Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Section VII – Schedule of Requirements 69

1. List of Goods and Delivery Schedule

Line Description of Goods Quantity Physical Final Delivery (as per Incoterms) Date
Item unit Destination
Earliest Delivery Latest Delivery Bidder’s offered
N (Project Site) as
Date Date Delivery date [to be
specified in BDS
provided by the
Bidder]

[insert [insert description of Goods] [insert [insert [insert place of [insert the number [insert the [insert the number of
item quantity of physical Delivery] of days following number of days days following the
No] item to be unit for the date of following the date of effectiveness
supplied] the effectiveness of the date of of the Contract]
quantity] Contract] effectiveness of
the Contract]
A. THREE PHASE TRANSFORMERS EQUIPMENT

1. TRANSFOMERS
1.1 50kVA 22/0.4kV 127 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.2 100kVA 22/0.4kV 149 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
Section VII – Schedule of Requirements 70

1.3 200kVA 22/0.4kV 116 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.4 315kVA 22/0.4kV 90 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.5 500kVA 22/0.4kV 19 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.6 1000kVA 22/0.4kV 9 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.8 2000kVA 22/0.4kV 8 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia
1.9 2000kVA 33/0.4kV 3 each CIP, LEC 120 days from 210 days from
Transformer-three phase Warehouse at Contract signing Contract
Bushrod Island, signing
Monrovia,
Liberia

You might also like