Professional Documents
Culture Documents
Insight July 2021 230313 122223
Insight July 2021 230313 122223
Insight July 2021 230313 122223
www.fenwickelliott.com
01 Insight Issue 91
However, in order to ensure that the Engineer’s role is as envisaged, it is essential that not only are the
Engineer’s powers and obligations known (and understood) by all involved, but that the Engineer has the
right qualifications and resources to make appropriate use of them. Deeming provisions and time bars are
in place to ensure that delays in carrying out certain requirements and/or failures to review documents
(such as programmes) in time have real consequences. The Engineer’s role is, therefore, a sophisticated one
and anyone taking that role on needs to spend time studying their responsibilities in advance.
Who is the Engineer? Engineer to exercise a power. That said, appointment requirements and the
the Employer’s consent is deemed to provisions on the replacement of the
have been given when the Engineer Engineer in clause 3.6, which provide
The Engineer fulfils the project
does exercise that power. In any event, that the Contractor has a right to raise
manager or contract administration
the Employer’s consent is not required reasonable objections if someone
role in the FIDIC Yellow and Red
2 3
for the Engineer to reach a unsuitable is nominated, sits rather
Books.4 Under Clause 3.1, the Engineer
determination and any amendments oddly with the concept of the Engineer
can be a person or “a legal entity” (i.e.
to this effect would, in our view, have a being part of the Employer. It is also
a company, partnership, etc). If they
major impact on the functionality of difficult to envisage how an employee
are a legal entity, then a natural
the contract provisions, arguably of the Employer could act “neutrally”
person must be appointed to act on its
breaching FIDIC’s golden principles in when making a determination (as to
behalf, and notice must be given to
the process.7 which see further below).
the Parties as to who that person is.
Whoever is appointed must be a
professional engineer5 having suitable The Engineer’s Representative The governing law of the contract may
qualifications, experience and also impact on the answer to this
competence to act, and must be question. For example, English case law
The Engineer’s Representative was a
fluent in the ruling language6. suggests that the Employer cannot
new concept introduced by the 2017
assume the role of construction
editions. It provides for a natural
manager and decision maker unless
Unless the terms of Clause 3.1 are person to be based at the site the
there is an express contractual
amended, these requirements can whole time that the works are being
provision permitting them to do so.10
cause difficulties for employers who executed. The Engineer’s
More generally, under English law,
would normally appoint project Representative is not to be confused
contract administrators must act in a
managers who are not necessarily with the natural person authorised to
fair and unbiased manner11 and it
engineers (perhaps, because they are act as the Engineer (where a legal
would be very hard for Employer’s
cheaper), since a failure to comply with entity appointed as the Engineer). The
employees to achieve that, in reality.
them would be a breach of contract. option of having someone based on
site reflects the increased focus and
project management in the 2017 What role does the Engineer play?
The duties and authority of the
editions. However, it obviously comes
Engineer are set out in Clause 3.2 and
with a cost attached to it.
provide that the Engineer must act as As already noted, the Engineer has a
a “skilled professional”. They will also very significant project management
be deemed to act for the Employer Finally, it is important to realise that role under the 2017 forms. Examples of
unless stated otherwise (for example, the Engineer’s powers can be the Engineer’s role (and tools for
in Clause 3.7, in the context of an delegated to the Engineer’s project management) include:12
Engineer’s Determination). However, Representative save for in relation to
the Engineer does not have unfettered two crucial respects. These are: (a)
1. Notifying the Contractor of the
powers. For example, they have no Determinations;8 and (b) Notices to
Commencement Date not less
authority to amend the contract and Correct9.
than 14 days before that date;13
cannot relieve anyone of any duty,
obligation or responsibility under the 2. Reviewing programmes;14
So, can the Engineer be an employee
contract. 3. Measuring the Works;15
of the Employer?
4. Issuing payment certificates;16
Further, the Particular Conditions 5. Issuing instructions (including for
Nothing within the FIDIC form
should state where the Employer’s variations);17
expressly prevents this. However, the
consent is required in order for the 6. Ensuring that the personnel of the
02 Insight Issue 91
contractor act professionally and highly effective project and risk programme is delayed and (rather
safely and removing them the site management tool to be created.25 crucially) no extension of time is due
if they do not;18 (i.e. the delay is the Contractor’s
7. Inspection and testing of the fault). The revised programme can
The Engineer must provide notice of
works;19 instruct revised methods for
any comments on programmes
expediting the programme and
8. Issuing notices to correct submitted by the Contractor within 21
completing on time. Costs for
failures;20 days after receiving the initial
implementing the revised programme
9. Issuing Taking-Over programme, or 14 days after receiving
are at the contractor’s risk, the
Certificate(s);21 a revised programme. If he does not
contractor must adopt it unless the
do so, he is deemed to have given a
10. Issuing the Performance engineer notifies otherwise, and the
Notice of No-Objection to the
Certificate;22 employer can notify a claim for costs
programme in question. Again, the
11. Assessing and making a neutral if they incur expense as a result of it.
Engineer has to be organised and
determination.23 ensure that he responds in the correct
time periods or an important However, this power comes with a
We take a look at some of these tools opportunity to put the project on the health warning. If the delays are due
in more detail below. right footing from the beginning will to matters entitling the Contractor to
be lost. an extension of time, the Contractor
will be entitled to their costs and the
Issuing Instructions revised methods will, in fact, be
Advanced Warning
acceleration.26 This is, therefore, a
Under Clause 3.5, the Engineer can potential recipe for disputes if not
issue instructions necessary for the Clause 8.4 also allows the Engineer (as used properly and, in particular, if
execution of the works. The well as the Parties) to issue an there is a dispute brewing as to
Contractor must then comply with advanced warning of circumstances extension of time entitlement when it
then unless: (a) the instruction is which: (a) adversely affect the work of is used.
actually a Variation but doesn’t say the Contractor’s Personnel; (b)
that; (b) or it is not compliant with adversely affect the performance of
Records, records and records
the applicable Laws, is unsafe or the Works to be completed; (c) may
technically impossible. increase the Contract Price; or (d)
may delay the Works. The Engineer Under Clause 20.2.3, the Engineer may
can also request proposals to avoid or also monitor the Contractor’s
If the contractor believes that the minimise the effect of issues under contemporaneous records after
instruction is a Variation, then they Clause 13.3.2 [Variation by Request for events giving rise to a Claim, instruct
must issue a notice to the Engineer Proposal] in order to avoid or mitigate the contractor to keep additional
immediately and (crucially) before the effects of such events. records, inspect those records (during
commencing the works. The Engineer normal working hours or as agreed)
then has 7 days to respond to that and ask for copies of them. No
Notice or the instruction is deemed to This is potentially a powerful risk
implied acceptance of them is
be revoked. This is helpful because it management tool, especially if used in
deemed to be given as a result of
is an opportunity for the Contractor conjunction with risk management
inspecting the records.
to challenge a Variation by the back meetings and, if appropriate, a
door followed by a refusal to pay later recovery programme.
on. Theoretically, this provision (if This is, undoubtedly, a useful tool
acted on) should enable the parties to allowing the Engineer (and the Parties
Risk Management Meetings
avoid typical “it’s a variation, oh no it generally) to keep track of the
isn’t” arguments developing. It also quantum or length of delays
allows the Employer to cancel a Under Clause 3.8, the Engineer can associated with any Claims after they
Variation in advance if unanticipated also require attendance at meetings have been notified. From the
consequences in terms of time and with the Contractor’s representatives Employer’s perspective, this power
expense flow from something initially and other contractors, Sub- should, if used properly, reduce the
thought to be straightforward. Contractors and Suppliers. The likelihood of exaggerated claims at
Engineer can keep records and supply the end of a project. For the
them to others in attendance. Contractor, it is helpful to try and
The Programme Actions can be noted but must be in agree the format of records and get
accordance with the Contract. the Employer to buy into any records
Clause 8.3 requires the Engineer to as it will make it harder for them to
“Review” the initial as-planned reject the records as inadequate later
Recovery Programme
programme as well as subsequent on.
iterations.24 They must do this against
a detailed list of requirements, with Clause 8.7 also allows the Engineer to
emphasis put on early detail to allow a instruct a recovery programme if the
03 Insight Issue 91
In making a determination, the Engineer must act The procedure, as a whole, is much more detailed and it
“neutrally”. This word was chosen specifically to avoid contains additional time limits on the Engineer when
issues with words such as impartially and independently agreeing or (if agreement is not possible) determining any
experienced in Civil Law jurisdictions historically. This matter or Claim. The aim is to resolve disputes between
neutrality obligation doesn’t apply elsewhere, for example, parties at an earlier stage so as to avoid the need for a
when issuing payment certificates. However, given a DAAB decision and/or any arbitral award. Obviously, for
dispute on a payment certificate may end up in a Claims for money or time, Parties must be vigilant of the
determination, an Engineer should always have the time bar for notification (and procedures for providing the
obligation to act neutrally in mind. necessary particulars) in Clause 20.2.1.