1. The petitioner applied for a mining lease near Mirjas village in Nagaur district. The mineral being mined, Bajri, is a type of processed sandstone found in the mining area, not riverbank sand which is 80km away.
2. A site inspection found the land suitable and a letter of intent was issued by the mining department. Environmental clearance was also given.
3. A mining lease was granted and the petitioner began mining work according to the rules. However, a drone survey and site inspection later claimed mining limits were exceeded without notice to the petitioner.
4. A demand was made but the petitioner argues the Bajri is not riverbank material and mining was according
1. The petitioner applied for a mining lease near Mirjas village in Nagaur district. The mineral being mined, Bajri, is a type of processed sandstone found in the mining area, not riverbank sand which is 80km away.
2. A site inspection found the land suitable and a letter of intent was issued by the mining department. Environmental clearance was also given.
3. A mining lease was granted and the petitioner began mining work according to the rules. However, a drone survey and site inspection later claimed mining limits were exceeded without notice to the petitioner.
4. A demand was made but the petitioner argues the Bajri is not riverbank material and mining was according
1. The petitioner applied for a mining lease near Mirjas village in Nagaur district. The mineral being mined, Bajri, is a type of processed sandstone found in the mining area, not riverbank sand which is 80km away.
2. A site inspection found the land suitable and a letter of intent was issued by the mining department. Environmental clearance was also given.
3. A mining lease was granted and the petitioner began mining work according to the rules. However, a drone survey and site inspection later claimed mining limits were exceeded without notice to the petitioner.
4. A demand was made but the petitioner argues the Bajri is not riverbank material and mining was according
The humble petitioner applied for grant of a mining
lease for mineral Bajri near village- Mirjas, Tehsil-
Mundwa and, District nagaur. It is relevant to mention here that the mineral Bajri found in the mining area of the humble petitioner is a type of sand which is being processed and named as Bajri as it is Friable sandstone and sedimentary deposit which cannot be termed as Bajri from river bank at all and the river bank is situated 80 kms. Away from the mining area of the humble petitioner. The respondent mining Engineer, mines and geology department, Nagaur so also the Halka patwari conducted a site inspection and prepared the report wherein the land in question was found to be flat sandy and Khatedari land. The mining engineer, mines and geology department, Nagaur issued a L.O.I. vide letter dated 8/5/2019 in favour of the of the petetioern and informed the humble petitioner that the department is intending to grant mining lease to the humble petitioner and the humble petitioner was directed to complete the formalities of L.O.I. The respondent superintending mining engineer, approved the mining plan with progressive mine closure plan with regard to the application of the humble petitioner. Then district level environment impact assessment authority, Nagaur issues environmental clearance of the humble petitioner. The respondent superintending mining engineer vide order dated 23/7/2019 granted the M.L. No.32/2019 in favour of the humble petitioner for excavation of the mineral Bajri at the location near district Nagaur and in pursuance of such order, the agreement was executed. After execution of the agreement, the humble petitioner started mining work at the allotted mining area as per the rules. Thereafter, the respondent mining engineer, conducted a site inspection and directed the petitioner to erect the pucca boundary pillars as per the prescribed size. The petitioner got the consent to operate from the Rajasthan state pollution control board. The respondent department conducted a Drone survey of various mining leases areas from the agency Eagle Eye Survey Pvt. Ltd., who submitted its Drone survey report dated 10.12.2021. Thereafter, on 31.12.2021, as per the direction of the mining engineer, Nagaur, a site inspection was conducted in the absence of the petitioner and no notice or opportunity of hearing was granted and report was prepared wherein it is observed that as per the drone inspection report, Bajri is lying spread there and the same cannot be measured.
Vide letter dated 21.1.2022, the respondent mining
engineer issues a notice to the humble petitioner asking him that he has excavated 1407.29 and as per the report dated 31.12.2021 given by central empowered committee who in compliance of the directions given by hon’ble the Supreme court in the order dated 11.11.2021 passed in S.L.P. No. 10587/2019, “All the Khatedari leases located within 5 kms from the river bank as well as leases violation of the lease condition including the misuse of e-ravannas are detected are detected are terminated forthwith and the state government shall not issue fresh Khatedari leases except the palaeo deposits in the district of Bikaner without the approval of this Hon’ble court.” And as such, the respondent mining engineer called upon the humble petitioner to put his defense in the matter within a period of 30 days with the submission of representation with evidence. As stated above, from the petitioner’s mining lease, mineral Bajri is being excavated which Bajri is not the river bank Bajri but is a type of sand which is being processed and named as Bajri as it is friable sandstone and sedimentary deposit which cannot be termed as Bajri from river bank and as such, the notice dated 21.1.2022 is misconceived as the report of the central empowered committee does not at all apply to the present case. The humble petitioner submitted its representation dated 17.2.2022 and submitted inter-alia that the inspection conducted through drone was not appropriate nor any physical inspection was carried out in presence of petitioner or his authorized representative. It was further stated in the representation that the mineral as shown in the notice is lower than the excavated mineral in the mining lease area in question. The above factual gamut clearly reveal before this Hon’ble court that the humble petitioner has not misused and e-ravannas nor the Bajri is river bank Bajri but is a sand Bajri rather the mining work was done as per the mining lease and the work was done as per the mining lease and the petitioner’s mining area is 80 kms. Away from the river bank but despite all this, the respondent mining engineer vide demand notice dated 2.3.2022 raised a demand of Rs.65328/- from the humble petitioner. It is also relevant to submit here that the difference between the production of mineral and Mokam report was very minor and that was happened when petitioner was removed the overburden from the lease area but respondent department not consider . As stated above, although the humble petitioner has not done any illegal mining. To other similarly situated mining lease holders, the respondent mining engineer has issued demands and also wrote letters intending to cancel the mining lease of such lease holders as such, such mining lease holders including the humble petitioner herein submitted a representation to the respondents praying therein to not to cancel their mining lease by alleging therein that there mines are situated 80 kms. Away from the river bank and the alleged Bajri is not river bank Bajri and further they have not misused the E-ravannas as they have done the mining work as their mining lease itself and they have already deposited the demand so raised by the respondent mining engineer. Despite the humble petitioner having deposited the demand so raised by the respondent mining engineer and despite there being the fact that the excavated Bajri is not the river bank Bajri rather the same being processed sand Bajri and the fact that the humble petitioner has not misused the E- ravannas, the respondents are held bent upon to cancel the mining lease of the humble petitioner. May it please this Hon’ble court: The petitioner above-named respectfully begs to submit as under:- 1.The humble petitioner is a citizen of India being permanent resident of District Nagaur. 2. That the humble petitioner applied for grant of a mining lease for mineral Bajri near village Mirjas, Tehsil- Mundwa, District Nagaur, vide application dated 06/3/2019 a copy of application along with mineral availability report dated 29/4/2019 is being submitted herewith and marked as Annexure-1 to the petition. It is relevant to mention here that the mineral Bajri found in the mining area of the humble petitioner is a type of sand which is being processed and named Bajri as it is friable sandstone and sedimentary deposit which cannot be termed as Bajri from river bank at all and the river bank is situated 80 kms. Away from the mining area of the humble petitioner. 3.That the respondent mining engineer, mines and geology department, nagaur so also the halka patwari conducted a site inspection and prepared the pre demarcation report wherein the land in question was found to be flat sandy and Khatedari land . 4.That the mining engineer, mines and geology department, nagaur issued a letter of intent vide letter dated 08/05/2019 informed the humble petitioner that the department is intending to grant mining lease to the humble petitioner was directed to complete the formalities. A copy of the letter of intent dated 8/5/2019 is being submitted herewith and marked as Annexure-2 to the petition. 5.That the respondent superintending mining engineer, vide order approved the mining plan with progressive mine closure plan with regard to the application of the humble petitioner. 6.That the district level environment impact assessment authority, nagaur issued environmental clearance to the humble petitioner. 7. That the respondent superintending mining engineer vide order dated 23/7/2019 granted the M.L. No.32/2019 in favour of the humble petitioner for excavation of the mineral Bajri at the location near village Mirjas, Tehsil Mundwa, District Nagaur and in pursuance of such order, the agreement was executed. A copy of the sanction order dated 23/07/2019 is being submitted herewith and marked as Annexure-3, to the petition 8. That after execution of the agreement, the humble petitioner started mining work at the allotted mining area as per the rules. Thereafter, after the sanction the respondent mining engineer, conducted a site inspection and directed the petitioner to erect the pucca boundary pillars as per the prescribed size. 9.That the petitioner got the consent to operate from the Rajasthan state pollution control board vide letter dated 07/08/2019 a copy whereof is being submitted herewith and marked as Annexure-4 to the petition. 10. That the respondent department conducted a drone survey of various mining leases areas from the agency Eagle Eye Survey Pvt. Ltd., who submitted its drone survey report dated 10.12.2021 a copy whereof is being submitted herewith and marked as Annexure-5 to the petition. 11. That thereafter, on 30.12.2021, as per the direction of the mining engineer, Nagaur, a site inspection was conducted and a report was prepared in absence of the petitioner wherein it is observed that as per the drone inspection report, Bajri is lying spread there and the same cannot be measured. A copy of the site inspection report dated 31.12.2021 is being submitted herewith and marked as Annexure-6 to the petition. And it is also relevant to submit here that no notice or opportunity of hearing was granted to the petitioner before the site inspection 12. That vide letter dated 21.1.2022, the