A-1.JSA-Service Panel & U.P.S

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 1

THE TATA POWER CO LTD FORMAT NO : S-FM-20

TPREL SOLAR POWER PLANTS

Job Safety Analysis RO-01-10-18

Plant Code: 4381 Date:12-08-2022

Maintenance of Service panel & U.P.S

JSA No: PO/WO No:


PTW NO:
List of Equipments Involved-U.P.S

List of Equipments to be Isolated- Servise panal( MCB siwtich off of Auxilary transformer)
List of Skilled Persons required-2nos
List of Tools & Tackles required- Rachit set, blower
List of PPE required-Insulated tool, Helmet,safety shoes, Safety floves
Name of
Responsible
Tasks Hazard & Risk Controls Person
Sr. No. (Break the job down into steps) (What could harm someone?) (What can be done to make the job safe?) (Who will
make sure it
happens?)
1 Isolation from Dry type transformer MCCB &
isolated from UPS supply.
Electric shock (Electrical) 1. Task need to be performed by authorised person. P.A
2.use Insulated gloves as per voltage rating and safety shoes.3. Maintain safe
distance with live parts.
4. Wear eye goggle to protect eyes from any flashover during switching 5. Follow
Lockout/Tagout and PTW System.

Slip trip fall Check for area cleaning and proper illumination. P.A
2 Check tightness of all connections as MCB's, Stored energy in the circuit (Electrical) 1.use Insulated gloves as per voltage rating and safety shoes. P.A
Energy meter, Busbars, UPS section, Isolation 2. Maintain safe distance with live parts.
transformer section. 3. Use insulated tools

Contact with Reptiles. 1. Maintain safe distance and do physical inspection before starting the work. P.A

3 Check healthyness of all associated MCB's via Stored energy in the circuit (Electrical) 1.use Insulated gloves as per voltage rating and safety shoes. P.A
continuity test 2. Maintain safe distance with live parts.
3. Use insulated tools

Measuring using Faulty insturment and 1. Check the calibration due date of measuring instrument. P.A
probes(Electrical) 2. Use Insulated probes.
4 Cleaning of all compartment through blower Exposed with dust 1. Wear dust mask. P.A

5 Cleaning of panel fan filters Exposed with dust 1. Wear dust mask. P.A
6 Check healthness of Space heaters, Panel Exposure to live parts(Electrical) 1. Task need to be performed by authorised person. P.A
illumination after switching on the AC supply. 2.use Insulated gloves as per voltage rating and safety shoes.
3. Maintain safe distance with live parts. 4. Use
insulated tools

7 Ensure duct fan MPCB healthiness and Amp. Exposure to live parts(Electrical) 1. Task need to be performed by authorised person. P.A
setting. 2.use Insulated gloves as per voltage rating and safety shoes.
3. Maintain safe distance with live parts. 4. Use
insulated tools

U.P.S Collection of tools Injury with collection of wrong 1. Check the healthiness of the Tools. 2.Use Insulated tools. 3.Task need to be P.A
maintainna tools/inadequate tools performed by authorised person. 4. Wear Required PPE.
ce
Isolation of U.P.S from battery Bank and Power Electric shock 1. Task need to be performed by authorised person. 2.use Insulated gloves as per P.A
supply voltage rating and safety shoes.3. Maintain safe distance with live parts. 4. Use
insulated tools 5. Follow Lockout/Tagout and PTW System. 6.Use ARC Flash Suit.
7. Confirm removal of any leftout/foreign items.

Slippery floor 1. Check for slippery surface. 2.Wear Proper PPE3. Check for area cleaning and P.A
proper illumination..

U.P.S internal section cleaning Slipping Durinig Tightness of fastners 1. Check for slippery surface. 2.Wear Proper PPE.3. Check for area cleaning and P.A
proper illumination.
Exposure to dust 1. Wear Nose Mask. 2. Wear Goggles along with PPE.3.Provide adequate P.A
ventilation.

Connect with battery bank Flash Over./Electric shock 1. Task need to be performed by authorised person. 2.use Insulated gloves as per P.A
voltage rating and safety shoes.3. Maintain safe distance with live parts. 4. Use
insulated tools 5. Follow Lockout/Tagout and PTW System. 6.Use ARC Flash Suit.
7. Confirm removal of any leftout/foreign items.

Swicth on the incoming Power Supply of U.P.S Flash Over./Electric shock 1. Task need to be performed by authorised person. 2.use Insulated gloves as per P.A
panel voltage rating and safety shoes.3. Maintain safe distance with live parts. 4. Use
insulated tools 5. Follow Lockout/Tagout and PTW System. 6.Use ARC Flash Suit.
7. Confirm removal of any leftout/foreign items.