FIRST FLOOR

1. General storage room = ORDINARY HAZARD


Total area= 75m2
Design Area
No of sprinklers=
Area covered per sprinkler
Table 13.2.5.2.1 CMSA Sprinklers
Spacing each sprinkler= 3.7m
Protection area= 12m2
2
75 m
No of sprinklers= =6.25∨6 sprinklers
12 m2

1.2∗ √ designarea∈ft 1.2∗√ 807.3


No of sprinklers per branch= =
distance of sprinkler ∈ft 12 ft
No of sprinklers per branch=2.8∨3
6 total sprinklers
=2 branches
3 sprinklers per branch
2. School supplies store = ORDINARY HAZARD
Total area= 100m2
Design Area
No of sprinklers=
Area covered per sprinkler
Table 13.2.5.2.1 CMSA Sprinklers
Spacing each sprinkler= 3.7m
Protection area= 12m2
2
100 m
No of sprinklers= 2
=8.333∨9 sprinklers
12 m

1.2∗√ designarea∈ft 1.2∗√1076.39


No of sprinklers per branch= =
distance of sprinkler∈ft 12 ft
No of sprinklers per branch=3.28∨3
9 total sprinklers
=3 branches
3 sprinklers per branch

3. Audio Visual hall = Light hazard


Total area= 153m2
Design Area
No of sprinklers=
Area covered per sprinkler
Table 14.28.2.1 ESFR sprinkler
Spacing each sprinkler= 3.7m
Protection area= 9m2
153 m2
No of sprinklers= =17 sprinklers∨use 16
9 m2
1.2∗√ designarea∈ft 1.2∗√ 1646.88
No of sprinklers per branch= =
distance of sprinkler∈ ft 12 ft
No of sprinklers per branch=4 .05∨5
16 total sprinklers
=3.2∨3 branches
5 sprinklers per branch