CONSTRUCTION
Building Construction
A/02/ad Submit shop drawings and order long lead items- 2 wks A/01/af
A/02/ae Submit shop drawings and order long lead items- 2 wks A/01/af
A/02/af Submit shop drawings and order long lead items- 2 wks A/01/af
A/06/ad Install miscellaneous iron and bracing-3rd floor and 2 wks A/05/ab
A/07/
A/07/au Cure 1st floor slab 7 days aq,
A/07/at
A/07/av Strip forms from 1st floor slab 2 days A/07/au
A/14/
ab,
A/15 Electrical Duration Predecessors
A/15/aa Rough-in electrical in masonry walls 4 wks A/02/ae,
A/07/av
A/15/ab Rough-in electrical in drywall walls 4 wks A/11/aa
A/15/ac Pull wire in conduit and set area transformers 3 wks A/12/ac,
A/15/aa
A/15/ad Install and terminate electrical devices 3 wks A/15/aa,
A/15/ac
A/15/ae Make electrical terminations for HVAC equipment 2 days A/10/ae,
A/15/ac
A/15/af Install light fixtures-test and clean 2 wks A/12/ae,
A/15/ad
A/19 Complete punch list items from all inspections 2 wks A/18/AD
Report Requirements
The activities listed above shall be appropriately linked with each other with the help of
the relationship information listed above to find the total duration of the project. What will be
the probable finish date if the company follows 5day-work week. Include all the national
holidays during the project execution period.
Resource Availability
ID Resources
A/01/aa General management
A/01/ab General management[25%], Project management
A/01/ac Project management[25%], Scheduler
A/01/ad General management[10%], Project management
A/01/ae Project management[50%], Procurement[50%]
A/01/af Project management[50%], Procurement[50%]
A/01/ag Project management[50%], Procurement[50%]
A/02/aa Steel Erection Contractor Management
A/02/ab Roofing Contractor Management
A/02/ac Elevator Contractor Management
A/02/ad Plumbing Contractor Management
A/02/ae Electric Contractor Management
A/02/af HVAC Contractor Management
A/02/ag Steel Erection Contractor Management[50%], Steel Erection Contractor[50%]
A/03/aa Electric Contractor
A/03/ab Plumbing Contractor
A/03/ac Labour Crew[10%], Superintendent
A/03/ad Survey Crew
A/03/ae Labour Crew[10%], Site Grading Contractor
A/04/aa Site Grading Contractor
A/04/ab Site Grading Contractor
A/04/ac Site Grading Contractor
A/04/ad Site Grading Contractor
A/04/ae Plumbing Contractor
A/04/af Site Grading Contractor
A/04/ag Survey Crew
A/05/aa Site Grading Contractor[50%]
A/05/ab Site Grading Contractor
A/05/ac Rough Carpenter Crew
A/05/ad Electric Contractor, Plumbing Contractor
A/05/ae Rough Carpenter Crew
A/05/af Rough Carpenter Crew
A/05/ag Concrete Crew
A/05/ah Concrete Crew
A/05/ai Labour Crew[10%]
A/05/aj Labour Crew[10%]
A/05/ak Labour Crew[10%]
A/05/al Labour Crew
A/05/am Elevator Contractor
A/05/an Concrete Crew
A/06/aa Steel Erection Contractor
A/06/ab Steel Erection Contractor
Project Planning & management| PRACTICALTECHNOLOGIES
ID Resources
A/06/ac Steel Erection Contractor[75%]
A/06/ad Steel Erection Contractor[75%]
A/06/ae Steel Erection Contractor[50%]
A/06/af Steel Erection Contractor[20%]
A/07/aa Labour Crew[20%], Rough Carpenter Crew
A/07/ab Labour Crew[33%], Electric Contractor[33%], Plumbing Contractor[33%]
A/07/ac Concrete Crew
A/07/ad Labour Crew[10%]
A/07/ae Labour Crew
A/07/af Labour Crew[20%], Rough Carpenter Crew[50%]
A/07/ag Labour Crew[33%], Electric Contractor[33%], Plumbing Contractor[33%]
A/07/ah Concrete Crew
A/07/ai Labour Crew[10%]
A/07/aj Labour Crew
A/07/ak Labour Crew[20%], Rough Carpenter Crew
A/07/al Labour Crew[33%], Electric Contractor[33%], Plumbing Contractor[33%]
A/07/am Concrete Crew
A/07/an Labour Crew[10%]
A/07/ao Labour Crew
A/07/ap Rough Carpenter Crew
A/07/aq Electric Contractor
A/07/ar Plumbing Contractor
A/07/as Labour Crew[33%], Electric Contractor[33%], Plumbing Contractor[33%]
A/07/at Concrete Crew
A/07/au Labour Crew[10%]
A/07/av Labour Crew
A/08/aa Dry Wall Contractor
A/09/aa Plumbing Contractor
A/09/ab Masonry Contractor
A/09/ac Masonry Contractor
A/09/ad Roofing Contractor
A/09/ae Tile Contractor
A/09/af Masonry Contractor[50%]
A/09/ag Tile Contractor[50%]
A/10/aa Roofing Contractor
A/10/ab Roofing Contractor
A/10/ac Roofing Contractor
A/10/ad Roofing Contractor
A/10/ae HVAC Contractor
A/11/aa Window Contractor
A/11/ab Dry Wall Contractor
A/11/ac Finish Carpenter Crew
A/11/ad Window Contractor
Project Planning & management| PRACTICALTECHNOLOGIES
ID Resources
A/12/aa Finish Carpenter Crew
A/12/ab Painting Contractor
A/12/ac Electric Contractor
A/12/ad HVAC Contractor
A/12/ae Dry Wall Contractor
A/12/af Dry Wall Contractor
A/12/ag Painting Contractor
A/12/ah Carpet Contractor
A/12/ai Finish Carpenter Crew
A/12/aj Landscape Contractor
A/12/ak Paving Contractor
A/13/aa Elevator Contractor
A/13/ab Elevator Contractor
A/13/ac Elevator Contractor
A/14/aa Plumbing Contractor
A/14/ab Plumbing Contractor
A/14/ac Plumbing Contractor
A/14/ad Plumbing Contractor
A/15/aa Electric Contractor
A/15/ab Electric Contractor
A/15/ac Electric Contractor
A/15/ad Electric Contractor
A/15/ae Electric Contractor
A/15/af Electric Contractor
A/16/aa HVAC Contractor
A/16/ab HVAC Contractor
A/16/ac HVAC Contractor
A/16/ad HVAC Contractor
A/16/ae HVAC Contractor
A/17/aa Tile Contractor
A/17/ab Tile Contractor[50%]
A/17/ac Labour Crew
A/17/ad Superintendent
A/18/aa Elevator Contractor
A/18/ab Project management[50%], Superintendent[50%]
A/18/ac Project management[50%], Superintendent[50%]
A/18/ad Project management[50%], Superintendent[50%]
A/19 Superintendent11%], Labour Crew[11%], Electric Contractor[11%], Plumbing
Contractor[11%], HVAC Contractor[11%], Painting Contractor[11%], Paving
A/20 Project management
A/21 Project management
A/22 General management, Project management, Accounting Contractor
50
Report Requirements
The activities listed above shall be appropriately linked with each other with
the help of the relationship information listed above to find the total duration of the
project. Find the hourly basis of work scheduled for each work package.
Prepare a report that gives the monthly cost expenditure incurred for the
activities planned and also prepare various reports which shows each level of
activities in the work breakdown structure defined. Analyse the resource distribution
and find the over allocated resource. Suggest suitable method to avoid over
allocation. What will be the probable finish date if the company follows 5day-work
week calendar with same working time for the resources involved. Include all the
national holidays during the project execution period.