W.weekly Activity Report - Week - Three.v2.2023.03.11
W.weekly Activity Report - Week - Three.v2.2023.03.11
Location BHC Belmopan, North Ring Road/Melhado Parade, PO Box 91, Belmopan, Belize
Summary of the completed planned work activities for the week FOUR:
Monday 06th March – Saturday 11th March 2023.
Activity Summary (Principal Work Item Headings Only) Complete Ongoing Late
Weekly Full site inspection /All works activity review with full team
Site Set Up
Erect Scaffolding
UNION still waiting on work permits. Although the approval has already been done.
Temp (°C) 27 29 30 31 32 30
Monday
Relative Humidity (%) 71 61 53 45 36 44
Wind Speed (km/h) 2.28 3.05 4.89 4.5 3.75 5.68
Comments or observations Mostly sunny
Temp (°C) 25 31 31 31 31 30
Tuesday
N/A
Work Permits - UNION work permits are approved, just waiting for Labour Department letter.
Security – UNION now have 2# dedicated security guards which allows work to start on site at 7.00am and finish at 6.00pm.
UNION will most likely work until 6.00pm every day, however the security rota will be agreed every Friday with the 2#
security guards for the week ahead and communicated back to POST.
UNION will arrange directly with the guards to have Saturday working from 7.00am through to 2.00pm as standard with the
option to extend through to 4pm as the need arises.
- END -
Week 5 (FIVE)