MGT Science Transportation Prblem

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 2

BUILDING BRICK COMPANY (BBC)

North-West Corner Rule Method

D1 D2 D3 D4
8 6 12 9
S1 325 75
7 11 10 14
S2 350 150
13 8 8 7
S3 325 275

325 425 475 275

Total Cost ₱ 12,925.00

Least Cost Method (Minimum Cost or Greedy Method)

D1 D2 D3 D4
8 6 12 9
S1 400
7 11 10 14
S2 325 25 150
13 8 8 7
S3 325 275
325 425 475 275

Total Cost ₱ 10,975.00

Vogel's Approximation Method (VAM)

D1 D2 D3 D4
8 6 12 9
S1 400
7 11 10 14
S2 325 175
13 8 8 7
S3 25 300 275
325 425 475 275

Row 1 2 2 2
Difference - 2 2 2
- - 2 2

Total Cost ₱ 10,950.00


400

500

600

400

500

600

Column Difference

400 2 3 -

500 3 1 4

600 1 1 1