Professional Documents
Culture Documents
Case Study-Drainage Pump House Automation
Case Study-Drainage Pump House Automation
Case Study-Drainage Pump House Automation
Introduction:
There are two Drainage Pump Houses (DPHs) in SMS-1.These pump out
used hot water which is accumulated in two different pits at a depth of 40 feet
below the ground level. There are 4 set of pumps in each DPH. DPHs are
critical for the proper operation of furnaces as it saves the flue paths from
flooding with water.
Problem:
The motor and pump mechanisms of the DPHs are installed 30 feet below the
ground. Pump operators had to go down frequently to check the water level.
When the water level reaches the threshold level the operator was priming the
pump and starting the pump manually from the panel which is at the ground
level. This work was manpower intensive as five pump operators were
required per shift. As the operators had to go down repeatedly to check water
levels, safety was also a major concern.
Also at times there was sudden increase in water levels causing motor to be
submerged and spoiled. The help of fire brigade had to be taken to empty the
pump house. Due to the hot water in the pump houses the pumps used by fire
brigade were often unable to drain the water. As a result the pumps had to be
changed repeatedly causing further delay in operation. Even after the water
was drained out, all the motors were required to be replaced due to low IR
value. But due to shortage of spares, the motors removed from the pump
house were overhauled and installed. This resulted in a total time period of
around one month to normalize the system. The pump mechanism also
required regular maintenance to prevent leakage from foot-valve and glands.
Analysis:
To solve the above problems discussions were carried out among the group. It
was suggested that a submersible pump be used for draining of water to
reduce breakdowns. A plc controlled system was suggested to prevent manual
error & save man power. Brain storming was done to find an alternative to
the manual process of removing motor/pump from the pit during breakdown
or maintenance.
A submersible pump was installed in place of one motor – pump set. The
panel of the old motor-pump set was used for the submersible pump. A new
PLC based panel along with level indicator was incorporated for an
automated system.
Schematic diagram of DPH
PUMP
STARTS
UPPER LEVEL
(1500mm)
PUMP
STOPS
LOWER LEVEL
(500mm)
REFERENCE
BENEFITS:
Tangible Benefits:
Intangible Benefits:
6. Protection for all zero level equipments and personnel from flooding.
----------------0---------------