List of Goods and Delivery Schedule - Transformers
List of Goods and Delivery Schedule - Transformers
Line Description of Goods Quantity Physical Final Delivery (as per Incoterms) Date
Item unit Destination
Earliest Delivery Latest Delivery Bidder’s offered
N (Project Site) as
Date Date Delivery date [to be
specified in BDS
provided by the
Bidder]
[insert [insert description of Goods] [insert [insert [insert place of [insert the number [insert the [insert the number of
item quantity of physical Delivery] of days following number of days days following the
No] item to be unit for the date of following the date of effectiveness
supplied] the effectiveness of the date of of the Contract]
quantity] Contract] effectiveness of
the Contract]
A. THREE PHASE TRANSFORMERS EQUIPMENT
1. TRANSFOMERS
1.1 50kVA 22/0.4kV 127 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.2 100kVA 22/0.4kV 149 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
Section VII – Schedule of Requirements 70
1.3 200kVA 22/0.4kV 116 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.4 315kVA 22/0.4kV 90 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.5 500kVA 22/0.4kV 19 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.6 1000kVA 22/0.4kV 9 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.8 2000kVA 22/0.4kV 8 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.9 2000kVA 33/0.4kV 3 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia