Professional Documents
Culture Documents
Desalination Final2
Desalination Final2
REPORT
ABSTRACT
This report discusses the possibility of constructing a desalination or desalinization plant at Galle
as a prototype for a larger project. The construction process involves a number of phases such as
design, work-on-site, fabrication of components, installation of the components and finally the
commissioning of the plant. Some assumptions too will be made to accommodate seemingly
difficult concepts involved in the process. Design stage of the plant is based on the conceptual
framework for the plant to be treated as a prototype thus incorporating as much local design
features as possible. Site work is determined by the topography of the seabed on and around the
plant location. However the location would not be subject to year-round alluvial surges or erratic
tidal currents. The component fabrication process would involve the usual description of material
but not the strength determination tests and analyses. Installation process perhaps occupies a
preeminent position for the sole reason that transportation of components which have been cast
components would be treated as an integral part of the installation process. The commissioning
stage is rather ceremonial in nature with little engineering work needed if at all. The process of
desalination ought to be treated with much more care and as such would be the most important
outcome of the project report. The emphasis would be on the outcomes directly related to the
1. Introduction
This paper on the construction of a small desalination plant proposes to examine the
desalination plant at Galle would involve seven major phases of work – site layout design,
commissioning and documentation for approval. The report would examine in detail the
construction aspects such as the site layout design, mechanical component design, site
preparation work, manufacturing of components, installation and commissioning. Thus the non-
Time and again a variety of consultation reports have been produced by engineering consultants
in Sri Lanka on the need to construct desalination plants to purify and convert the abundant sea
water surrounding Sri Lanka into drinking or potable water. A variety of prototypes also have
been suggested though none has been implemented. Even the few environment friendly
prototypes of desalination plants that have received serious consideration by the World Bank and
the International Monetary Fund (IMF) have been shelved due to disagreement at the funding
level.
Thus this report looks at the feasibility of designing and constructing a small desalination plant
as the first step towards fuller implementation of a program that would be comprehensive enough
to include a national level project of constructing mega desalination plants. This report identifies
and addresses such practical issues as the structural engineering aspects in designing and
constructing the plant and the feasibility of adopting the kind of design and construction
To study the feasibility of designing and construction of such a desalination plant as first
To study the feasibility of converting abundant sea water around Sri Lanka into potable
water.
To Study the significance of such a project for the design and construction of national
The scope of the report and the project thereof is very significant and involves a series of
important and relevant issues. Scarcity of potable or drinking water is becoming a national issue
and it requires the attention of engineering community at the highest level. Since Sri Lanka has
abundant sea water resources the problem has attracted additional interest. In fact another very
important issue is the cost factor. The construction cost matters and thus the engineering
perspective acquires a very important dimension here. The report would be considered as a first
step towards future developments on similar lines since it has the original footprint of being the
first to consider engineering and cost related aspects of desalination. This can also be regarded as
a pioneering effort to identify and address the more important issues of approach to and adoption
Analysis
Drinking water technology is still in its infancy despite major strides made by some countries in
the Middle East in converting sea water into potable water at a fairly lower cost. Integrated water
treatment and purification solutions are being marketed by new technology firms on an ever
increasing scale in the world today. Against this backdrop designing and fabricating a
desalination plant could be considered a major step in the direction of technology improvement
in a country like Sri Lanka where almost 100 per cent of potable water comes from rain-filled
reservoirs, rivers and waterfalls. This is all the more significant when the future forecasts for
steeply rising costs on water purification and receding water beds are taken into consideration.
Once completed the maximum capacity of the plant is expected to be 1 million gallons per day
and would be functioning throughout the year except for occasional maintenance and repair shut-
downs. The project would include the seawater reverse osmosis (SWRO) plant, a sea water
intake facility, a system for discharging concentrate and the facilities and systems for chemical
storage and dosing. There would be efforts to 3D model the chemical dosing systems so that the
The pretreatment facility will be located closer to the sea water intake. Water is pumped from the
intake to the pretreatment facility. The subsequent inflow would pass through a two stage sand
filter. Here dosing the water can be done in order to adjust the level of salinity or pH in
accordance with requirements. The SWRO would involve 7 unconnected flows each of which in
turn will have a pump to transfer water, membranes, cartridge filters, a turbine for energy
recovery and a high pressure pump. The following diagram, Figure 1, illustrates the pretreatment
5
process and is in conformance with the established civil engineering practice in designing the
parameters of the process. Osmosis is a natural phenomenon found in biological systems. The
membranous process inhibits the movement of sediments like salt thus leaving the water devoid
of any solid substance. Movement does not take place without pressure. Thus the pressure
requires energy to be used. Fossil fuel can be expensive but nevertheless in a country like Sri
Big Bend
Roughing
Polishin Power Station
Cartridge Filters Filters
g Filters
Filter backwash
First pass
Storage
Second Pass
Energy Recovery
Concentrate return
Source: www.watertechnology.net
The design parameters are expected here to give an idea of what the plant should be like and its
full operational specifications are not intended for extensive description in this analysis. While
6
many previous studies on the subject of desalination of seawater in Sri Lanka discussed the
inevitable outcomes related to the process only a few of them have focused attention on the
design related constraints faced by civil engineering consultants at the initial stages. For example
as the above diagram shows there are the reverse osmosis membranes which have to be fed with
pressurized water from a 1,250hp and a split case horizontal high pressure pump that is equipped
with adjustable frequency drives. Assuming that the variable frequency drives which permit the
feed pressure to be adjusted between 625psi and 1,050psi cause variations to be higher and
frequent, the variations in the salinity level might be affected though. Such fluctuations are to be
Desalination plants with the application of reverse osmosis require to be placed under
constant supervision for the sole reason that they are installed and operated closer to the shore.
Since the osmosis filtration is basically a membranous technique the larger solids, molecules and
ions are easily removed from the seawater thus facilitating the filtration process. Structural
design of the process apart, the usual osmotic process ought to be designed to facilitate the
osmotic pressure. For instance when water potential is low the solute concentration is high and
vice versa. Thus any water movement intended to equalize the concentrations of solvents on
either side of a membrane would lead to osmotic pressure. In the reverse osmosis an external
source is introduced to apply pressure thus reversing the flow of the purified solvent. Though
there are some differences between filtration technique and reverse osmosis this report does not
concentrate on them for they are not important here. But nevertheless this report places emphasis
on reverse osmosis for it is mostly adopted by designers of desalination plants that are intended
The following Table 1 shows the parameters of seawater quality in reverse osmosis process.
With a recovery rate of 45% and an operating pressure equal to 900 psi, the estimates therein
provide a concise but clear picture of the outcomes directly related to the seawater. Seawater
parts per million (ppm), concentrate ppm and permeate ppm are presented in the table.
Source: www.watertreatmentguide.com
8
Chemicals $0.05
Miscellaneous $0.03
Source: www.watertreatmentguide.com
The following four items are not included in the cost estimates. But they are included in Table 4
below.
Intake water cost, concentration discharge cost, amortization of equipment cost, and the cost of
labor to monitor and maintain are thus not included here. However it must be noted here these
costs are discussed separately below in a comprehensive analysis. It must also be noted that these
costs need not be classified as they are usually done in accounting. Operating or running costs
are not included in the construction costs but nevertheless they are equally important for they
have to be incurred by the authorities for the continuous and successful operation of the plant.
While some costs are incurred on a continuous basis others are just on-and-off. Therefore each
9
cost involves some prior estimate and planning though the extent to which it has to be carried out
Primary Heater
Condensate Pump
Source: http://www.google.com/imgres?imgurl=http://www.netl.doe.gov
The above diagram Figure 2, illustrates a Multistage Distillation Model. Even Distillation
Models are so famous in the world today. Thus this report recommends such a Model for Sri
Lanka. As the Figure 2 illustrates a small desalination plant can be represented by the prototype
and it can be convincingly used to plan the entire project from the time of design to the
commissioning stage. However this is the desalination plant and the ground work and
Starting from the salt water source, e.g. the sea, the water moves through the regenerative
heaters. This type of cogeneration desalination plant is capable of using either nuclear energy or
10
other source of energy to convert the sea water into fresh potable water. In other words heat can
be generated in the plant itself. Next, when sea water is heated the steam will collect in the
condenser. Then the distillation process is used to collect the vapor on the top of the condenser
and the unevaporated water would be collected at the bottom of the diffusion tower in the form
of brine. The brine would next be pumped through the regenerative heater (Robert et al, 2000).
At the bottom of the condenser fresh liquid water is collected in the form of condensed vapor.
The condenser can be cooled by drawing water from the sea and circulating it through a
circulating pump so that the potable water can be cooled before it is pumped out for
consumption. The process can be simplified by using fossil energy. Fossil fuel is not expensive
Heating Steam
T=112c
Source: www.wtertechnology.net
11
As the above diagram, Figure 3, illustrates how the process of distillation is carried out by using
the prefabricated multistage distillation process. However it must be noted that one technology
cannot be said to be all too superior because each technology or process has its own advantages
and disadvantages. This model is presented as an alternative but is not explained in detail.
Fabrication of Components
It must be noted that equipment used for the removal of solids like salts from seawater can vary
significantly under each process or model. However one common factor stands out in all
methods, viz. according to the pressure requirement the laws of physics would dictate that each
100 mg/l of solid in seawater would need a driving force of 1 psi. It is not a secret that seawater
anywhere in the world has roughly 35,000 mg/l of solids in it. Thus as per the above rule of
thumb the minimum pressure required is 350 psi. On the other hand membranous reverse
osmosis can be applied usually when the solids dissolved in seawater are around 6,000 mg/l ore
The current trend is to go for hybrid configurations of the desalination equipment. The water
treatment process related equipment need not be divided into seawater units and reverse osmosis
units any more. They can be combined to produce a desirable level of drinking water output on a
surface plant. However differences in pressure requirements for the conversion purposes must be
paid attention in order to minimize mishaps. After all, equipment has to be fabricated in
Installation of Components
The process of installing components must be taken as the next most important step in the whole
process. Under this process it is desirable to identify the nature of components that in this
12
instance are basically Multistage Distillation Model related. Thus all structural, mechanical, filter
and pipe work will have to be executed with greater focus on the material being utilized. The
following components will have to be installed in using a pressure exchanger in the reverse
2
1
C
4
5
D
Source: www.watertechnology.net
1. Seawater inflow 2. Fresh water flow 3. Concentrate flow 4. Seawater flow and 5. Concentrate
A. High pressure pump flow B. Circulation pump, C. Osmosis unit with membrane,
D. Pressure exchanger
13
Project Execution
The seven tasks as outlined above can be executed according to a plan. However it must be noted
that these seven phases need not follow a logical sequence. Some of the tasks can be performed
simultaneously as demonstrated by the network diagram. Such overlapping tasks would enable
the project leader to reduce the amount of time spent on individual tasks (Danoun, 2007).
Next each individual task would require a particular accompanying quality management
task to be performed. Therefore the whole process would involve a set of tasks just before the
actual commissioning, a set of tasks during the component fabrication process and finally a set of
tasks just after commissioning. The relative significance of each set would in turn determine the
relocation outcomes. The process of task management would be decisive in the final context
because the outcomes are related to the final success or failure of the construction process. While
some tasks might have a better rate of success some others might not be so successful. However
in the final analysis successful construction of the desalination plant is determined by a number
of endogenous and exogenous variables that have to be predicted and managed within
Diverse skills of team members are to be utilized in their respective areas of specialty
thus leading to all benefits associated with the clear division of labor. The project plan has been
initiated with clearly defined targets and phases of activity that were put through the whole
process with well balanced steps. Team leadership was particularly impressive in establishing a
close rapport with team members whose contribution was measured in relation to a set of
motivation factors. Though some positive synergies were recorded through this process, there
were some shortcomings as well. For instance being mobile from one place to the other during
14
the week would entail a lot of time waste in sending multiple e-mails and a rise in costs
(Wahlquist, 2008).
Network Diagram
Figure 5 represents the network diagram for the task of constructing and commissioning the
small desalination plant. The following assumptions have been made in this regard to simplify
Though the actual project would more likely take approximately 37 months to finish, this
writer assumes that it would take no more than 88 days. This is intended to simplify the
calculations.
The critical path is calculated on the assumption that the total project can be
Each month has 30 days on average and each week has five working days.
The activity duration estimating process requires that the amount of work effort required to
complete the schedule of activities is appropriately estimated; the assumed amount of resources
to be applied to complete the schedule of activities is estimated; and the number of work periods
needed to complete the schedule of activities is determined. According to the diagram Task B’s
15
Earliest Starting Time, i.e. EST is projected to be 4 days and Latest Finishing Time, i.e. LFT is
projected to be 9 days. To complete the activity A 4 days are required and EST is projected to be
4 days because activity B cannot be started until activity A is finished. Also LFT is projected to
be 9 days basically because activity B requires 9 days to complete. Under actual circumstances
Total float is the total amount of time that a schedule of activities may be delayed from its
early start date without delaying the project finish date, or violating a schedule constraint.
Otherwise it is the amount of delay that can be accommodated in an activity's finish time without
affecting the project completion date. These delays are known as the total float, and project
management team must always keep this number in mind to ensure that the project will be
finished on time. According to the above hypothetical example the total float is calculated to be
88 days.
16
Figure 5: Network diagram for the process of constructing the desalination plant
10
C 4
9
9
1 9 I 47 J 51
99
51 61
4 5 10 6
D 19
10 8 4 4
A 28 H 46 K 61
B 4
10 47
67
9 E 28 1 1
1
8
36
10 6 L 67 M 68
G 42
10 F 36 68 70
46
42 2 6
4
N 70
76
8
R 87 Q 86 P 84 O 76
88 87 86 84
1 1 2
The project duration, more specifically, represents the total and complete sum total of work
the work breakdown structure. A critical path for a project is the series of activities that
determines the earliest time by which the project can be completed. The critical path through a
project schedule is the sequence of tasks which have a zero float. Thus, if any task on the critical
path finishes late, then the whole project will also finish late. There is always at least one critical
17
path. According to the above network diagram critical path can be identified as A, B, F, G, H, J,
K, M, N, O, P, Q, R and the total number of days is 53. According to the network diagram, the
project required 37 months to complete with assuming that there are 30 days a month despite the
holidays.
(a). If Task P were delayed by 1 day it will require 2 days to start Task Q. Then the
(b). If Task N were completed 1 day before the schedule it would take 7 days to finish
(c). If Task A were delayed by 2 days, it would take 12 days to complete Task A and the total
scheduling an activity. However, this diagram does need to be drawn in a rather specific manner
in order to be understood by those who are in quality management. It will show just how the
project management team should position the project and how long the schedule of tasks should
take, from the very beginning to the very end of the project (Fishman, 2011). A specific project
might consist of several network diagrams such as project network and project evaluation and review
technique (PERT).
18
This project management experience has, particularly, been focused on the significance of team
work and its benefits to the client. Quality management constraints basically occur in respect of
complex technical details that have to be managed in conformance with original guidelines.
While project success is determined by how best the team is able to perform its assigned tasks,
its learning outcomes are individually and collectively determined by a diverse and complex set
of variables (Portny, 2010). For instance a reverse osmosis desalination plant would require the
team of workers to focus on the time schedule while at the same time they would be required to
In the first instance the success of this particular project of constructing the
desalination plant depends on team management efforts including clearly defined goals and
successful coordination. Once the cost parameters are known the management of the
construction plan can put in place the priorities so that work teams consisting of engineers,
technical personnel and others would be prepared to achieve the set targets. This particular
aspect of the project of constructing a desalination plant becomes all the more important due to
the fact that any delay in a task could affect the whole project with the attendant problem of cost
As an essential condition for the smooth flow of work on the site supplier networks must be
strategically positioned. Both men and material supplier networks ought to have credentials
beyond doubt in order to ensure that quality related problems do not arise. Deficiencies in
material and inefficient teams of workers could mean both delays and lower standards, thus
aspects are therefore emphasized thought it is beyond the scope of this report to present a
Performance-centric approach of the team leader and the team members would enable the
making, strategic concept development and organizational culture and leadership. These positive
changes have to be introduced in good measure during the duration of the project and the
subsequent learning outcomes would determine the success parameters of each task according to
the guidelines
Cost Estimates
Table 1 illustrates the Gantt chart of the desalination plant. The total project is divided into 7
phases and the each phase has its set of resources, cost estimate, start date, finish date and the
duration. For example design phase comes first. It is handled by the internal design team; cost
estimate is put at $ 0.6 million; the start date is March, 1 st 2011; finish date is May, 31st 2011;
and the duration is 87 days. These figures are tentative in nature. The subsequent phases are
made out to represent the total project on the same basis of approximation and hypothesis.
While the existing technically feasible cost structures would even entail implied costs associated
with projected tasks, there would still be a marginal error in estimation notwithstanding the
resultant benefits-related outcomes. Thus cost minimization efforts are not necessarily influenced
by implied costs but by the amount of tangible benefits. This report would squarely analyze such
benefits in order to delineate a hypothetical but approximate cost-benefit scenario for the
construction of the plant. Thus the subsequent estimation would take into account the relative
significance of cost structures that are the results of the planned construction.
21
HR Engineers 20 $ 20 000
Managers 3 $ 4 500
Skilled Labor 25 $ 125 000
Unskilled Labor 20 $ 5 000
Others 20 $ 4 000
Machinery Machinery 10 units $ 650 000
Such cost structures as immediate and prime arising from the location outcomes would be
determined according to their importance in this analysis. Should such structures be correlated
with construction outcomes then the subsequent decision making on the part of the management
would be determined by the positive or/and negative results presented at the end of this report by
The above hypothetical cost structures were developed by this writer in conformance with the
current level of work. These structures are associated with the probable construction cost
estimates determined as at a near future date and are expressed in US Dollars. The relative
22
significance of these structures and estimates lie in the fact that they invariably impact on the
overall outcomes of construction of the plant. Therefore these costs must be regarded as near
content. The hypothetical nature of figures would not reduce the degree of analytical rigor by one
iota because the conceptual framework applied in this context is significantly influenced by an
There is an alternative method for the construction of a desalination plant of considerable size
and scope at Galle by using the Build, Own, Operate and Transfer (BOOT) or Design, Build,
Own, Operate and Transfer (DBOOT) approach. For example the biggest seawater desalination
plant in South Asia is located in Chennai, India with a capacity for 100 million liters per day.
The Minjur desalination plant produces 1,000 liters of water at an average cost of US$ 0.90.
When converted into Sri Lankan Rupees it is around Rs.115.00 per 1,000 liters.
In fact the Minjur desalination plant was to be commissioned in 2008 but due to the roughness of
the sea near Chennai the builders and Chennai Metro Water were forced to delay it till July 2010.
However, the sea near Galle does not pose such a problem to the authorities. Thus a similar
approach can be adopted by Sri Lankan authorities in order to avoid a once-and-all cost outlay.
Projects like desalination plants are more feasibly carried out on the basis of BOOT elsewhere
too.
In the case of Minjur Plant the builder would own and operate the plant for 25 years and then
transfer the ownership to the Chennai Metro Water (www.water-technology.net). Such a BOOT
based approach would benefit both the government of Sri Lanka and the consumers of water by
23
way of reduced budgetary burdens on the former and reduced cost per unit of fresh water
consumed for the latter respectively. These suggestions are intended to facilitate the decision
making process of authorities against the backdrop of shortages of funds and above all the ever
increasing costs of men and material. However it must be noted that a desalination plant with a
capacity of 100 million liters per day is too big for Galle. After all Chennai with extended
reverse osmosis desalination plant with the capacity of 4,000 m³ per day. One of the most
remarkable features of the project is the fact that it has adopted highly advanced technology to
save energy in addition to installing monitoring and control equipment with remote capacity.
Again it was on DBOOT basis and OneSteel is a private company. This example shows the
extent of possibilities in the area of technology related projects. Such possibilities are basically
Technology transferring under BOOT or DBOOT is of great importance for the sole reason that
it enables the contracting parties to benefit from the given arrangement. For instance the
contractor or the builder gains a lot of experience in the process while the client does need to
spend a huge sum of money on or commit scarce funds to development. Always benefits might
not outweigh costs though. Assuming that the contractor delays or abandons the project due to
cost escalation the outcome would be disastrous to the client. Similarly if the cost overruns are
persistent and unmanageable the contractor might be compelled to redesign and scale down the
project.
24
Finally cost per unit of desalinated water consumed can be much higher than a unit of fresh
water provided through conventional means. This possibility is the biggest problem faced by
authorities in cities where operations become more expensive on a day to day basis due to the
scarcity of skilled labor to run the plant. Still such uncertainties should not deter authorities
whose primary responsibility is to ensure a continuous and dependable supply source for the
Process of Disinfection
The process of treating the purified water through reverse osmosis before the distribution for
final drinking by people involves some important tasks. Though reverse osmosis effectively
inhibits the survival of pathogens in the water, there must be a secondary treatment process to
ensure that the water distributed for human consumption is free of all bacterial pathogens. For
instance all membranes cannot be equally efficient. Some could malfunction and further
downstream pipes and backwash would have let in some pathogens. In order to do this,
authorities must adopt a cost effective disinfection method. However, yet again such a method
Some desalination plants around the world adopt UV technique in which UV lamps are used to
kill off pathogens. Such sterilization techniques will kill off germs and bacteria which have
survived the reverse osmosis process. Ultraviolet disinfection systems might ensure the quality
of water that finally people drink. Despite the fact that disinfection costs might substantially
increase the final operation costs of the project the possibility of reducing costs with efficient
membranes and backwash can be a reality one day. Such outcomes depend on quality
25
The final stage of commissioning the desalination plant involves a series of sub-tasks though
they are not a matter of concern for the civil engineering consultant. The commissioning of the
desalination plant is a formality and is executed with more fanfare and pageantry with
government officials and politicians attending the function. However it must be noted that with
the commissioning comes the additional responsibility for the operating authority, i.e. either the
Galle Municipality or any government agency to ensure the continuous operations of the plant.
Any breakdown in its operations can be a huge loss, especially by way of maintenance costs that
All formalities related to the operations and operability are executed under this process. The
plant operations staff are assigned tasks and put on rotation. Various quantities of chemicals
needed for the reverse osmosis desalination process are determined with the given capacity for
generation. Further the commissioning phase of the project determines the extent of staff
requirements to be available for the day-to-day running. Thus the commissioning phase is very
significant for some other reasons as well. If the project is one under BOOT or DBOOT there is
the probability of the contractor or builder identifying a variety of concurrent obligations for both
The client would be required to monitor the progress from the day of commissioning so that the
pace of work is measured in accordance with the accepted norms. Any deviation from the norms
such as frequent breakdowns and other internal interruptions can be regarded as a sign of poor
design and failure. When technology fails costs are bound to increase. This in turn is followed by
Conclusion
This report specifically discusses the feasibility of building a small desalination plant with the
capacity of 1 million gallons of fresh water per day at Galle in Sri Lanka. It is more or less a
project involving the construction of the prototype of a desalination plant. The prototype of a
small desalination plant describes the project specifications including the project size, nature and
the process. Thus it is to be treated as a probable solution to the impending water crisis in the
island, especially in the southern districts. The report presents two models – the Reverse Osmosis
Model and the Multistage Distillation Model. Indeed it must be noted that hybrid models have
This report is basically focused on the seawater reverse osmosis desalination plants. This method
is more suitable for a country like Sri Lanka given the huge seawater sources that surround it.
While the technological aspects are more centered on the plant design and component
manufacturing phases of the report, there is added emphasis on the outcomes such as costs and
quality improvement. The technical aspects of the SWRO desalination are basically determined
The cost tables are intended to provide the approximate cost structures and the total project plan
is intended to provide an idea about how the project would proceed in theoretical outline. The
rest of the explanation is based on the reverse osmosis model with added emphasis on
membranous technology. The seawater reverse osmosis desalination plants have been
constructed by a number of countries such as Australia, the US and Israel with a view to
providing fresh potable water to city dwellers under different circumstances. Such efforts are
based on a single premise that in addition to being a dependable source of drinking water it is
also a cheaper alternative to on-land rain filled reservoirs as a source of supply. The report makes
some pertinent suggestions on the need to adopt BOOT or DBOOT method as a solution to the
REFERENCES
Danoun, R. (2007), Desalination Plants: Potential impacts of brine discharge on marine life,
Retrieved from http://ses.library.usyd.edu.au/bitstream/2123/1897/1/Desalination%20Plants.pdf.
Fishman, C. (2011). The Big Thirst: The Secret Life and Turbulent Future of Water, New
York: Free Press.
Lewis, J. P. (2006). Fundamentals of Project Management, 3rd Ed, New York: AMACOM.
Lindgren, M. & Bandhold, H. (2009). Scenario Planning: The Link Between Future and
Strategy, New York: Palgrave Macmillan.
Portny, S. E. (2010). Project Management for Dummies, 3rd Ed, New Jersey: Wiley.
Robert, K. et al, (2000). Effective Project Management, 2nd Ed, New Jersey: Wiley.
Wahlquist, A. (2008). Thirsty Country: Options for Australia, Sydney: Allen & Unwin.
Walker, D.H.T., Web-Based Project Management Scenario Case Studies, Retrieved from
http://dhtw.tce.rmit.edu.au
www.watertreatmentguide.com on January
2012.
ABBREVIATIONS
5. HR (human resources)
8. UV (ultraviolet)