MONTHLY TIME SUSPENSION REPORT

For JULY 2015

#REF! Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road
Standards (HDM-4 Project Analysis) (Intermittent Sections) along Acop – Kapangan – Kibungan – Bakun Road,
K0322+115 – K0326+935
#REF! #REF!
Date Weather Remarks Time Suspension Recommended
1 Cloudy/Rainy
2 Rainy Work Suspended 1
3 Cloudy/Rainy
4 Rainy Work Suspended 1
5 Typhoon Work Suspended 1
6 Typhoon Work Suspended 1
7 Typhoon Work Suspended 1
8 Typhoon Work Suspended 1
9 Typhoon Work Suspended 1
10 Typhoon Work Suspended 1
11 Rainy Work Suspended 1
12 Rainy Work Suspended 1
13 Rainy Work Suspended 1
14 Rainy Work Suspended 1
15 Rainy Work Suspended 1
16 Rainy Work Suspended 1
17 Rainy Work Suspended 1
18 Rainy Work Suspended 1
19 Cloudy/Light Rain Work Suspended 1
20 Cloudy/Light Rain
21 Rainy Work Suspended 1
22 Rainy Work Suspended 1
23 Cloudy/Light Rain
24 Cloudy/Light Rain
25 Cloudy/Light Rain
26 Rainy Work Suspended 1
27 Rainy Work Suspended 1
28 Rainy Work Suspended 1
29 Cloudy/Rainy Work Suspended 1
30 Rainy
31 Fair
TOTAL SUSPENSION TIME RECOMMENDED FOR THIS MONTH 23
TOTAL SUSPENSION TIME RECOMMENDED PREVIOUSLY
GRAND TOTAL TO DATE 23
TOTAL PREDETERMINED UNWORKABLE RAINY DAYS 48
TOTAL NUMBER OF UNWORKABLE RAINY DAYS CONSIDERED FOR TIME EXTENSION
ORIGINAL CONTRACT TIME (Calendar Days) 285
ORIGINAL EXPIRY DATE #REF!
REVISED EXPIRY DATE due to approved Variation Orders
REVISED EXPIRY DATE due to approved Time Extensions due RROW
REVISED EXPIRY DATE due to approved Time Extensions due to Adverse Weather Condition
REVISED EXPIRY DATE DUE TO THIS SUSPENSION EXTENSION #REF!
PERCENT TIME ELAPSED 11.23%

Prepared by: Concurred by:

#REF! #REF!
Project Engineer General Manager
(DPWH) (Contractor)

Submitted by: RECOMMENDING APPROVAL:

CLIFTON D. VALENCERINA ALBERTO N. GAHID


Chief, Construction Division OIC-Assistant Regional Director
APPROVED:

EDILBERTO P. CARABBACAN, CESO IV


Regional Director
MONTHLY TIME SUSPENSION REPORT
For August 2015

#REF! Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road
Standards (HDM-4 Project Analysis) (Intermittent Sections) along Acop – Kapangan – Kibungan – Bakun Road,
K0322+115 – K0326+935
#REF! #REF!
Date Weather Remarks Time Suspension Recommended
1 Fair
2 Rainy Work Suspended 1
3 Rainy Work Suspended 1
4 Light Rain
5 Fair
6 Fair
7 Light Rain
8 Cloudy/Light Rain
9 Cloudy/Light Rain
10 Rainy Work Suspended 1
11 Rainy Work Suspended 1
12 Rainy Work Suspended 1
13 Light Rain
14 Light Rain
15 Light Rain
16 Fair
17 Fair
18 Cloudy/Light Rain
19 Cloudy/Light Rain
20 Typhoon Work Suspended 1
21 Typhoon Work Suspended 1
22 Typhoon Work Suspended 1
23 Rainy Work Suspended 1
24 Rainy Work Suspended 1
25 Rainy Work Suspended 1
26 Rainy Work Suspended 1
27 Rainy Work Suspended 1
28 Fair Work Suspended 1
29 Rainy Work Suspended 1
30 Rainy Work Suspended 1
31 Rainy Work Suspended 1
TOTAL SUSPENSION TIME RECOMMENDED FOR THIS MONTH 17
TOTAL SUSPENSION TIME RECOMMENDED PREVIOUSLY 23
GRAND TOTAL TO DATE 40
TOTAL PREDETERMINED UNWORKABLE RAINY DAYS 48
TOTAL NUMBER OF UNWORKABLE RAINY DAYS CONSIDERED FOR TIME EXTENSION
ORIGINAL CONTRACT TIME (Calendar Days) 285
ORIGINAL EXPIRY DATE #REF!
REVISED EXPIRY DATE due to approved Variation Orders
REVISED EXPIRY DATE due to approved Time Extensions due RROW
REVISED EXPIRY DATE due to approved Time Extensions due to Adverse Weather Condition
REVISED EXPIRY DATE DUE TO THIS SUSPENSION EXTENSION #REF!
PERCENT TIME ELAPSED 22.11%

Prepared by: Concurred by:

#REF! #REF!
\ General Manager
(DPWH) (Contractor)

Submitted by: RECOMMENDING APPROVAL:

CLIFTON D. VALENCERINA ALBERTO N. GAHID


Chief, Construction Division OIC-Assistant Regional Director
APPROVED:

EDILBERTO P. CARABBACAN, CESO IV


Regional Director
MONTHLY TIME SUSPENSION REPORT
For September 2015

#REF! Road Upgrading (Gravel to Paved) Based on Gravel Road Strategies, Traffic Benchmark for Upgrading to Paved Road
Standards (HDM-4 Project Analysis) (Intermittent Sections) along Acop – Kapangan – Kibungan – Bakun Road,
K0322+115 – K0326+935
#REF! #REF!
Date Weather Remarks Time Suspension Recommended
1 Rainy Work Suspended 1
2 Rainy Work Suspended 1
3 Rainy Work Suspended 1
4 Rainy Work Suspended 1
5 Rainy Work Suspended 1
6 Rainy Work Suspended 1
7 Rainy Work Suspended 1
8 Rainy Work Suspended 1
9 Rainy Work Suspended 1
10 Rainy Work Suspended 1
11 Cloudy/Rainy Work Suspended 1
12 Fair Work Suspended 1
13 Fair Work Suspended 1
14 Fair Work Suspended 1
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
TOTAL SUSPENSION TIME RECOMMENDED FOR THIS MONTH 14
TOTAL SUSPENSION TIME RECOMMENDED PREVIOUSLY 40
GRAND TOTAL TO DATE 54
TOTAL PREDETERMINED UNWORKABLE RAINY DAYS 48
TOTAL NUMBER OF UNWORKABLE RAINY DAYS CONSIDERED FOR TIME EXTENSION 6
ORIGINAL CONTRACT TIME (Calendar Days) 285
ORIGINAL EXPIRY DATE #REF!
REVISED EXPIRY DATE due to approved Variation Orders
REVISED EXPIRY DATE due to approved Time Extensions due RROW
REVISED EXPIRY DATE due to approved Time Extensions due to Adverse Weather Condition
REVISED EXPIRY DATE DUE TO THIS SUSPENSION EXTENSION #REF!
PERCENT TIME ELAPSED 27.37%

Prepared by: Concurred by:

#REF! #REF!
Project Engineer General Manager
(DPWH) (Contractor)

Submitted by: RECOMMENDING APPROVAL:


CLIFTON D. VALENCERINA ALBERTO N. GAHID
Chief, Construction Division OIC-Assistant Regional Director

APPROVED:

EDILBERTO P. CARABBACAN, CESO IV


Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 9

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective October 1, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 8

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 26, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 7

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 22, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 6

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 16, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 5

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 11, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 4

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 7, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 3

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
CONTRACTOR : 3K ROCK ENGINEERING

DATE : #REF!

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective September 1, 2014.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

#REF! ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 2

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
Sections

STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681


LOCATION : Baguio City
CONTRACTOR : 3K ROCK ENGINEERING

DATE : June 24, 2015

ROGELIO S. SEPIAN
General Manager
R.S. SEPIAN CONSTRUCTION & TRUCKING

You are hereby directed to resume all construction operations effective June 24, 2015.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

ISMAEL B. DELA CRUZ FRANCIS B. CUYOP


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

RESUME ORDER NO. 1

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
Sections

STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681


LOCATION : Baguio City
CONTRACTOR : 3K ROCK ENGINEERING

DATE : June 21, 2015

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to resume all construction operations effective June 21, 2015.

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

ISMAEL B. DELA CRUZ FRANCIS B. CUYOP


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 3

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 1, 2014
due to the road right of way.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . 12 calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 1

PROJECT NAME : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and Management-4
(HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent Sections
STATION LIMITS : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
LOCATION : Baguio City
CONTRACTOR : 3K ROCK ENGINEERING

DATE : June 03, 2015

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective June 3, 3015
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . 220 calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . 14 calendar days
Days remaining ...................... 206 calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

ISMAEL B. DELA CRUZ FRANCIS B. CUYOP


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 2

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
Sections
STATION LIMIT : K300+134 - K0300+911; K0301+195 - K0305+000; K0305+290 - K0305+681
LOCATION : Baguio City
Contractor : 3K ROCK ENGINEERING

DATE : June 22, 2015

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective June 22, 2015
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . . 220 calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . 33 calendar days
Days remaining ...................... 187 calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

ISMAEL B. DELA CRUZ FRANCIS B. CUYOP


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 4

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 1, 2014
due to road right of way.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 5

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 7, 2014
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 6

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 14, 2014
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 7

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 19, 2014
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 8

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 24, 2014
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME SUSPENSION/EXTENSION ORDER NO. 9

PROJECT NAME & NO. : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage,
K300+134Based on Pavement
- K0300+911; Management
K0301+195 System/ Highway
- K0305+000; Development
K0305+290 and
- K0305+681
STATION LIMIT :
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
LOCATION : Baguio
SectionsCity
Contractor : 3K ROCK ENGINEERING

DATE : #REF!

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend all construction activities effective September 30, 2014
due to adverse weather condition and unworkable road base due to oversaturation of materials.

Contract time including extensions/suspensions. . . . . . #VALUE! calendar days


Days used to date . . . . . . . . . . . . . . . . . . . . . . #VALUE! calendar days
Days remaining ...................... #VALUE! calendar days

Please acknowledge receipt of this order by dating, signing and returning three (3) of the attached copies.
The other copy is for your file.

VERIFIED BY: CONCURRED BY:

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME EXTENSION DUE TO WEATHER

FOR THE MONTH OF : June 2015

REGION : CAR
PROJECT : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
Drainage, Based on Pavement Management System/ Highway Development and
Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
Sections
STATION LIMITS : #REF!
LOCATION : Baguio City

DATE WEATHER REASON FOR TIME EXTENSION TIME EXTENSION


RECOMMENDED

June 3, 4, 5, 6, 7, 8,
Time extension due to adverse weather
9, 10, 11, 12, 13, 14,
15, 16, 17, 18, 19, 20,
Heavy Rainfall condition and unworkable road base due to 18 Day
oversaturation of materials
2015
Time extension due to adverse weather
June 22, 23, 2015 Heavy Rainfall condition and unworkable road base due to 2 Days
oversaturation of materials

TOTAL CALENDARS DAYS 20 Days

Total Extension of Time Recommended ============================ == 20 DAYS


Total Extension of Time Recommended Previously====================== == DAYS
Grand total to date ======================================== == 20 DAYS
Original contract time======================================= == 220 DAYS
Revised contract time due to approved extensions/suspensions============== == 240 DAYS
Date of effectivity of contract ================================= == May 19, 2015
Original Expiry Date ======================================== == December 24, 2015
Revised Expiry Date due to Approved Time Extension/Suspension No. 1======== == January 13, 2016
Percent of Time Elapse ====================================== == 17.92%

PREPARED BY: CONCURRED BY;

ISMAEL B. DELA CRUZ FRANCIS B. CUYOP


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief, Construction Division Regional Director
WORK RESUMPTION ORDER NO. 1

Contract I.D No. : 15P00014


Name of Project
: Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads
Including Drainage, Based on Pavement Management System/ Highway
Development and Management-4 (HDM-4) Along Quirino Highway (Baguio-
Bauang) (S00420LZ) Intermittent Sections K300+134 - K0300+911; K0301+195 -
K0305+000; K0305+290 - K0305+681

Location : Baguio City


Date : June 21, 2015

To: `

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

Effective to date, you are directed to resume construction operations in the project site in
view of the good weather condition and workable, dried road base.

Hereunder is the historical dat of your approved Work Suspension Order and Contract
Time Extension.

Approved Contract
Original Contract Approved Work Suspension
Time Extension: 18 Days Used to Date: 33 CD
Time: 220 CD Order: 18 CD
CD
Contract Time W.S.O No. 1: 18 CD C.T.E. No. 1: 18 CD
including extension: W.S.O No. 2: C.T.E. No. 2:
Days remaining: 205 CD
238 CD Total: 18 CD Due to V.O.:
Total: 18 CD

Please acknowledge receipt of this order by signing (with date) and returning the three
(3) of the attached copies. The fourth copy is for your file.

ISMAEL B. DELA CRUZ


Project Engineer

NOTED:

CLIFTON D. VALENCERINA
Chief, construction Division

RECOMMENDING APPROVAL: APPROVED:


ALBERTO N. GAHID EDILBERTO P. CARABBACAN
Assistant Regional Director Regional Director

I hereby acknowledge receipt of the above notice.

DATE:

3K ROCK ENGINEERING
Contractor
By:

Authorized Representative
WORK SUSPENSION ORDER NO. 2

Contract I.D No. : 15P00014


Name of Project
: Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads
Including Drainage, Based on Pavement Management System/ Highway
Development and Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang)
(S00420LZ) Intermittent Sections K300+134 - K0300+911; K0301+195 -
K0305+000; K0305+290 - K0305+681

Location : Baguio City


Date : June 22, 2015

To: `

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

You are hereby directed to suspend construction operations effective June 22, 2015 due to
adverse weather condition and unworkable road base due to oversaturation of materials.

Hereunder is the historical dat of your approved Work Suspension Order and Contract
Time Extension.

Original Contract Approved Work Suspension Approved Contract Time


Days Used to Date: 33 CD
Time: 220 CD Order: 18 CD Extension: 18 CD

Contract Time W.S.O No. 1: 18 CD C.T.E. No. 1: 18 CD


including extension: W.S.O No. 2: 2 CD C.T.E. No. 2
Days remaining: 205 CD
238 CD Total: 20 CD Due to V.O.
Total:

Please acknowledge receipt of this order by signing (with date) and returning the three
(3) of the attached copies. The fourth copy is for your file.

ISMAEL B. DELA CRUZ


Project Engineer

NOTED:

CLIFTON D. VALENCERINA
Chief, construction Division

RECOMMENDING APPROVAL: APPROVED:


ALBERTO N. GAHID EDILBERTO P. CARABBACAN
Assistant Regional Director Regional Director

I hereby acknowledge receipt of the above notice.

DATE:

3K ROCK ENGINEERING

By:

Authorized Representative
WORK RESUMPTION ORDER NO. 2

Contract I.D No. : 15P00014


Name of Project
: Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads
Including Drainage, Based on Pavement Management System/ Highway
Development and Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang)
(S00420LZ) Intermittent Sections K300+134 - K0300+911; K0301+195 -
K0305+000; K0305+290 - K0305+681

Location : Baguio City


Date : June 24, 2015

To: `

FRANCIS B. CUYOP
General Manager
3K ROCK ENGINEERING

Effective to date, you are directed to resume construction operations in the project site in
view of the good weather condition and workable, dried road base.

Hereunder is the historical dat of your approved Work Suspension Order and Contract
Time Extension.

Original Contract Approved Work Suspension Approved Contract


Days Used to Date: 36 CD
Time: 220 CD Order: 20 CD Time Extension: 20 CD

Contract Time W.S.O No. 1: 18 CD C.T.E. No. 1: 18 CD


including extension: W.S.O No. 2: 2 CD C.T.E. No. 2: 2 CD
Days remaining: 204 CD
240 CD Total: 20 CD Due to V.O.:
Total: 20 CD

Please acknowledge receipt of this order by signing (with date) and returning the three
(3) of the attached copies. The fourth copy is for your file.

ISMAEL B. DELA CRUZ


Project Engineer

NOTED:

CLIFTON D. VALENCERINA
Chief, construction Division

RECOMMENDING APPROVAL: APPROVED:


ALBERTO N. GAHID EDILBERTO P. CARABBACAN
Assistant Regional Director Regional Director

I hereby acknowledge receipt of the above notice.

DATE:

3K ROCK ENGINEERING
Contractor
By:

Authorized Representative
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME EXTENSION DUE TO RROW

FOR THE MONTH OF : August 2014

REGION : CAR
PROJECT : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
STATION LIMITS : Drainage, Based on Pavement Management System/ Highway Development and
#REF!
LOCATION : Management-4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent
###
Sections

DATE WEATHER REASON FOR TIME EXTENSION TIME EXTENSION


RECOMMENDED

Fair & Light


August 24-31, 2014
Rainfall
Time extension due to Road Right of Way 8 Days

TOTAL CALENDARS DAYS 8 Days

Total Extension of Time Recommended ============================ == 8 DAYS


Total Extension of Time Recommended Previously====================== == 20 DAYS
Grand total to date ======================================== == 28 DAYS
Original contract time======================================= == 269 DAYS
Revised contract time due to Variation Order ======================== == 309 DAYS
Revised contract time due to approved extensions/suspensions============== == 337 DAYS
Date of effectivity of contract ================================= == August 6, 2014
Original Expiry Date ======================================== == May 1, 2015
Revised expiry date due to Variation Order No. 01 ===================== == June 10, 2014
Revised Expiry Date due to Approved Time Extension/Suspension No. 1======== == July 8, 2015
Percent of Time Elapse ====================================== == 1.50%

PREPARED BY: CONCURRED BY;

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME EXTENSION DUE TO RROW

FOR THE MONTH OF : September 2014

REGION : CAR
PROJECT : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
STATION LIMITS : Drainage,
#REF! Based on Pavement Management System/ Highway Development and Management-
LOCATION : 4 (HDM-4) Along Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent Sections
Baguio City

DATE WEATHER REASON FOR TIME EXTENSION TIME EXTENSION


RECOMMENDED

Fair & Light


September 1-6, 2014
Rainfall
Time extension due to Road Right of Way 6 Days

TOTAL CALENDARS DAYS 6 Days

Total Extension of Time Recommended ============================ == 6 DAYS


Total Extension of Time Recommended Previously====================== == 28 DAYS
Grand total to date ======================================== == 34 DAYS
Original contract time======================================= == 269 DAYS
Revised contract time due to Variation Order ======================== == 309 DAYS
Revised contract time due to approved extensions/suspensions============== == 343 DAYS
Date of effectivity of contract ================================= == August 6, 2014
Original Expiry Date ======================================== == May 1, 2015
Revised expiry date due to Variation Order No. 01 ===================== == June 10, 2014
Revised Expiry Date due to Approved Time Extension/Suspension No.1========= == July 14, 2015
Percent of Time Elapse ====================================== == 1.70%

PREPARED BY: CONCURRED BY;

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief Construction Division Regional Director
Republic of the Philippines
DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
CORDILLERA ADMINISTRATIVE REGION
Office of the Regional Director
Engineer's Hill, Baguio City

TIME EXTENSION DUE TO WEATHER

FOR THE MONTH OF : September 2014

REGION : CAR
PROJECT : Rehabilitation/ Reconstruction/ Upgrading of Damaged Paved National Roads Including
STATION LIMITS : Drainage,
#REF! Based on Pavement Management System/ Highway Development and Management-
LOCATION : 4 (HDM-4)
Baguio CityAlong Quirino Highway (Baguio-Bauang) (S00420LZ) Intermittent Sections

DATE WEATHER REASON FOR TIME EXTENSION TIME EXTENSION


RECOMMENDED

Time extension due to adverse weather


September 7-10, 2014 Heavy Rainfall condition and unworkable road base due to 4 Days
oversaturation of materials
Time extension due to adverse weather
September 14-15, 2014 Heavy Rainfall condition and unworkable road base due to 2 Days
oversaturation of materials
Time extension due to adverse weather
September 19-21, 2014 Heavy Rainfall condition and unworkable road base due to 3 Days
oversaturation of materials
Time extension due to adverse weather
September 24-25, 2014 Heavy Rainfall condition and unworkable road base due to 2 Days
oversaturation of materials
Time extension due to adverse weather
September 30, 2014 Heavy Rainfall condition and unworkable road base due to 1 Days
oversaturation of materials

TOTAL CALENDARS DAYS 12 Days

Total Extension of Time Recommended ============================ == 12 DAYS


Total Extension of Time Recommended Previously====================== == 34 DAYS
Grand total to date ======================================== == 46 DAYS
Original contract time======================================= == 269 DAYS
Revised contract time due to Variation Order ======================== == 309 DAYS
Revised contract time due to approved extensions/suspensions============== == 355 DAYS
Date of effectivity of contract ================================= == August 6, 2014
Original Expiry Date ======================================== == May 1, 2015
Revised expiry date due to Variation Order No. 01 ===================== == June 10, 2014
Revised Expiry Date due to Approved Time Extension/Suspension No.1========= == July 26, 2015
Percent of Time Elapse ====================================== == 5.10%

PREPARED BY: CONCURRED BY;

DOMINGO A. ENCISO ROGELIO S. SEPIAN


Project Engineer General Manager

RECOMMENDING APPROVAL: APPROVED:

CLIFTON D. VALENCERINA EDILBERTO P. CARABBACAN, CESO IV


Chief Construction Division Regional Director
Republic of the Philippines
COMMISSION ON AUDIT
CORDILLERA ADMINISTRATIVE REGION
La Trinidad, Benguet

SUMMARY OF TIME SUSPENSION / EXTENSION

Name of Project : Construction of COA PSAO


Location : Payanan, Luna, Apayao
Contractor : LINCEE GENERAL CONSTRUCTION and GENERAL MERCHANDISE
Date Started : January 6, 2022
Original Expiry Date : November 1, 2022 Revised Expiry Date Due to T.E. : March 31, 2023
Original Contract Time : 300 CD Rev. Contract Time Due to T.E. : 450 CD

REVISED
REVISED EXPIRY
ORIGINAL APPROVED CONTRACT TIME CONTRAC DAYS
TIME EXTENSION/ NO. OF DAYS DATE DATE DUE TO REASON FOR SUSPENSION/
MONTH/YEAR DATE SUSPENDED DURATIO TIME INCLUDING T TIME REMAININ
SUSPENSION SUSPENDED RESUMED EXTENSION/ EXTENSION
N EXTENSION EXTENSION/ USED G
SUSPENSION
SUSPENSION

Previously Approved T.E # 1 due to


Monthly Time Suspension January 2022 26,27,28, and 30 4 300 4 304 November 5, 2022 1 303
adverse weather condition

Monthly Time Suspension February, 2022 21 to 28 8 300 8 312 November 13, 2022 31 281
Work Suspension due to Lot Boundary
dispute
Monthly Time Suspension March, 2022 1 to 15 15 300 March 16, 2022 15 327 November 28, 2022

Monthly Time Suspension March, 2022 16,17, and 20 3 300 3 330 December 1, 2022 59 271

Monthly Time Suspension April, 2022 1,2,3,4,7, and 8 6 300 6 336 December 7, 2022 90 246

2,3,16,17,18,19,21,22, Previously Approved T.E # 1 due to


Monthly Time Suspension May, 2022 11 300 11 347 December 18, 2022 120 227
25,29, and 30 adverse weather condition

7,8,13,14,18,23,24,
Monthly Time Suspension June, 2022 8 300 6 353 December 24, 2022 151 202
and 27

Monthly Time Suspension July, 2022 5,7,11,12,21, and 24 6 300 353 December 24, 2022 181 172

Monthly Time Suspension August, 2022 17,20,21,22, and 23 5 300 5 358 December 29, 2022 212 146

Suspended Days due to Adverse


Monthly Time Suspension September, 2022 22,23,28, and 29 4 300 4 362 January 2, 2023 243 119
Weather Condition (T.E # 2)

10,11,12,13,14,15,16,1
Monthly Time Suspension October, 2022 12 300 12 374 January 14, 2023 273 101
9,20,21,30, and 31
4,12,13,14,17,18,19,21
Monthly Time Suspension November, 2022 9 300 9 383 January 23, 2023 304 79
, and 30

1,3,4,6,7,8,10,12,13,
Suspended Days due to Adverse
Monthly Time Suspension December 2022 15,16,17,19,20,21,27, 20 300 20 403 February 12, 2023 334 69
Weather Condition (T.E # 3)
28,29,30, and 31

Monthly Time Suspension January 2023 1,2,5, and 6 4 300 1 404 February 13, 2023 365 39

22,23,27,28,29,30, and
Monthly Time Suspension January 2023 7 300 7 411 February 20, 2023 396 15
31
Suspended Days due to Adverse
Weather Condition (T.E # 4)
1,2,14,15,16,17,20,21,
Monthly Time Suspension February 2023 14 300 14 425 March 6, 2023 424 1
22,23,24,25,26, and 27

TOTAL RECOMMENDED
TOTAL SUSPENDED DAYS 136 21
TIME EXTENSION

Time Extension due to Variation Order 25 CD


Time Extension due to Work Suspension and Monthly Time Suspension 125 CD
Total Time Extension 150 CD

NOTE: The Contractor, LINCEE GENERAL CONSTRUCTION and GENERAL MERCHANDISE , will not file any monetary claim by virtue of this Extension of Contract Time and with the consent/conformity of the Contractor's Bondsman.

Conformed by: Prepared by: Checked & Reviewed by : Approved by:

ENGR. JEREMY B. DARCIO ENGR. JUN JUN P. ANCHETA ARCH. ERWIN DARIO B. CASTILLO ENGR. RONALD L. FERNANDO RENATO O. ROSALES
Authorized Managing Officer Project Engineer Project Architect Project Head OIC Regional Director