MANAGEMENT
Chapter Four
McGraw-Hill/Irwin Copyright © 2014 by The McGraw-Hill Companies, Inc. All rights reserved.
Learning Objectives
LO4–1: Explain what projects are and how projects
are organized.
LO4–2: Analyze projects using network-planning
models.
LO4–3: Evaluate projects using earned value
management.
LO4–4: Exemplify how these techniques are
implemented in commercial software packages.
4-2
Project Management
What is a project?
A series of related jobs, usually directed toward some
major output and requiring a significant period of time
to perform.
4-3
Project Management
What is project management?
Planning, directing (chỉ đạo), and controlling
resources (people, equipment, material, etc.) to meet
the technical, cost, and time constraints of the project.
4-4
Project Management
Why is project management important?
At the highest levels of an organization, management
often involves juggling a portfolio of projects.
Big projects
Panama Canal: The Biggest Megaproject in History
https://www.youtube.com/watch?v=K_XIX8d_om8&ab
_channel=TopLuxury
4-5
Types of Development Projects
Degree of Change
Type
of
Projec
t
4-6
Project Structure (Tổ chức ban dự án)
• Responsibility for the project lies within one functional area of the firm.
Employees from that area work on the project, usually only part-time.
• A blend (kết hợp) of pure and functional project structures – people from
different functional areas work on the project, possibly only part-time.
4-7
Pure Project Structure
• Duplication of resources
• Organizational goals and policies are ignored,
as team members are often both physically and
psychologically removed from headquarters.
Disadvantages • Lack of technology transfer
• Because team members have no functional area
home, they worry about life-after-project, and
project termination is delayed.
4-8
Functional Project Structure
4-9
Matrix Project Structure
• Better communications between functional areas
• Project manager held responsible for success
Advantages • Duplication of resources is minimized
• Functional “home” for team members
• Policies of the parent organization are followed
4-10
Example
VietinBank khởi động Dự án Triển khai thí
điểm cải tiến chất lượng dịch vụ theo phương
pháp Lean Six Sigma
https://www.vietinbank.vn/vn/tin-tuc/VietinBank-
khoi-dong-Du-an-Trien-khai-thi-diem-cai-tien-chat-
luong-dich-vu-theo-phuong-phap-Lean-Six-Sigma-
20200928185341.html
4-11
Example
Trường Đại học Kinh tế TP. Hồ Chí Minh được
kiểm định và công nhận theo chuẩn quốc tế
FIBAA
https://www.ueh.edu.vn/kiem-dinh-va-xep-
hang/kiem-dinh/04-chuong-trinh-dao-tao-cua-ueh-
dat-chuan-fibaa/
4-12
Example
Petrovietnam khởi động dự án triển khai hệ thống
ERP giai đoạn 1
https://petrovietnam.petrotimes.vn/petrovietnam-
khoi-dong-du-an-trien-khai-he-thong-erp-giai-
doan-1-613636.html
4-13
Defining the Project
Statement of Work (Bảng báo cáo công việc)
A written description of the objectives to be achieved
Task (Nhiệm vụ)
A further subdivision of a project – usually shorter than
several months and performed by a single group or
organization
Work Package (Gói công việc)
A group of activities combined to be assignable to a
single organizational unit
4-14
Defining the Project (continued)
Project Milestone (các mốc dự án)
Specific events in the life of the project
Work Breakdown Structure (Bảng cấu trúc công việc)
Definesthe hierarchy of project tasks, subtasks, and
work packages
Activities
Pieces of work that consume time
4-15
Work Breakdown Structure Example
Overview
Details
4-16
Work Breakdown Structure – Large
Optical Scanner Design
Overview
Details
4-17
Network-Planning Models (Mô hình lập kế
hoạch mạng)
4-18
The two best-known network-planning models were developed
in the 1950s.
The Critical Path Method (CPM) was developed for scheduling
maintenance shutdowns at chemical processing plants owned
by DuPont.
The Program Evaluation and Review Technique (PERT) was
developed for the U.S. Navy’s Polaris missile project. This was
a massive project involving over 3,000 contractors.
As years passed, features that distinguished CPM from PERT
have diminished, so in our treatment here we just use the term
CPM.
4-19
What is the Critical Path Method (CPM)?
https://www.youtube.com/watch?v=rxGcV0tuxRU
4-20
Critical Path Method (CPM)
Identify each activity to be done
and estimate how long it will take.
4-21
Example 4.1 – Identify Activities and
Construct Network
C(7) F(8)
A(21) G(2)
4-22
Determine Early Start/Early Finish and Late
Start/Late Finish Schedule
Critical 21 28 28 36
Path 1:
ACFG C(7) F(8)
21 28 28 36
0 21 36 38
A(21) G(2)
0 21 36 38
21 26 26 28 28 33
4-23
CPM with Activity Time Estimates
When activity times vary, a single time estimate may
not be reliable.
Instead, estimate three values
◼ Minimum
◼ Maximum
◼ Most likely
4-24
PERT Method Calculations
Excel: PERT
Calculations
4-25
Example 4.2 - Three Time Estimates
4-26
Example 4.2 - Network with Time
Estimates
21 28 28 36
C(7) F(8)
21 28 28 36
0 21 36 38
A(21) G(2)
0 21 36 38
21 26 26 28 28 33
21 26 26 28 31 36
4-27
Example 4.2 – Three Time Estimates
Probability of finishing in 35 weeks (or less)
4-28
Example 4.2 – Three Time Estimates
Probability of finishing in 35 weeks (or less) is about
19%
4-29
Time-Cost Models and Project Crashing
4-30
Project Crashing
4-31
Example 4.3 – Project Crashing
Excel: Project
Crashing
4-32
Example 4.3 – Project Crashing
Activity D cannot be
reduced any further at
this point
Activity A cannot be
reduced any further at
this point
4-33
Managing Resources
In addition to scheduling tasks, resources must also
be assigned to specific tasks.
Software can be used to spot over-allocation.
Planned use exceeds available supply
When resources are over-allocated, either more
resources are required or rescheduling is necessary.
Taking advantage of task slack can free resources
4-34
Project Control Charts
Charts provide an easily
understood visual
presentation.
Software can be used to
create the charts.
Gantt charts show, in a
graphic manner, the
amount of time involved
and the sequence of
activities. Often
referred to as a bar
chart.
4-35
Project Report Samples
4-36
Earned Value Management (EVM)
A technique for measuring project progress in an
objective manner
Has the ability to combine measurements of scope,
schedule, and cost in a project
Provides a method for evaluating the relative
success of a project at a point in time
4-37
Earned Value Management – Essential
Features
4-38
Earned Value Management Charts
Budgeted costs (scheduled) and actual costs Costs of scheduled and performed work
4-39
Project Tracking without EVM
A simple comparison of just costs versus budget
does not tell the whole story.
4-40
Project Tracking with EVM
With predefined methods of quantifying the
quantity of work accomplished, EVM provides much
more information.
EVM provides After week 6, the
information project has fallen
about behind schedule.
performance
according to Project is ahead of
the schedule. schedule in weeks
1 – 5.
4-41
Project Tracking with EVM
With predefined methods of quantifying the
quantity of work accomplished, EVM provides much
more information.
Project is under
budget in terms of
actual work
performed
4-42
Project Tracking with EVM
A combined view gives an overview of project
performance in terms of the original plan.
4-43
Example 4.4 – Earned Value
Management
At time “X”, Activity A is 100%
complete (budgeted cost was
$18K).
4-45
Example 4.4 – Budgeted Cost of Work
Performed (BCWP)
Activity A – 100% of $18K = $18K
Activity B – 80% of $10K = $8K
Activity C – 70% of $20K = $14K
Activity D – 0% of $40K = $0K
BCWP = $18K + $8K + $14K + $0K = $40K
4-46
Example 4.4 – Performance Measures
Actual cost of
$45K obtained
from accounting
records
For performance indices:
PI < 1 means costs are higher than planned
PI = 1 means costs are exactly as planned
PI > 1 means costs are lower than planned 4-47
Project Management: Information
Systems
Check out the website of the Project Management Institute
(www.pmi.org).
Two of the leading companies are Microsoft, with Microsoft
Project, and Primavera, with Primavera Project Planner.
The Microsoft Project program comes with an excellent online
tutorial, which is one reason for its overwhelming popularity
with project managers tracking midsized projects.
For managing very large projects or programs having several
projects, Primavera Project Planner is often the choice.
Primavera was the first major vendor of this type of software
and has possibly the most sophisticated capability.
4-48
Other Capabilities of the Software
In addition to scheduling tasks, a major capability of all
these software packages is assigning resources to
competing tasks and projects.
For example, the systems can schedule back labor and
equipment for a project.
Mid- to high-level project management information
systems (PMIS) software can also resolve over-
allocations through a “leveling” feature. Several rules
of thumb can be used such as:
You can specify that low-priority tasks should be delayed
until higher-priority ones are complete
Or that the project should end before or after the original
deadline, etc.
4-49