Professional Documents
Culture Documents
6-Request AC - Ventilation Work Inspection 01 - 02
6-Request AC - Ventilation Work Inspection 01 - 02
#NAME?
Project : ### Date : Time :
Contractor : RFWI : Ref. Dwgs./Specs. __
LOCATION :
REMARKS : (Those activities which are rejected must be reported within this section, the next activity must not be started until rectification is complete and re-inspected)
OPERATIONS:
QC
BY : (Print Name)
ACCEPTED REJECTED
PROJECT MANAGER
APRPOVED BY : NOTED: (Print Name)
BY : (Print Name)
VP-CONSTRUCTION OPERATIONS
Note : This From shall be submitted 24 hrs. before inspection and accompanied with Shop Drawings.
LOCATION :
REMARKS : (Those activities which are rejected must be reported within this section, the next activity must not be started until rectification is complete and re-inspected).
OPERATIONS:
QC
BY : (Print Name)
APPROVED BY :
BY : (Print Name)
VP-CONSTRUCTION OPERATIONS
Note : This From shall be submitted 24 hrs. before inspection and accompanied with Shop Drawings.