Weekly Report 7-13 Januari 2023 PDF
Weekly Report 7-13 Januari 2023 PDF
KONSTRUKSI
CASTAVIA ROYALE
AQSHA (CRA)
SEVILLA
ALMAYARA
ROSEVILLE
Handover Estimation
No. Location Unit Status Progress Remarks
(STB)
1 CRA B1-B2 Desember 2022 98% Internal Castavia
2 CRA C6 March 2023 69% Vendor : Arifin
3 CRA C8 Januari 2023 85% Vendor : Suparman
4 CRA D2 Januari 2023 50% Vendor : Supri
5 CRA C3 Mei 2024 79% Vendor : Arifin
6 CRA C7 January 2023 79% Vendor : Arifin
7 CRA B3-B4 February 2023 60% Vendor : Hendi Wijaya
8 CRA C5 October 2023 18% Vendor : Supri
9 CRA B8 September 2023 10% Vendor : Supri
Handover Estimation
No. Location Unit Status Progress Remarks
(STB)
1 ALMAYARA A5 December 2023 52% Vendor : Ramlan
2 ALMAYARA A6 April 2023 52% Vendor : Ramlan
3 ALMAYARA C4 August 2023 18% Vendor : Ramlan
4 ALMAYARA C3 January 2023 79% Internal Castavia
5 ALMAYARA A1 May 2023 8% Vendor : Arifin
6 ALMAYARA A2 November 2023 8% Vendor : Arifin
7 ALMAYARA A3 July 2023 60% Vendor : Ferry
8 ALMAYARA D1 July 2023 1% Vendor : Arifin
9 ALMAYARA E3 June 2023 2% Vendor : Ferry
10 ALMAYARA E4 June 2023 2% Vendor : Ferry
Handover Estimation
No. Location Unit Status Progress Remarks
(STB)
1 ALMAYARA C1 January 2023 91% Waiting Vendor/Contractor
2 ALMAYARA C10 November 2023 0% Waiting Vendor/Contractor
Handover Estimation
No. Location Unit Status Progress Remarks
(STB)
1 ROSEVILLE A2 40% Waiting Vendor/Contractor
2 ROSEVILLE A4 January 2024 0% Waiting Vendor/Contractor
3 ROSEVILLE A5 June 2024 0% Waiting Vendor/Contractor
4 ROSEVILLE A7 April 2023 0% Waiting Vendor/Contractor
5 ROSEVILLE B5 September 2023 0% Waiting Vendor/Contractor
6 ROSEVILLE B12 November 2023 0% Waiting Vendor/Contractor
7 ROSEVILLE B13 November 2023 0% Waiting Vendor/Contractor
Handover
No. Location Unit Status Progress Remarks
Estimation (STB)
1 MAHAKAM A5 & A6 April 2024 0% Waiting Vendor
Security Office
FACILITY & EXTERNAL
WORK