Professional Documents
Culture Documents
Syndicate 4 - AMI Project
Syndicate 4 - AMI Project
PROJECT AT AMI
SYNDICATE 4
• Hasia Ahmadi – 29321366
• Hazred Umar Fathan – 29321616
• Hertalina Anastassia Hasibuan – 29321321
• Idho Ferditya Rakhman – 29321411
• Imam Baehaqi – 29321409
• Irfan Naufaldi - 29321380
Case Background
1. Nikhil, Head of Electricity Department at Contact Infrastructure had a very complex project.
Hence, he asked Suresh to prepare a detailed project plan for carrying out the electrical
supply work.
2. Project : A2Z Management Institute (AMI)
3. Due date project : last year
4. New deadline : October 2018
5. There are several task that need to be scheduled:
• Initial Phase
§ Area measurement
§ Classification of the site based on its application
• Middle Phase
§ Installation of main and block substation
§ Setting-up LT distribution
• Final Phase
§ Laying cable for distribution power
§ Installing connection and electrical appliances
Schematic
Academic
Block
Hostel
Faculty
Residences
Calculate the total duration to complete
all activities!
Total duration :
375 days !
1. Laying of the distribution
power cable is included
with the procurement.
2. Activities that can be
done in parallel:
purchasing material and
laying of distribution
power cable from LT
Panel.
How long can the non-critical activities
be delay in the total duration?
Non-critical activities days
allowance :
1
1. Area measurement: 70
days
2. Civil work (substation): 30
days
2 3. Procurement material for
LT panel: 100 days
4. Laying cable:
3
a. Academic block: 70
days
b. Hostel : 10 days
4 c. Residence: 100 days
Which activity shall be the focus if
schedule crashing is needed?
What is crashing ?
Technique used to shorten the schedule duration for the lowest incremental cost by adding resources.
[The PMBOK Guide, 6th edition]
14
FINAL PHASE = 375 – 125 = 250
280 - 375
125 - 305
13
195 - 375
125 - 245
0 - 20
70 - 90 3 9 15
0 - 90 160 - 195 225 - 255 315 - 375
255 - 275 275 - 315
2 90 - 150 150 - 170
0 - 90
10 11
4 5
255 - 275 275 - 315
90 - 150 190 - 210
150 - 180
210 - 255
6
8
180 - 210
210 - 255
150 - 210
7
150 - 210