.
Once a proposed course of remediation action for any particular area of land occupied by the
installation has been identified and agreed with the EHS, Operators will need to consider:
1. Management of the remedial works:- identifying both general and specific site
management objectives for the implementation of the remediation strategy.
2. Design and procurement:- confirming that the remedial works have been designed and
specified in sufficient detail for the strategy to be implemented. Precautions need to be
considered to protect health and safety, and the environment, during the
implementation of the works.
3. Implementation and validation:- the measures (e.g. monitoring programme for the
remediation ) that are to be put into place to show that remedial works have achieved
their objectives over a specified period of time and, where necessary given the nature
of the action taken, over a longer-term.
4. Ongoing monitoring and maintenance:- documenting the purpose and aims of ongoing
monitoring and maintenance.
Operators should also make appropriate financial and time provision for:
• Obtaining all necessary regulatory permissions to set-up and operate the remediation
strategy (e.g. waste management licences, mobile plant licence, etc.);
• Contingencies in the event that remediation fails to meet its objectives, necessitating
additional work, or is otherwise delayed or varied;
• Disruption to normal operations at the installation.
Verification of Remediation
54
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
All proposed verification work should be set out in a written specification or method statement.
This should assign clear responsibility for the work, set out the methods to be used (including
sampling and testing requirements) and specify reporting requirements.
More detailed guidance on the validation of remedial action is given in References 13 and 19.
It is essential that Operators produce accurate, reliable and unambiguous factual reports on
any remediation work carried out. The report should contain sufficient information for
someone unconnected with the work to easily establish what the work involved and whether it
was technically valid.
Thus the factual content of remediation reports should include a full account of:
• The rationale for remedial objectives and design of the works including the reasoning
for selecting the methods adopted;
• An updated conceptual site model;
• The responsibilities of all those involved (e.g. project managers, advisors and
contractors);
• How the work was carried out (e.g. methods and programme);
• The final condition of the land;
• Verification programme, methods and findings;
• Any monitoring, inspection and maintenance work and outcomes.
55
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
APPENDIX D
Glossary
Application Site Report (ASR) A report on the condition of land at the time an application is
made for permission to operate an installation or mobile plant.
Conceptual Site Model (CSM) A textual and/or graphical representation of the relationship(s)
between pollutant source(s), pathway(s) and receptor(s).
Closure Site Report (CSR) A report on the condition of land at the time of definite cessation
of permitted activities and an application is made for the
surrender of a Permit to operate an installation or mobile plant.
Emergency Monitoring Plan A formally agreed, quality assured and quality controlled plan for
environmental monitoring at an installation following a release of
polluting substances to land, or the identification of pollution
during the routine environmental monitoring programme. The aim
of the plan is to identify the source of the pollution, characterise
the extent of the pollution and to collect data to facilitate any
necessary remediation to return the site to a satisfactory state.
Environmental Management A documented structure that allows for the monitoring and
System (EMS) assessment of environmental impact with the objective of
continuously improving environmental performance.
Failure Mode Analysis Technique to assess the likelihood and means of failure of
equipment.
Fault / Event Tree Analysis Technique to predict the likely events or combination of events
that will lead to an unacceptable outcome.
Hazard / Environmental and Technique to assess the outcome of deviations to normal process
Operability Studies operations.
56
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Reference Data The condition of the land, with respect to potentially polluting
substances, which is set within the SPMP consisting of quantified
data (See Appendix A for further explanation).
Risk assessment The process of assessing the hazards and risks associated with a
particular site or group of sites.
57
H7 Guidance - Application Site Report and Site Protection and Monitoring Programme
Substance Includes any chemical element and its compounds and any
biological entity or micro-organism, with the exception of
radioactive substances within the meaning of Council Directive
80/836/Euratom, genetically modified micro-organisms within the
meaning of Council Directive 90/219/EEC and genetically
modified organisms within the meaning of Council Directive
90/220/EEC.
Zoning The process of delineating one or more parts of a site that justify
different or specific approaches to sampling on the basis of
existing or future conditions.
58
Technical Guidance Note
IPPC H7 (Reporting Template 1)
Control (IPPC)
Template for an
Applications
H7 Reporting Template 1
INTRODUCTION
This document presents a reporting template for applicants to use when preparing a PPC
Application Site Report. It is designed to assist applicants with the submission of the correct
information in a suitable format to the Environment and Heritage Service (EHS) and should
be completed in full.
This template has been prepared assuming that the Applicant will use a suitably qualified
third-party to assist in the preparation of the Application Site Report. Where this is not the
case it is acceptable for the information required to be cross-referenced to other parts of the
application.
Where there are deficiencies or uncertainties in the information provided in the application,
these should be clearly marked and annotated to indicate where further data gathering may
be required. It must be used in conjunction with the following guidance document:
Guidance on the Protection of Land Under the PPC Regime: Application Site Report
and Site Protection and Monitoring Programme
In the template, those parts written in italics and enclosed in square brackets ( i.e. [italics] ),
indicate where relevant information and or assessment is required to be entered. In entering
this information the italics should be deleted along with the brackets or written over and the
text reformatted to normal style.
Where text in italics appears prefixed with the word “Note” in bold ( i.e. [NOTE: italics] ) this
provides guidance on filling in the relevant [italics] part. On completion of the [italics] part the
[NOTE: italics] should be deleted from the final report prior to submission.
59
H7 Reporting Template 1
[Date]
60
H7 Reporting Template 1
Contents
Summary
1.0 Introduction
2.0 O
bjectives
3.1. Introduction
3.4. Site Operational Records, Emergency Response Records and Records of any Land
4.1 Introduction
4.4 Vegetation
6.7.1. Introduction
61
H7 Reporting Template 1
References
B1 Figures
B2 Photographs
B3 Relevant Test Certificates
E1 Tabular
E2 Graphical
62
H7 Reporting Template 1
Summary
This document represents the Site Report for [name installation] submitted as part of an application to
the EHS [Reference Number, where known at this stage..........] for a permit to operate an installation
under Regulation 10 of the Pollution Prevention and Control Regulations ( Northern Ireland) 2003.
Records of the site and surrounding areas have been reviewed [along with operational site records] in
order to describe the condition of the site and, in particular, to identify any substance in, on or under
the land that may constitute a pollution risk to the land. Pollution prevention measures have been
identified and an assessment of pollution potential to land has been undertaken.
63
H7 Reporting Template 1
1.0 Introduction
[Enter details of persons and / or companies undertaking the assessments for the applicant and
any other additional details.]
The installation is located at [ADDRESS plus any further relevant location descriptor]. The
centre of the site is at National Grid Reference [8-figure grid reference ]. The site covers an
area of [...] Ha and can be seen in Figure 1 of Appendix A1.
[Describe features around the site of the installation, e.g. To the North of the site...(include brief
descriptions of land use, geographical or topographical features of note)]
[Briefly describe the operations to be conducted under the permit referencing specific sections
of the permit application.]
64
H7 Reporting Template 1
2.0 Objectives
♦ Identifying the environmental setting and land pollution history of the site;
♦ Identifying activities that will be conducted at the installation that may lead to land
pollution;
♦ Identifying and assessing the preventative measures that are in place to protect the land;
and
1. little likelihood that land pollution or leaks to land will occur during the future life of
the installation;
or there is:
2. a reasonable possibility that there is potential for current or future pollution of the
land from the installation.
65
H7 Reporting Template 1
3.1. Introduction
The following sections detail the sources of desk study information searched in order to
describe the condition of the installation and, in particular, to determine the potential for
substances to be present in, on or under the land associated with present and past uses of the
site and its surrounding areas.
[NOTE: It must be noted that this is not an exhaustive list and other sources of information may
exist that have relevance to your site. Such information should be detailed in Section 3.6 below
and collated in Appendix C6. As the text below is not an exhaustive list it is also not an all
inclusive list of data sources. The applicant will need to balance the resources available for this
data collection with the need to collect enough information at their site.]
The [named organisation] was requested to provide records of any Discharge Consents, Waste
Management Licences, Abstraction Licences, IPC Authorisations, PPC Permits and Land
Drainage Consents for the site and within ... metres of the site boundary.
The [named organisation} was requested to provide details of any Trade Effluent Consents for
the site.
The [named organisation] were requested to provide details of any Nature Conservation
Designations for the site and within 10 kilometres of the site boundary. The locations of
Designated Sites within the vicinity of the site are shown in Figure[s] [x] on Figure A5.
Geological and hydrogeological information for the site was obtained from the following sources
and is reproduced in Appendix C2, and a geological map is included as Figure 1 of
Appendix A2.
3.4 Site Operational Records, Emergency Response Records and Records of any
Land Pollution Incidents in the Vicinity of the Site
[Operational records from the site have been reviewed and are summarised in Appendix C4.
Records of any spills or discrepancies in stock control of potentially polluting substances have
been identified and their significance assessed. A chronology of the installation of suitable
pollution control measures has been produced with reference to the dates of any incidents
involving the loss of containment or the release of potentially polluting substances to land.]
[NOTE: Basically were the pollution prevention measures that exist now, in place and effective
at the time of any incidents? Existing installations only]
The [named organisation] was approached to provide records of any land pollution incidents
associated with the site and within […] metres of the site boundary, the response to which is
also included within Appendix C4.
Site operational layout plans, including the location and nature of underground services and
pipelines are shown on Figure[(s) 1 to x] in Appendix A3.
66
H7 Reporting Template 1
The location of bulk storage tanks and raw materials / product storage areas are shown on
Figure[/s x to x] in Appendix A6.
Site foul and surface water drainage plans are included as Figure[(s) 1 to x] in Appendix A4.
There has been no previous relevant site investigation or assessment undertaken at this site.
or
The following investigation[s] and assessment[s] [has/have] been undertaken on the site and
[is/are] reproduced in Appendix C5.
[The aerial extent of the investigations in relation to one another] or [The extent of this
investigation] with respect to the area of the site is shown on Figure 1 of Appendix C5.
The following additional sources of information have been queried and the results are shown in
Appendix C6.
67
H7 Reporting Template 1
4.1 Introduction
The purpose of the reconnaissance was to inspect the site and surrounding area for indicators
of potential land pollution. Site infrastructure was visually inspected [and in some cases
physically tested] to assess its competence and potential to cause or have caused releases to
land.
The following site features were inspected and as a result any indicators of potential areas of
land pollution are shown on Figure[(s) 2 to x] of Appendix B1. Photographs of features are
included in Appendix B2.
The locations of the tanks and pipe work are shown in Figure[(s) x] in Appendix B1.
[NOTE: Each tank should be clearly identified in the above list. The Figure(s) should be at a
scale such that individual tanks are clearly identifiable.
Where visual evidence suggests secondary containment may be compromised, for instance
cracking of bund floors or walls, it is strongly suggested that tests be carried out to assess their
significance.]
[Detail the integrity of areas of hardstanding and bunds (not covered in Section 4.2 above) that
provide a barrier to the downward percolation of substances. This should include process
areas, transfer areas, drum or waste storage areas etc.
4.4 Vegetation
[This section should provide a description of vegetation cover on the site and its immediate
surroundings for the area shown on Figure 1 of Appendix B2. It should include details of any
visual evidence of "stress" in vegetation on the site and surrounding areas. It is recognised that
68
H7 Reporting Template 1
on many sites there may be little or no vegetation due to the extent of hardstanding and
infrastructure. In such cases a statement to this effect would suffice.
Particular attention should be paid to the presence or absence of vegetation, the type and
diversity of vegetation, the health of the vegetation and the presence of any indicator species
tolerant to extreme soil conditions.]
[This section should include a description of any surface water features including such things
as evidence of discolouration and films, turbidity, odour, vegetation die-back, unusual or
impoverished benthic communities.]
[This section should describe any activities or procedures noted during the site reconnaissance
that could have or may lead to the loss of substances to the land, such as:
Where no such activities noted at the installation then a statement to this effect would be
sufficient.]
[This section should include details of the inspection of drainage at the site such as:
[This section should detail any other observations of relevance from the site reconnaissance.]
69
H7 Reporting Template 1
A list of all substances used, stored, manufactured (or waste by-products from the
manufacturing process) is contained in Appendix D1. An assessment of their pollution potential
has been made based upon their properties, toxicity and volume stored, used or manufactured.
Those substances thus identified in Appendix D1 have been taken forward to 5.2 below.
[NOTE: The first step in assessing polluting potential therefore is simply to confirm what
substances are present at the installation, making brief notes on the volumes stored
environmental properties (including toxicity, fate and behaviour) and assessment whether if
released would pollute land and/or groundwater.
From the desk study data collection the applicant must also list polluting substances that may
already be in or under the land, no quantification is required.
The applicant also needs to present the information on potentially polluting substances based
on the zoning of the site and the concept of relevant activities as explained in the guidance.
The applicant should introduce the work undertaken in this section and list the sources of
information consulted in undertaking this activity. The results should be tabulated and
presented in Appendix D1.]
The pollution preventative measures (physical infrastructure and those relating to testing,
inspection and maintenance) for each relevant activity associated with the potentially polluting
substances have been identified and their extent and condition assessed. The results of this
work are shown in Appendix D2.
Plans showing the location of these activities are shown in Appendix A6 and A7.
[NOTE: In accordance with the guidance the applicant needs to state the preventative
measures associated with each of the relevant activities.
The guidance introduces the terms primary, secondary and tertiary containment and check
monitoring to assist in undertaking this activity.
The applicant should introduce the work undertaken in this section and list the sources of
information consulted in undertaking this activity.
The example Table D2A and D2B have relevant activities numbered. Plans in Appendix A6 and
A7 should be similarly numbered (or other identifier used in Appendix D2) and be at scale such
that features of the relevant activity that would have an effect on the nature and location of any
land pollution can be clearly discerned]
Appendix D2 contains an assessment of the likelihood of land pollution from the installation.
[For all relevant activities at the installation there is little likelihood that land pollution or leaks to
the land will occur during the future life of the installation. It is the conclusion of this report that
reference data for the site does not need to be collected]
[NOTE: or]
70
H7 Reporting Template 1
[The assessment has identified relevant activities where there is a reasonable possibility that
there is or will be current or future pollution of the land from the installation. Reference Data will
be collected and reported within 6 months of the issue of a permit for the installation]
[NOTE: Delete as applicable. Using TABLES 2A and 2B in the guidance the applicant needs
to undertake the assessment of the likelihood of land pollution.
The applicant should introduce the work undertaken in this section and list the sources of
information consulted in undertaking this activity and summarise the areas of the site where the
assessment indicates there is the reasonable possibility of land pollution.
The applicant must supply a site drawing, to a suitable scale and detail, indicating the areas of
the site that present a “reasonable possibility” of pollution to the land and therefore will require
reference data to be collected within six months after a Permit has been issued. ]
71
H7 Reporting Template 1
3 e.g.]
This can be seen in plan form in Figure 1 and in cross-section in Figures [2 to X] in Appendix
A2.
This and succeeding sections should describe the extent, thickness, and characteristics of the
individual geological units listed above. The hydrogeological characteristics of the units must be
described.
The surface water features in the vicinity of the site are shown on Figure [x] of Appendix A5 and
are as follows:
[List surface water features. For watercourses include flow direction and details of any
culverting.]
Surface water drainage for the site is shown on Figure [x] of Appendix A4.
Groundwater beneath the site [is / is not] in hydraulic continuity with [name surface water
feature. Describe extent of groundwater / surface water interactions or best level of current
understanding, including areas of uncertainty.]
[Briefly outline the scope of the investigations referencing source material within Appendix C5.
Substances analysed for should only cover those substances and environmental media
identified in Appendix D1 and D2.
The laboratory or laboratories that undertook the analysis should wherever possible be UKAS
Accredited for those analytical techniques. Copies of the accreditation's, valid for the time of
analysis should be included in Appendix C5.
72
H7 Reporting Template 1
It is not good practice to present only summaries of the data set. The full data set should be
included in Appendix C5.]
[NOTE: Include information on other sensitive environmental receptors identified through the
desk study research and/or site reconnaissance]
[NOTE: Detail any land and/or groundwater pollution events as identified through desk study
research and/or site reconnaissance associated with the activities of the site.]
The site [has / has not] been divided into a series of zones based upon the site setting and the
possible (and actual) location of potentially polluting substances. These zones are shown on
Figure [x] of Appendix A7. Pollutant sources within each zone are shown as Figures [x to x] of
Appendix A7. Table 2 below has been split up on the basis of these Zones.
[List Zones with a description of each zone and the reason for its delineation.]
6.7.1. Introduction
The findings of the desk study and site reconnaissance (detailed above) have been used to
develop the conceptual site model (CSM) for the site. Uncertainties in the CSM are identified
and their significance discussed.
[NOTE: All of Section 6.0 of this report contributes to the overall Conceptual Site Model for the
site. This section requires a summary of the data in terms of contaminant sources, pathways
and receptors. The CSM can be in both tabular and / or graphical form and should be
presented in Appendix E. Detailed information on the requirements of A CSM can be found in
the Guidance. Applicants should refer to that document in the first instance. ]
Graphical representations of the CSM have been produced and are shown in Appendix E2.
[NOTE: Graphical representations are a powerful communication tool and should be used
where possible in conjunction with supporting text. The Guidance provides an example of a
Conceptual Site Model for a particular zone of a site]
In developing the conceptual model for the site the following assumptions have been made:
¾ Assuming a low permeability layer exists beneath the site isolating an Aquifer from any
potential pollutant sources on site.
¾ Hydrogeological conditions beneath the site (assuming depth to water table, permeability
of strata etc).
¾ Using values for environmental parameters from literature sources rather than
determining site-specific values.
The significance of these assumptions with respect to the likely fate and behaviour of the
substances identified needs to be discussed.]
73
H7 Reporting Template 1
Site Operation or Substance Relevant Activity Potential for 1. Records of pollution 2. Existence of Nature of Primary Testing and Inspection of Nature of Columns
Site Zone Pollution from the pollution Containment Primary Containment Secondary continue
relevant activity prevention Containment on to
measures table 2B
Name Unit Name substance, Detail the Detail the failure Detail any incidents of Do pollution Detail the nature of the Provide details of a Detail the nature
Ope ration and provide CAS RN if relevant activity mechanism and pollution or s pills from prevention storage vessel, including testing and ins pection of the secondary
refer to the appropriate as well for each potential pollution the relevant activity. measure exist volume, location and programme or reference containment.
relevant section as manufacturers substance where arising from the This can be based on for each provide unique reference to a separate document,
of the Permit Site product name. the location, loss of primary visual assessment during element of the number and indicate which e.g. pressure tests, leak
Report Volume stored. For pollution risk or containment site reconnaissance, relevant site plan it is shown on tests, material thickness
containing its mixtures provide pollution installation or other activity ? checks etc.
description breakdown of prevention records and data sources.
polluting substances measures differ Have measures been put
and percentage by in place to ensure no
volume. further pollution
incidents?
A) Factory Kerosene 1. Delivery by Spillage from road No evidence/records of Yes Road Tanker Compliant to British Site drains
heating and road tanker on spills or leaks Standard and DOT discharge to oil
steam tanker to installation roads Regulations interceptors prior
generation by installation entering road to soakaways
boiler using fuel drainage and
oil hence soakaways
2. Road Spillage from road Visual inspection Yes Road Tanker Compliant to British Tankers park
tanker off- tanker or delivery indicates land impacted Standard and DOT when filling tank
loading pipework to land with heating oil Regulations on Impermeable
pavement with
kerbs and falls
to underground
sealed tank of
30 cubic metre
capacity
Storage Failure of No evidence/records of Yes 200 cubic metre floating None Earth Bund
containment spills or leaks roof tank (ref A1 figure 3) containing tank
leading to spillage and fill point
to land
Fuel supply to Failure of Leaking underground No Underground steel Annual pressure test None
boiler plant underground pipe discovered during pipeline (ref A2 figure 3)
pipeline between general maintenance
the oil storage tank works in service trench
and boiler plant in 1999, pipe repaired.
leading to loss of
product to land
Boiler plant Spillage within No evidence/records of Yes Boiler Plant (ref A3 figure 6 monthly maintenance Kerbed concrete
boiler room to land spills or leaks 3) and inspection floor with no
or site drainage programme surface drainage
74
H7 Reporting Template 1
Continued Testing and Inspection of Nature of Testing and Inspection of 3. Adequacy of pollution 4. Are the 5. Is there an The assessment on the likelihood of pollution
from table Secondary Containment Tertiary Tertiary Containment prevention measures proposed adequate and hence the need to collect reference samples
2A Containment Yes/No Integrity documented will be made on the questions set in the GREEN
testing of manage ment columns on this table and supported by the
pollution system to information provided.
prevention demonstrate To make the case that there is little likelihood of
measures operator pollution the Applicant will need to provide the
Adequate manage ment and following ans wers:
Yes/No competence with Green Column 1 - No past pollution incidents or
the relevant spillages
activity? Green Column 2 - Yes pollution prevention
Provide details of a testing and Detail the nature Provide details of a Do the pollution prevention measures exist for each relevant activity
inspection programme or reference of the tertiary testing and ins pection measures and testing and Green Column 3 - Yes pollution prevention
to a separate document, e.g. Containment programme or reference inspection programme measures are adequate
pressure tests, leak tests, material to a separate document, comply with the indicative Green Column 4 - Yes adequate integrity testing
thickness checks etc. e.g. pressure tests, leak require ments set out in Box 5 undertaken or proposed
tests, material thickness ? Green Column 5 – Yes there is an adequate
checks etc. If yes then justify how. manage ment system
IF THE ABOVE CRITERIA CANNOT BE
SATISFIED THEN THERE IS THE
REASONABLE POSSIBILITY OF
POLLUTION AND THE OPERATOR WILL
NEED TO COLLECT REFERENCE DATA IN
THE SITE PROTECTION AND
MONITORING PROGRAMME
Little Likelihood of Reasonable Possibility
pollution ? of Pollution ?
6. Interceptors visually None None Yes Yes Yes
inspected monthly and
following any notified spill as
part of EMS ref x.x a -
7. High level alarm to notify None None No Yes No
need for emptying. No
Integrity testing
- a
8. None None None No No No
- a
9. None None None N/A Yes No
- a
10. Design quality assurance and None None Yes: Requirements of Yes Yes
inspection and monitoring surfacing in section 2.2.5 of
programme as part of EMS
ref x.x
the Sector Guidance
complied with as part of a -
EMS
75
Technical Guidance Note
IPPC H7 (Reporting Template 2)
Template for
Design of a
Collected
H7 Reporting Template 2
INTRODUCTION
This document presents a reporting template for Operators to use when preparing a
Site Protection and Monitoring Programme (SPMP) for Installations that require
reference data to be collected. It is designed to assist Operators with the
submission of the correct information in a suitable format to the EHS and should be
completed in full.
Guidance on the Protection of Land Under the PPC Regime: Application Site
Report and Site Protection and Monitoring Programme
In the template, those parts written in italics and enclosed in square brackets (i.e.
[italics] ), indicate where relevant information and or assessment is required to be
entered. In entering this information the italics should be deleted along with the
brackets or written over and the text reformatted to normal style.
Where text in italics appears prefixed with the word “Note” in bold ( i.e. [NOTE:
italics] ) this provides guidance on filling in the relevant [italics] part. On completion
of the [italics] part the [NOTE: italics] should be deleted from the final report prior to
submission.
76
H7 Reporting Template 2
DESIGN OF A
[Date]
77
H7 Reporting Template 2
Contents
Summary
1.0 Introduction
2.0 Objectives
3.1.1 General
Protocols
3.2.1 Zone 1
4.2.1 Location
Monitoring Infrastructure
78
H7 Reporting Template 2
6.0 References
7.0 Glossary
Appendices
79
H7 Reporting Template 2
Summary
This document represents the Site Protection and Monitoring Programme (SPMP) for
[installation site] submitted to the Environment and Heritage Service in pursuance of
Condition 4.1.7 of the Permit No. [Reference Number] (the "Permit") authorising the operation
of [the installation name] (the "installation").
This document is required to be submitted to the Agency within 2 months of the date of issue
of the Permit.
The Environmental Monitoring Programme for the installation is presented in Section 4 and
Appendices B to E. The results of routine monitoring will be collated into a Monitoring Report
and sent to the EHS by the 31st of January each year. The Monitoring Report will also contain
any recommendations for changes to the Site Protection and Monitoring Programme which
will be incorporated into the SPMP subject to the agreement, in writing, of the EHS. The
format of the Monitoring Report is given in Appendix E3.
The testing, inspection and maintenance programme for pollution prevention infrastructure at
the site (the Infrastructure Monitoring Programme) has been designed as detailed in Section
4.4 and Appendix E2.
80
H7 Reporting Template 2
1.0 Introduction
[Enter details of persons and / or companies undertaking the assessments for the
applicant and any other relevant additional details.]
The installation is located at [ADDRESS plus any further relevant location descriptor].
The centre of the site is at National Grid Reference [8-figure grid reference]. The site
covers an area of [enter area] Ha and can be seen in Figure 1 of Appendix A1.
[Briefly describe the operations conducted under the permit referencing specific
sections of the ASR and permit application.]
2.0 Objectives
♦ Obtaining sufficient information with respect to the site to allow the refinement of
the conceptual model of the site and its surroundings.
♦ [Designing a robust and adequate intrusive investigation, which would allow the
collection of Reference Data for the Installation.]
♦ [To collect data on the condition of the ground at the installation to assist in the
permit surrender process.]
♦ [To provide defensive monitoring at site boundaries for pollutant migration onto
the site of the installation.]
¾ To review and if necessary amend the inspection, testing and maintenance programme
for pollution prevention infrastructure at the installation to ensure their continued
integrity.
81
H7 Reporting Template 2
3.1.1 General
[NOTE: This investigation should be based upon the preliminary zoning of the site (if
applicable) detailed in Section 6.6 of the ASR]
[Detail any potential constraints upon the nature, aerial extent, scope, timings etc of the
investigation(s). For instance health and safety considerations limiting investigation and
sample collection, requirements within operational areas, avoiding compromising
bunding and other pollution control measures, known or suspected location of
underground tanks and services. Refer to specific Figures in Appendix A1].
[NOTE: Consideration must also be given to sensitive receptors and circumstances, for
instance avoiding creating preferential pathways for contaminant migration by
incorrectly installing boreholes.]
Refer to the relevant sections of the QA/QC plan in Appendix D to detail the controls
and checks on the sampling, sample handling and transport.]
[NOTE: In this context soils is taken to include all solid materials, not including
infrastructure at and below surface including made ground and geological materials.]
[Standard operating procedures for the use of the different techniques to be employed
at the site should be referenced and reproduced in Appendix B1.]
82
H7 Reporting Template 2
[As 3.1.3 but for any groundwaters (and associated dissolved, emulsified or free-
product pollutants) beneath the site identified as a pathway and / or receptor within the
conceptual model for the site.
Standard operating procedures for the use of the different techniques as employed at
the site should be referenced and reproduced in Appendix B2.]
[As 3.1.3 but for soil-gas and vapours beneath the site if volatile or semi-volatile organic
chemicals or biodegradable pollutants are identified beneath the site.
Standard operating procedures for the use of the different techniques as employed at
the site should be referenced and reproduced in Appendix B3.]
[NOTE: Whilst such investigation and sampling of soil-gas and vapours may not be
required to collect reference data for the site, such results can be used to screen areas
of the site for elevated pollutants and target further investigations.]
[As 3.1.3 but for any surface waters (and associated dissolved, emulsified or free-
product pollutants) on the site identified as a pathway and / or receptor within the
conceptual model for the site.
Standard operating procedures for the use of the different techniques as employed at
the site should be referenced and reproduced in Appendix B4.]
[As 3.1.3 but for the investigation and testing of any process and pollution control
infrastructure. Include details on the accuracy of any integrity testing procedure, e.g.
minimum leakage rate detectable using that technique.
Standard operating procedures for the use of the different techniques as employed at
the site should be referenced and reproduced in Appendix B5.]
[NOTE: For all the different media above, if no such investigation and sampling
occurred then delete the relevant section and renumber the Appendices accordingly]
Sample locations were chosen with reference to the sources, pathways and receptors
identified within the conceptual model for the site detailed in Section 6 of the ASR.
Sample locations for the site are shown on Figure [insert figure number(s)] of
Appendix A1.
Discussion of the selection, justification and design for each sample location with
respect to individual zones for the site are given in the following sections.
83
H7 Reporting Template 2
3.2.1 Zone 1
The sample locations for Zone 1 are shown on Figure [insert figure number] of
Appendix A1.
Discuss the choice of location, the number of samples, the depths of samples and the
environmental media sampled with respect to the conceptual model and particular
source-pathway-receptor relationships.]
[As above.]
[NOTE: Justifications can be given for groups of samples relating to particular sources
or SPR relationships or other reasons identified from the conceptual model rather than
on a sample by sample basis. Each sample relating to a group must be referenced in
the particular section of the text.]
3.2.2 Zone 2
Sample locations for Zone 2 are shown on Figure [insert figure number] of
Appendix A1.
[etc]
The analytical suite for each Zone was chosen by reviewing Table D2 of Appendix D of
the ASR and is shown in Tables C1 to C[insert table number] of Appendix C1.
[The conceptual model for the site indicated the potential for contaminant migration of
[List substance(s) or refer to table inserted below] in groundwater from areas adjacent
to the site. As a result these have been added to the relevant Table in Appendix C1 for
both soil and groundwater.]
[Due to the hydrogeological conditions beneath the site identified within the conceptual
model, there is the potential for the migration in groundwater of potentially polluting
substances from zone(s) x] to zone(s) y]. As a result, substances identified in Table D2
of Appendix D of the ASR for zone(s) x] have been added to the relevant Table in
Appendix C1 for both soil and groundwater.]
84
H7 Reporting Template 2
The laboratory analytical technique for each analysis is referenced in Tables C1 to C[X]
[and is reproduced in Appendix C2]
[NOTE: If the technique is UKAS accredited then it is sufficient to include the UKAS
reference number in the relevant column of Tables C1 to C[X] in Appendix C. If the
laboratory does not have UKAS accreditation then the analytical method summary,
method validation test data and the on-going quality control method statements should
be reproduced in Appendix C2.]
Where field testing of samples has occurred, the standard operating procedure is
referenced in Tables C1 to C[X] and reproduced in Appendix C2.
Detection Limits for each analytical and field technique are shown in Tables C1 to C[X].
The following sections provide a justification for choosing a particular technique for a
particular substance in a particular phase. The detection limits of a substance using
that technique is justified with respect to expected background concentrations and
likely pollutant distribution and concentration.
[NOTE: Choice of analytical technique and thus detection limits should be made on a
site-specific basis. It is a general rule that as one lowers the detection limits one
increases the cost of analysis. The EHS has not set specific detection limits for the
preparation of a Site Protection and Monitoring Programme as such levels would,
necessarily, have to be the most stringent to be protective of the environment in all
cases. Careful consideration should be given to detection limits and the operator or
their consultants may wish to liaise with the EHS prior to undertaking site investigations
or analysis to agree them. Too high a limit could mask environmentally significant
pollutant distributions at the site. A statement of Reference Data using too high a limit
could, allow an unacceptable deterioration in land quality (through operations allowed
under the permit) up to that level. In such circumstances the EHS may not accept this
Scope SPMP and modifications could be required.]
3.3.2.1 Substance A
[Justify the choice of analytical technique for all phases of the substance (i.e. free-
product, dissolved in porewater / groundwater / surface water, sorbed to soil / rock
matrix, soil-gas or vapour). Justify detection limits with respect to collecting reference
data for the site. Discuss any potential issues with interference of the analytical
technique from other substances identified in Table D2 of Appendix D of the ASR.]
3.3.2.2 Substance B
[etc]
[NOTE: or]
85
H7 Reporting Template 2
Appendix D1 contains the sampling and analytical quality assurance and quality control
plan.
[Detail the objectives of the Environmental Monitoring Programme for the Installation
(see Section 5.3 of the "Guidance on the Protection of Land under the PPC Regime:
Application Site Report and Site Protection and Monitoring Programme")]
[Detail the objectives of the Infrastructure Monitoring Programme for the Installation
(see Section 5.3 of the "Guidance on the Protection of Land under the PPC Regime:
Application Site Report and Site Protection and Monitoring Programme")]
4.2.1 Location
[NOTE: Figures must be at a scale such that the location of monitoring points could be
accurately determined on the ground. As such a number of Figures may be needed for
large installations]
No on-going groundwater monitoring will occur at the installation during the life of the
permit.
[Justify the lack of groundwater monitoring at the installation, refer to specific sections
above or within the ASR]
[NOTE: or]
86
H7 Reporting Template 2
[Justify the proposed location of all groundwater monitoring points with respect to
specific monitoring objectives, and specific sources or pathways for pollution migration]
No on-going soil vapour monitoring will occur at the installation during the life of the
permit.
[Justify the lack of soil vapour monitoring at the installation, refer to specific sections
above or within the ASR]
[NOTE: or]
Proposed completion details of each soil vapour monitoring installation are contained in
Appendix E1. Each installation will be finished with a lockable cover and designed to
prevent the ingress of surface water.
[NOTE: Soil vapour monitoring will not give quantitative data on land or groundwater
quality. With careful design, location and a suitable monitoring programme, it may
provide useful defensive monitoring for volatile and semi-volatile organic compounds
giving warning of a loss of containment.]
[Justify the location of all soil vapour monitoring points with respect to specific
monitoring objectives, and specific sources or pathways for pollution migration]
No on-going soil monitoring will occur at the installation during the life of the permit.
[Justify the lack of soil monitoring at the installation, refer to specific sections above or
within the ASR]
[NOTE: or]
The design and proposed completion details of soil monitoring points are contained in
Appendix E1.
[NOTE: Soil monitoring can be the repeated sampling and analysis of soil at a location.
However due to cost constraints it is recognised that soil monitoring is unlikely to be an
attractive or well used monitoring strategy. The installation of lysimeters (or other
unsaturated zone soil moisture monitoring equipment) may be a useful monitoring tool
given the right circumstances and such monitoring should be considered within this
section.]
[Justify the location of all soil monitoring points with respect to specific monitoring
objectives, and specific sources or pathways for pollution migration]
87
H7 Reporting Template 2
[NOTE: Most groundwater monitoring boreholes will require periodic maintenance. The
most common problem is associated with silt accumulation in the base of a borehole,
which can completely block screened intervals. It is expected that the inspection
frequency will be high in the initial stages of the monitoring programme until the
characteristics of the deterioration in the performance of the infrastructure can be
ascertained.]
The protocols for analysis will remain the same as those to be used for the
investigations to collect reference data detailed in Section 3.3 above and reproduced in
Appendix C.
[NOTE: or]
Different analytical protocols will be used for the regular environmental monitoring as
listed below and reproduced in full in Appendix C.
[Detail different protocols and justify their use on an environmental setting and
substance specific basis as per Sections 3.1 and 3.3 above]
88
H7 Reporting Template 2
assurance and quality control plan. Roles and responsibilities for monitoring and
ensuring adequate competence of staff are shown in Appendix E1.
[NOTE: or]
[Detail the methods, and procedures for assessing monitoring data as a result of
operating this Site Protection and Monitoring Programme (within an overall EMS for the
installation.)]
Summaries of the monitoring data will be sent to the EHS on the 31st of January each
year along with the results of the data assessment, and any recommendations for
amendments to the Monitoring Programme.
89
H7 Reporting Template 2
[Detail the recording and data management procedures for environmental monitoring
data and the results of infrastructure monitoring and of emergencies.]
[NOTE: One of the purposes of the SPMP is to provide the operator with data to aid in
the process of surrendering of a Permit. In order to surrender a Permit the operator
must demonstrate to the EHS that the site is in a satisfactory state. A suitably designed
monitoring programme should provide sufficient data to demonstrate satisfactory state
without recourse to additional intrusive investigations. However this is encumbant upon
suitable procedures to record such data, or summaries thereof.]
[Detail other issues relevant to the protection of ground or groundwater within the
installation, such as general staff awareness and specific training. If necessary append
additional information within Appendix F]
6.0 References
[List references]
7.0 Glossary
[NOTE: The glossary should contain an explanation of all acronyms and industry
specific jargon used within the report]
90
H7 Reporting Template 2
APPENDIX A
Contents
A1 Plans
A2 Photographs
91
H7 Reporting Template 2
APPENDIX B
Contents
B1 Soil
B2 Groundwater
B4 Surface Water
B5 Infrastructure
92
H7 Reporting Template 2
APPENDIX C
Contents
C1 Tables
C2 Analytical Techniques
93
H7 Reporting Template 2
APPENDIX D
Contents
94
H7 Reporting Template 2
APPENDIX E
Contents
95
H7 Reporting Template 2
APPENDIX F
OTHER ISSUES
Contents
F1 [add title]
96
Technical Guidance Note
IPPC H7 (Reporting Template 3)
Template for
Collected
H7 Reporting Template 3
INTRODUCTION
This document presents a reporting template for Operators to use when preparing a
Site Protection and Monitoring Programme (SPMP) for Installations that do not
require reference data to be collected. It is designed to assist Operators with the
submission of the correct information in a suitable format to the EHS and should be
completed in full.
Guidance on the Protection of Land Under the PPC Regime: Application Site
Report and Site Protection and Monitoring Programme
In the template, those parts written in italics and enclosed in square brackets (i.e.
[italics] ), indicate where relevant information and or assessment is required to be
entered. In entering this information the italics should be deleted along with the
brackets or written over and the text reformatted to normal style.
Where text in italics appears prefixed with the word “Note” in bold ( i.e. [NOTE:
italics] ) this provides guidance on filling in the relevant [italics] part. On completion
of the [italics] part the [NOTE: italics] should be deleted from the final report prior to
submission.
97
H7 Reporting Template 3
DESIGN OF
COLLECTED
[Date]
98
H7 Reporting Template 3
Contents
Summary
1.0 Introduction
2.0 Objectives
3.1.1 General
Protocols
3.2.1 Zone 1
4.2.1 Location
Monitoring Infrastructure
99
H7 Reporting Template 3
6.0 References
7.0 Glossary
Appendices
100
H7 Reporting Template 3
Summary
This document represents the Site Protection and Monitoring Programme (SPMP) for [name
installation] submitted to the Environment and Heritage Service in pursuance of Permit No.
[Reference Number] (the "Permit") authorising the operation of [the installation name] (the
"installation").
This design document is required to be submitted to the EHS within 2 months of the date of
issue of the Permit.
[An Environmental Monitoring Programme for the site is presented in Section 3 and
Appendices B to E. The results of routine monitoring will be collated into a Monitoring Report
and sent to the EHS on the 31st of January each year. The Monitoring Report will also
contain recommendations for changes to the Site Protection and Monitoring Programme (if
any) to be formally agreed, in writing, by the EHS. The format of the Monitoring Report is
given in Appendix E3.]
[NOTE: Whilst, by condition, the Permit does not require environmental monitoring there may
be good reasons for including such monitoring in the SPMP (see Section 5.3 of the "Guidance
on the Protection of Land under the PPC Regime: Application Site Report and Site Protection
and Monitoring Programme")]
[If no environmental monitoring is to occur then delete the relevant sub-sections of Section 3,
i.e. 3.1.1, 3.2 and 3.3]
The testing, inspection and maintenance programme for pollution prevention infrastructure at
the site (the Infrastructure Monitoring Programme) has been designed as detailed in Section
4.4 and Appendix E2.
101
H7 Reporting Template 3
1.0 Introduction
[Enter details of persons and / or companies undertaking the assessments for the
applicant and any other relevant additional details.]
The installation is located at [ADDRESS plus any further relevant location descriptor].
The centre of the site is at National Grid Reference [8-figure grid ref ]. The site covers
and area of [enter area] Ha and can be seen in Figure 1 of Appendix A1.
[Briefly describe the operations conducted under the permit referencing specific
sections of the ASR and permit application.]
2.0 Objectives
♦ [To collect data on the condition of the ground at the installation to assist
in the permit surrender process.]
[Detail the objectives of the Environmental Monitoring Programme for the Installation
(see Section 5.3 of the "Guidance on the Protection of Land under the PPC Regime:
Application Site Report and Site Protection and Monitoring Programme")]
102
H7 Reporting Template 3
[Detail the objectives of the Infrastructure Monitoring Programme for the Installation
(see Section 5.3 of the "Guidance on the Protection of Land under the PPC Regime:
Application Site Report and Site Protection and Monitoring Programme")]
3.2.1 Location
[NOTE: Figures must be at a scale such that the location of monitoring points could be
accurately determined on the ground. As such a number of Figures may be needed for
large installations.
If monitoring of the media in the sub-sections below will not occur then delete that sub-
section and re-number the remaining sub-sections accordingly]
[Justify the proposed location of all groundwater monitoring points with respect to
specific monitoring objectives, and specific sources or pathways for pollution migration]
Proposed completion details of each soil vapour monitoring installation are contained in
Appendix E1. Each installation will be finished with a lockable cover and designed to
prevent the ingress of surface water.
[NOTE: Soil vapour monitoring will not give quantitative data on land or groundwater
quality. With careful design, location and a suitable monitoring programme, it may
provide useful defensive monitoring for volatile and semi-volatile organic compounds
giving warning of a loss of containment.]
[Justify the location of all soil vapour monitoring points with respect to specific
monitoring objectives, and specific sources or pathways for pollution migration]
The design and proposed completion details of soil monitoring points are contained in
Appendix E1.
[NOTE: Soil monitoring can be the repeated sampling and analysis of soil at a location.
However due to cost constraints it is recognised that soil monitoring is unlikely to be an
attractive or well used monitoring strategy. The installation of lysimeters (or other
unsaturated zone soil moisture monitoring equipment) may be a useful monitoring tool
103
H7 Reporting Template 3
given the right circumstances and such monitoring should be considered within this
section.]
[Justify the location of all soil monitoring points with respect to specific monitoring
objectives, and specific sources or pathways for pollution migration]
[NOTE: Most groundwater monitoring boreholes will require periodic maintenance. The
most common problem is associated with silt accumulation in the base of a borehole,
which can completely block screened intervals. It is expected that the inspection
frequency will be high in the initial stages of the monitoring programme until the
characteristics of the deterioration in the performance of the infrastructure can be
ascertained.]
The protocols for analysis are summarised below and reproduced in Appendix C.
[Detail different protocols and justify their use on an environmental setting and
substance specific basis]
104
H7 Reporting Template 3
[NOTE: or]
This section summarises alterations to the existing EMS that are detailed in
Appendix E2.
[Detail the methods, and procedures for assessing monitoring data as a result of
operating this Site Protection and Monitoring Programme (within an overall EMS for the
installation.)]
Summaries of the monitoring data will be sent to the EHS on the 31st of January each
year along with the results of the data assessment, and any recommendations for
amendments to the Monitoring Programme.
105
H7 Reporting Template 3
The formats for standard and emergency reporting procedures are shown in
Appendix E3.
[Detail the recording and data management procedures for environmental monitoring
data and the results of infrastructure monitoring and of emergencies.]
[NOTE: One of the purposes of the SPMP is to provide the operator with data to aid in
the process of surrendering of a Permit. In order to surrender a Permit the operator
must demonstrate to the EHS that the site is in a satisfactory state. A suitably designed
monitoring programme should provide sufficient data to demonstrate satisfactory state
without recourse to additional intrusive investigations. However this is encumbant upon
suitable procedures to record such data, or summaries thereof.]
[Detail other issues relevant to the protection of ground or groundwater within the
installation, such as general staff awareness and specific training. If necessary append
additional information within Appendix F]
5.0 References
[List references]
6.0 Glossary
[NOTE: The glossary should contain an explanation of all acronyms and industry
specific jargon used within the report]
106
H7 Reporting Template 3
APPENDIX A
Contents
A1 Plans
A2 Photographs
107
H7 Reporting Template 3
APPENDIX B
SAMPLING PROTOCOLS
Contents
B1 Soil
B2 Groundwater
B4 Surface Water
B5 Infrastructure
108
H7 Reporting Template 3
APPENDIX C
Contents
C1 Tables
C2 Analytical Techniques
109
H7 Reporting Template 3
APPENDIX D
Contents
110
H7 Reporting Template 3
APPENDIX E
Contents
111
H7 Reporting Template 3
APPENDIX F
OTHER ISSUES
Contents
F1 [add title]
112
Technical Guidance Note
IPPC H7 (Reporting Template 4)
Template for
Required
H7 Reporting Template 4
INTRODUCTION
This document presents a reporting template for Operators to use when reporting the
first phase of a Site Protection and Monitoring Programme (SPMP) for Installations
that require reference data to be collected. It is designed to assist Operators with the
submission of the correct information in a suitable format to the EHS and should be
completed in full.
Guidance on the Protection of Land Under the PPC Regime: Application Site
Report and Site Protection and Monitoring Programme
In the template, those parts written in italics and enclosed in square brackets (i.e.
[italics] ), indicate where relevant information and or assessment is required to be
entered. In entering this information the italics should be deleted along with the
brackets or written over and the text reformatted to normal style.
Where text in italics appears prefixed with the word “Note” in bold ( i.e. [NOTE:
italics] ) this provides guidance on filling in the relevant [italics] part. On completion
of the [italics] part the [NOTE: italics] should be deleted from the final report prior to
submission.
113
H7 Reporting Template 4
[Date]
114
H7 Reporting Template 4
Contents
Summary
1.0 Introduction
Model
2.4.2 Zone 1
6.0 References
7.0 Glossary
Appendices
115
H7 Reporting Template 4
116
H7 Reporting Template 4
Summary
This document represents the first report of the Site Protection and Monitoring Programme
(SPMP) for [name site] submitted to the Environment and Heritage Service in pursuance of
Permit No. [Reference Number] (the "Permit") authorising the operation of [the installation
name] (the "installation").
This report sets the reference data for the installation which are summarised in Section 4 and
Appendix G.
The monitoring programme for the site is presented in Section 4 of the Design SPMP.
[NOTE: or]
[As a result of the investigations the monitoring programme has been amended and is
provided as Appendix H to this document. This supercedes the Monitoring Programme in the
Design SPMP]
117
H7 Reporting Template 4
1.0 Introduction
[Enter details of persons and / or companies undertaking the assessments for the
applicant and any other additional details.]
The installation is located at [ADDRESS plus any further relevant location descriptor].
The centre of the site is at National Grid Reference [8-figure grid reference ]. The site
covers and area of [enter area] Ha and can be seen in Figure 1 of Appendix A1.
The investigations and sampling undertaken at the site was in accordance with the
Section 3 and Appendices B, C and D of the Design SPMP.
[NOTE: or]
The following Sections detail variations to and deviations from the Design SPMP
2.1.1 General
[Detail any constraints upon the nature, aerial extent, scope, timings etc encountered
during the iinvestigation(s) that were not identified within the Scope. Refer to specific
Figures in Appendix A1].
Refer to the relevant sections of the QA/QC plan in Appendix F to detail the controls
and checks on the sampling, sample handling and transport.]
[NOTE: In this context soil is taken to include all solid materials, not including
infrastructure at and below surface including made ground and geological materials.]
[New or modified standard operating procedures for the use of the different techniques
as employed at the site should be referenced and reproduced in Appendix B1.]
118
H7 Reporting Template 4
[As 2.1.3 but for any groundwaters (and associated dissolved, emulsified or free-
product pollutants) beneath the site identified as a pathway and / or receptor within the
conceptual model for the site.
New or modified standard operating procedures for the use of the different techniques
as employed at the site should be referenced and reproduced in Appendix B2.]
[As 2.1.3 but for soil-gas and vapours beneath the site if volatile or semi-volatile organic
chemicals or biodegradable pollutants are identified beneath the site.
New or modified standard operating procedures for the use of the different techniques
as employed at the site should be referenced and reproduced in Appendix B3.]
[As 2.1.3 but for any surface waters (and associated dissolved, emulsified or free-
product pollutants) on the site identified as a pathway and / or receptor within the
conceptual model for the site.
New or modified standard operating procedures for the use of the different techniques
as employed at the site should be referenced and reproduced in Appendix B4.]
[As 2.1.3 but for the investigation and testing of any process and pollution control
infrastructure. Include details on the accuracy of any integrity testing procedure, e.g.
minimum leakage rate detectable using that technique.
New or modified standard operating procedures for the use of the different techniques
as employed at the site should be referenced and reproduced in Appendix B5.]
The number and location of samples remain the same as agreed in the Design SPMP.
[or]
The following Sections detail those sample locations that deviate from those agreed in
the Design SPMP. The following table lists all sample locations agreed in the Design
SPMP and identifies all the amendments [and augmentations].
Discussion of the selection, justification and design for each additional or modified
sample location with respect to individual zones for the site are given in the following
sections.
Samples have been referenced using the classification system detailed in the Design
SPMP (Section 3.2)
119
H7 Reporting Template 4
The findings of investigations are discussed in Section 2.4 below and all physical
ground results (borehole logs, trial pit logs, etc) are reproduced in Appendix D.
[2.2.1 Zone 1
The modified sample locations for Zone 1 are shown on Figure [insert figure number] of
Appendix A1.]
Discuss the choice of location, the number of samples, the depths of samples and the
environmental media sampled with respect to the conceptual model and particular
source-pathway-receptor relationships.
As above.]
[NOTE: Justifications can be given for groups of samples relating to particular sources
or SPR relationships or other reasons identified from the conceptual model rather than
on a sample by sample basis. Each sample relating to a group must be referenced in
the particular section of the text.]
[2.2.2 Zone 2
The modified sample locations for Zone 2 are shown on Figure [insert figure number] of
Appendix A1.
[etc]
120
H7 Reporting Template 4
The analytical suites agreed in the Design SPMP were used in the analysis of samples
from the investigation to collect reference data.
[or]
The analytical suite for each Zone was modified for the following reasons. They are
shown in Tables C1 to C[insert table number] of Appendix C1.
[NOTE: Delete as applicable. Justify any modifications to the analytical suites in section
2.3.2 below]
The laboratory / field analytical techniques and detection limits for each analysis were
as agreed in the Design SPMP.
[or]
[NOTE: If the technique is UKAS accredited then it is sufficient to include the UKAS
reference number in the relevant column of Tables C1 to CX in Appendix C. If the
laboratory does not have UKAS accreditation then the analytical method summary,
method validation test data and the on-going quality control method statements should
be reproduced in Appendix C2.]
Detection Limits for each modified analytical and field technique are shown in Tables
C1 to C[X].
The following sections provide a justification for modifying a particular technique for a
particular substance in a particular phase. Any resultant modification to the detection
limits of a substance using that technique is justified with respect to expected
background concentrations and likely pollutant distribution and concentration.
[NOTE: Choice of analytical technique and thus detection limits should be made on a
site-specific basis. Careful consideration should be given to detection limits and the
operator or its consultants may wish to liaise with and seek the Agency's agreement
prior to undertaking site investigations or analysis. It should be noted that the use of too
high a limit could mask environmentally significant pollutant distributions at the site,
making it more difficult to assess the impact of any pollution which occurs from the
permitted installation In such circumstances the Agency might not accept the SPMP
and additional investigations / analysis might be required.]
2.3.2.1 Substance A
[Justify the modification to the analytical technique for all phases of the substance (i.e.
free-product, dissolved in porewater / groundwater / surface water, sorbed to soil / rock
matrix, soil-gas or vapour). Justify detection limits with respect to collecting reference
data for the site. Discuss any potential issues with interference of the analytical
technique from other substances identified in Table G1 of Appendix G.]
121
H7 Reporting Template 4
2.3.2.2 Substance B
[etc]
or
[NOTE: It is not yet EHS policy to insist upon the use of laboratories with UKAS
Accreditation for each specific laboratory analysis for soil sampling. However the UKAS
Accreditation is the UK's recognised laboratory quality assurance scheme and use of
such laboratories is strongly advised as best practice.]
There were no modifications to the agreed sampling and analytical quality assurance
and quality control plan and Appendix F2 the results obtained from the QC plan.
[Discuss the findings of the QC plan with respect to the implications on the reliability
and accuracy of the analytical results presented as the statement of baseline condition.
If analysis data is presented in Appendix E which fell outside of the UKAS
Accreditation, the reason for the failure should be indicated in the relevant part of
Appendix F. The implications of this failure of analytical quality control on reliability of
the analytical result must be discussed within this and Section 2.5.1 below.]
[Briefly outline the results of the physical investigation for the site as a whole. e.g.
122
H7 Reporting Template 4
2.4.2 Zone 1
[Detail the findings and observations from the investigation within zone 1. Refer to
photographs reproduced within Appendix A2 to illustrate points, pollutant sources,
ground and contaminant conditions at sample locations referring to the full data set
reproduced within Appendix E. Refer to specific borehole logs, trial pit logs or the
results and interpretations of other investigation techniques (if appropriate) reproduced
within Appendix D.]
[Detail the pollutant concentrations and distributions for the different geological strata
and groundwater(s) within the zone. Refer to Figures and Plans showing contaminant
concentration variations across the zone to be included in Appendix A3.]
[NOTE: Only include Figures to illustrate particular points or for those pollutants with
elevated and variable concentrations.]
2.4.3 Zone 2
[As Above
etc]
[NOTE: The purpose of this Section is to examine the analytical data collected for each
zone to determine whether it is sufficient to adequately characterise baseline conditions
at the site]
2.5.1.1 Zone 1
[Discuss the need for any subdivision of the zone on the basis of the occurrence and
distribution of pollution.]
[NOTE: It is necessary to examine the analytical data to determine whether any sample
location represents a hot-spot of pollution associated with a particular source or
sources. If a sample or (group of samples) is a hot-spot (i.e. from a different data
population) then the zone should be sub-divided into two zones, one enclosing the hot
spot. The spatial distribution of the data should be assessed to determine whether
sufficient data exists to delineate this new zone(s). If not, further investigation and
sampling may be required. The new zone(s) should be numbered in a way so as to
avoid confusion with the existing zoning of the site (e.g. Zone 1A, 1B etc). The new
zones should be shown in Figures in Appendix A3.]
2.5.1.2 Zone 2
[As Above]
[All known sources of elevated levels of pollutants within the zones should be identified
at this stage (from the assessments in Section 3.5.1 above along with a reasoned
assessment of the implications for operations to be conducted under the permit. For
instance:
Pollution is identified from activities that will continue under the terms of a
permit: The cause of the pollution should be identified. Any necessary improvements
to an EMS or pollution control or other infrastructure to prevent any further pollution
123
H7 Reporting Template 4
should be identified within Section 6 below (or cross reference to relevant parts of
permit application/application site report). It is considered that operational monitoring
(of ground or groundwater to determine the effectiveness of these improvements)
should always be designed and undertaken as part of the EMS for the installation
under these circumstances.
Pollution is identified from activities that will not continue (historic activities)
under the terms of a permit: The cause of the pollution should be identified and it
should be confirmed that there is no potential for additional pollution from that source.
Other potential source(s) of the same pollutant within the zone will continue or come
into operation under the terms of a permit. The implications for the requirements for
operational records and to the EMS to aid in an eventual permit surrender process
should be discussed in Section 5 below.
Pollution is identified that has migrated onto or beneath the site of the
installation from adjacent activities: The cause of the pollution should be identified
or hypothesised. There is / are potential source(s) of the same pollutant within the zone
that will continue or come into operation under the terms of a permit. The implications
for the requirements for operational records, operational monitoring and to the EMS to
aid in the permit surrender process should be discussed in Section 5 below.]
The sources of all elevated levels of pollutants within the ground or groundwater have
been identified and attributed within Section 3.5.2 above.
[NOTE: or]
[This section should identify areas of pollution where the source is unknown / uncertain
and could be a result of activities which are now covered by the Permit. If known,
potential sources of the pollutants should be detailed along with an assessment of the
data required to prove or disprove those sources]
[NOTE: In completing this and the preceding section it must be emphasised that
only those substances used (etc) under the terms of the permit will have been
investigated for. The EHS will therefore conclude that the permitted activities are
the source of the pollution unless an alternative source is confirmed. It will not be
considered sufficient to hypothosise an alternative source without direct physical or
documentary evidence. Statements of the integrity of pollution prevention infrastructure
will not suffice to exclude permitted activities if an alternative source is not proved.]
Reference Data for the site have been collected by this report and are presented in
summary as Appendix G2.
[NOTE: As detailed in Section 6 of the " Guidance on the Protection of Land under the
PPC Regime: Application Site Report and Site Protection and Monitoring Programme",
Reference Data are collected for the installation at the time sampling, investigation,
monitoring and / or testing occurs. They are not set at the date six months after the
issue of the permit or the date at which the SPP is received by the EHS (if different).]
The investigations to collect reference data have not led to any amendments to the
monitoring and inspection programme.
[or]
124
H7 Reporting Template 4
4.2.1 Location
[NOTE: Figures must be at a scale such that the location of monitoring points could be
accurately determined on the ground. As such a number of Figures may be needed for
large installations]
The log and completion details of each groundwater monitoring installation are
contained in Appendix H1. Each monitoring point is finished with a lockable cover and
is designed to prevent the ingress of surface water.
[Justify any modifications to the location of all groundwater monitoring points with
respect to specific monitoring objectives, and specific sources or pathways for pollution
migration]
No on-going soil vapour monitoring will occur at the installation during the life of the
permit.
125
H7 Reporting Template 4
[Justify the lack of soil vapour monitoring at the installation, refer to specific sections
[NOTE: or]
[Logs (if applicable) and] completion details of each soil vapour monitoring installation
are contained in Appendix H1. Each installation is finished with a lockable cover and
designed to prevent the ingress of surface water drainage.
[NOTE: Soil vapour monitoring will not give quantitative data on land or groundwater
quality. With careful design, location and a suitable monitoring programme, it may
provide useful defensive monitoring for volatile and semi-volatile organic compounds
giving warning of a loss of containment.]
[Justify the location of all soil vapour monitoring points with respect to specific
monitoring objectives, and specific sources or pathways for pollution migration]
No on-going soil monitoring will occur at the installation during the life of the permit.
[Justify the lack of soil monitoring at the installation, refer to specific sections above or
within the ISR]
[NOTE: or]
The design and completion details of soil monitoring points are contained in
Appendix H1.
[NOTE: Soil monitoring can be the repeated sampling and analysis of soil at a location.
However due to cost constraints it is recognised that soil monitoring is unlikely to be an
attractive or well used monitoring strategy. The installation of lysimeters (or other
unsaturated zone moisture monitoring equipment) may be a useful monitoring tool
given the right circumstances and such monitoring should be considered within this
section.]
[Justify the location of all soil monitoring points with respect to specific monitoring
objectives, and specific sources or pathways for pollution migration]
[NOTE: Most groundwater monitoring boreholes will require periodic maintenance. The
most common problem is associated with silt accumulation in the base of a borehole,
which can completely block screened intervals. It is expected that the inspection
frequency will be high in the initial stages of the monitoring programme until the
characteristics of the deterioration in the performance of the infrastructure can be
ascertained.]
126
H7 Reporting Template 4
The protocols for analysis remain the same as those used for the investigations to
determine baseline conditions detailed in Section 3.3 above and reproduced in
Appendix C.
[NOTE: or]
Different analytical protocols were used for this additional round of investigation as
listed below and reproduced in full in Appendix C.
[Detail different protocols and justify their use on an environmental setting and
substance specific basis as per Sections 3.1 and 3.3 above]
The infrastructure monitoring programme meets the objectives identified within Section
5.1.2 above and thus there are no changes to the EMS programme for the installation
summarised within the Permit Application.
[NOTE: or]
[NOTE: The SPP is not intended to replace or reproduce an existing EMS. HOWEVER
the operator shall ensure, and demonstrate, that the changes identified within this and
preceding Sections are incorporated and implemented within the existing inspection,
testing and maintenance programme.]
[Detail the methods, and procedures for assessing monitoring data as a result of
operating this Site Protection Plan within an overall EMS for the installation.]
127
H7 Reporting Template 4
[NOTE: It is certain that the concentration at each monitoring location will change for
each monitoring round even if there are no anthropological influences (e.g. due to
seasonal variations, sample and analytical uncertainty etc). Monitoring data should be
assessed in a time series to determine the range of natural variation in pollutant
concentrations. Values should be set that trigger more intensive monitoring and
investigation if they are exceeded. The monitoring programme for the site should be
assessed in the light of the data it produces. It is hoped that the frequency of
monitoring would reduce as trends in pollutant concentrations are characterised and
improvements to pollution prevention infrastructure (if any were necessary) are shown
to have worked.]
Summaries of the monitoring data will be sent to the EHS on the 31st of January each
year along with the results of the data assessment, and any recommendations for
amendments to the monitoring programme.
The formats for standard and emergency reporting procedures are shown in Appendix
H3.
[Detail the recording and data management procedures for monitoring data and the
results of inspection and testing of pollution prevention infrastructure and of
emergencies.]
[NOTE: One of the purposes of the SPMP is to provide the operator with data to aid in
the process of surrendering of a Permit. In order to surrender a Permit the operator
must demonstrate to the EHS that the site is in a satisfactory state. A suitably designed
monitoring, testing and inspection programme should provide sufficient data to
demonstrate satisfactory state without recourse to additional intrusive investigations.
However this is incumbent upon suitable procedures to record such data, or summaries
of such data.]
[Detail other issues relevant to the protection of ground or groundwater within the
installation, such as general staff awareness and specific training. If necessary append
additional information within Appendix I]
6.0 References
[List references]
7.0 Glossary
[NOTE: The glossary should contain an explanation of all acronyms and industry specific
jargon used within the report]
128
H7 Reporting Template 4
APPENDIX A
Contents
A1 Plans
A2 Photographs
129
H7 Reporting Template 4
APPENDIX B
Contents
B1 Soil
B2 Groundwater
B4 Surface Water
B5 Infrastructure
130
H7 Reporting Template 4
APPENDIX C
Contents
C1 Tables
C2 Analytical Techniques
131
H7 Reporting Template 4
APPENDIX D
Contents
D4 [e.g.
D5
132
H7 Reporting Template 4
APPENDIX E
Contents
E1 [e.g. Zone 1]
E2 [e.g. Zone 2]
E3 [e.g. etc
133
H7 Reporting Template 4
APPENDIX F
Contents
F2 Results of the Sampling and Analytical Quality Assurance and Quality Control Plan
134
H7 Reporting Template 4
APPENDIX G
REFERENCE DATA
Contents
G2 Reference Data
135
H7 Reporting Template 4
APPENDIX H
Contents
H1 Monitoring Protocols
H3 Reporting Procedures
136
H7 Reporting Template 4
APPENDIX I
OTHER ISSUES
Contents
I1 [add title]
137
Technical Guidance Note
Template for
Required
H7 Reporting Template 5
INTRODUCTION
This document presents a reporting template for Operators to use when reporting the
first phase of a Site Protection and Monitoring Programme for installations that do not
require reference data to be collected. It is designed to assist Operators with the
submission of the correct information in a suitable format to the EHS and should be
completed in full.
Guidance on the Protection of Land Under the PPC Regime: Application Site
Report and Site Protection and Monitoring Programme
In the template, those parts written in italics and enclosed in square brackets (i.e.
[italics] ), indicate where relevant information and or assessment is required to be
entered. In entering this information the italics should be deleted along with the
brackets or written over and the text reformatted to normal style.
Where text in italics appears prefixed with the word “Note” in bold ( i.e. [NOTE:
italics] ) this provides guidance on filling in the relevant [italics] part. On completion
of the [italics] part the [NOTE: italics] should be deleted from the final report prior to
submission.
138
H7 Reporting Template 5
[Date]
139
H7 Reporting Template 5
Contents
Summary
1.0 Introduction
4.0 References
5.0 Glossary
Appendices
140
H7 Reporting Template 5
Summary
This document represents the first report of the Site Protection and Monitoring Programme
(SPMP) for [name installation] submitted to the Environment and Heritage Service in
pursuance of Permit No. [Reference Number] (the "Permit") authorising the operation of
[installation name] (the "installation").
The scope of this monitoring is detailed within the Design SPMP submitted in pursuance of
Condition 4.1.7 of the above mentioned Permit. This document should be read in conjunction
with both documents.
The monitoring programme for the site is presented in Section 3 of the Design SPMP.
141
H7 Reporting Template 5
1.0 Introduction
[Enter details of persons and / or companies undertaking the assessments for the
applicant and any other additional details.]
The installation is located at [ADDRESS plus any further relevant location descriptor].
The centre of the site is at National Grid Reference [8-figure grid reference ]. The site
covers and area of [enter area] Ha and can be seen in Figure 1 of Appendix A1.
The infrastructure monitoring programme meets the objectives identified within Section
2.1 above and thus there are no changes to the Design SPMP for the installation.
[NOTE: or]
[Detail the methods, and procedures for assessing monitoring data as a result of
operating this Site Protection Plan within an overall EMS for the installation.]
142
H7 Reporting Template 5
Summaries of the monitoring data will be sent to the EHS on the 31st of January each
year along with the results of the data assessment, and any recommendations for
amendments to the monitoring programme.
The formats for standard and emergency reporting procedures are shown in Appendix
B3.
[Detail the recording and data management procedures for monitoring data and the
results of inspection and testing of pollution prevention infrastructure and of
emergencies.]
[NOTE: One of the purposes of the SPMP is to provide the operator with data to aid in
the process of surrendering of a Permit. In order to surrender a Permit the operator
must demonstrate to the EHS that the site is in a satisfactory state. A suitably designed
monitoring, testing and inspection programme should provide sufficient data to
demonstrate satisfactory state without recourse to additional intrusive investigations.
However this is incumbent upon suitable procedures to record such data, or summaries
of such data.]
[Detail other issues relevant to the protection of ground or groundwater within the
installation, such as general staff awareness and specific training. If necessary append
additional information within Appendix C]
4.0 References
[List references]
5.0 Glossary
[NOTE: The glossary should contain an explanation of all acronyms and industry
specific jargon used within the report]
143
H7 Reporting Template 5
APPENDIX A
144
H7 Reporting Template 5
APPENDIX B
Contents
B1 Monitoring Protocols
B3 Reporting Procedures
145
H7 Reporting Template 5
APPENDIX C
OTHER ISSUES
Contents
C1 [add title]
146