Professional Documents
Culture Documents
Lecture 6 PDF
Lecture 6 PDF
CIVE 421
Fall 2022
Dr. Issam Srour
Housekeeping
Term Project
Further reading
Article in Al-Mouhandess on Moodle
Construction and Contracts
What is a contract?
An agreement between two or more parties to
do something for a consideration
A promise for the breach of which the law
recognizes duty
Does it have to be in writing?
How so?
Finished product is not available for
inspection
Product is bought from multiple sources
Two General Processes for
Construction Contracts
How it works
How it works
Advantages
Disadvantages
How it works
Project is broken down into work items that can be
characterized by units
Contractor quotes price by units rather than single total price
Low bidder is determined by summing the total amount for
each of the work items
Unit Price Contract
How it works
Unit-price quotations are based on the guide quantity
specified
Unit price includes direct and indirect costs
Progress payments are based on precise
measurement of field quantities
How important is the accuracy of the quantities?
Most unit-price contracts provide for a price
renegotiation in the event that actual field quantity
deviates significantly (e.g. 10%) from guide quantity
specified
To whom is this more important: owner or contractor?
Unit Price Contract
Advantages
Allows some flexibility: estimated quantities are to
be re-measured
Risk of quantity variation is not accounted for in the
contingency allocation of the contractor’s price
BOQ is fully developed
What type of projects lend themselves into UP?
Disadvantages
Budget is not completely fixed
It gives room for bid unbalancing to be exercised
Project Expenditure/Income
Unbalanced Bid Income Profile
Income Profile With Mobilization
Payment
(Cost + Fee) Contract
How it works
How it works
Fee structures
Cost + percent of cost
• Lucrative for the contractor
Cost + fixed fee
• Determined as a percent of an originally
estimated total cost figure
• This gives the contractor an incentive to get the
job done in the shortest time frame
(Cost + Fee) Contract
How it works
Fee structures
Cost + fixed fee plus profit-sharing clause
• Provides reward to the contractor to control cost
• Common sharing formula: 25/75
• Target value can sometime be defined as a
guaranteed maximum (GMP)
• What does it take to have a GMP?
Cost + sliding fee
• Penalizing contractor for overrunning target
value
(Cost + Fee) Contract
Advantages
Disadvantages
Administrative complexity
Budget is not fixed before hand
- Mitigation?