January 24, 2022

To: Ms. Angela P. Reyes


Pollution Control Officer
Bakemasters, Inc.
32-A Arthur Drive, Bagumbayan
Taguig City

SUBJECT: QUOTATION FOR THE REHABILITATION OF EXISTING WASTEWATER


TREATMENT FACILITY
___________________________________________________________________________________

Dear Sir,

Aqua Add On Systems Inc., is pleased to submit herewith our quotation on the above captioned
subject for your evaluation. The rehabilitation is based on your submitted wastewater characteristics
(laboratory results) and daily flow rate. Please refer to the attached scope of services and bill of
quantities for your perusal.

Your current wastewater treatment facility failure to comply with DENR set effluent standards
particularly BOD, TSS, Oil and Grease, COD, Ammonia, Nitrate, Phosphate and Fecal Coliform
indicates a need for review of current treatment (Conventional Activated Sludge). It is possible that the
system is experiencing organic overloading beyond its design capacity.

It is proposed to install two (2) Ozonator units, one to be installed at one of the Settling Tanks
before the Aeration Tank and another unit at the Final Clarifier. Ozone (O 3) is a powerful primary
oxidant that is produced from the Ozonator. The ozone will effectively reduce the influent BOD and
COD with the partial oxidation of organic and inorganic matter in the wastewater stream. It is also an
effective disinfectant to eliminate pathogens from wastewater. This will greatly reduce the needed
chlorine, if not totally eradicate it. It should be noted that from the wastewater test results summary
(please see Table 1 below), the Fecal Coliform parameter failed in all the tests.

Page 1 of 5
Ozone readily decomposes to oxygen in the wastewater stream providing excess dissolved
oxygen in the Settling Tank. This will also promote better flotation of suspended solids, oil and grease
that can easily be removed by scooping. With reduced organic and inorganic pollutants entering the
Aeration Tank, the activated sludge will not be experiencing shock organic loading. This should
improve the ability of the biomass to biodegrade phosphate phosphorus.

With this proposal we are confident that this will solve your current problem with compliance to
DENR effluent standards.

Thank you very much for the opportunity to quote on your requirements and looking forward for
your earliest favorable consideration.

I. PROPOSAL

DESIGN CRITERIA
BASIS
Flowrate, Q: 30 CMD

WASTEWATER CHARACTERISTICS
Table 1. Effluent Characteristics (Provided By the Client)

SCOPE OF WORKS:

Page 2 of 5
ACTIVITY 1: Ozonator
1. Supply and installation of (2) units of Ozonator
2. Piping
3. Electrical wiring

ACTIVITY 2: Control Panel


1. Electrical wiring and termination

ACTIVITY 3: Testing and Commisioning


1. Testing and commisioning

II. WARRANTY

1. Warranty for the ozonator units are 12 months.

III. FINANCIAL ASPECT

A. PROJECT COST

The total project cost is PhP375,000.00 inclusive of tax.

Should this amount be considerable to you, the terms of payment are as follows:

1. 50% Down payment


2. 50% Progress Billing

Page 3 of 5
B. LEAD TIME AND WORK DURATION

Possible lead time for the project is around 30-60 days and the work duration is expected to be
between 7-12 days.

C. INCLUSIONS AND EXCLUSIONS

Inclusion:
 Transportation cost of laborers during installation and commissioning

Exclusion:
 Provision of Source Lines/Electrical Lines
 Provision of Area for Ozonators and Control Panel

ATTACHMENT:
ITEM DESCRIPTION UNIT QTY UNIT PRICE TOTAL
I GENERAL REQUIREMENTS
Mobilization and
Demobilization
  1 lot 15,000.00 15,000.00
(Including meals and
transportation of laborers)
        SUB TOTAL  15,000.00
II. MECHANICAL & SANITARY WORKS
Ozonator unit

Capacity: 30g O3/ hr


Brand: 1 unit/s 150,000.00 150,000.00
Origin:
Power: 230/ Single Phase

Ozonator unit

Capacity: 20g O3/ hr


Brand: 1 lot 120,000.00 120,000.00
Origin:
Power: 230/ Single Phase

Pipes and Fittings


1 lot 10,000.00 10,000.00
(for Ozonator Units)

        SUB TOTAL 280,000.00


IV ELECTRICAL WORKS
Control Panel 1.00 lot 30,000.00 30,000.00

Page 4 of 5
  Wirings & Conduit 1.00 lot 20,000.00 40,000.00
        SUB TOTAL 70,000.00
V TRAINING AND COMMISIONING
1.00 lot 10,000.00 10,000.00
SUB TOTAL 10,000.00
        TOTAL PRICE (VAT INC) PhP375,000.00

Thank you very much and best regards.

Very truly yours,

_________________________
Krisuelle Escanela
Sales and Marketing Officer

APPROVED BY:

_________________________
Gregorio Villacorta
General Manager

Page 5 of 5