Professional Documents
Culture Documents
Material Chapter 4 Inventory Management PDF
Material Chapter 4 Inventory Management PDF
4.1 Introduction
Inventory: Stock of goods, which must be carried and
stored in order to ensure smooth and efficient running of
affairs of production and business.
Inventories are materials and supplies that a business or
institution carries either for sale or to provide inputs or
supplies to the production process
Inventory management is responsible for planning and
controlling inventory from the raw material stage to the
customer.
Cont..
Inventory one of the most expensive assets of many companies representing as
much as 50% of total invested capital
On one hand a firm can reduce cost by reducing inventory, on the other hand,
production may stop and customers become dissatisfied when an item is out of
stock.
Operations managers must balance inventory investment and customer service
Thus, objective of inventory management is to strike a balance between inventory
investment and customer service
A firm wishing to maximize profit will have at least the following objectives:
• Maximum customer service.
• Low-cost plant operation.
• Minimum inventory investment
4.2. Functions and types of inventory
Functions of Inventory
95% 5%
Input Wait for Wait to Move Wait in queue Setup Run Output
inspection be moved time for operator time time
Elements of inventory management system
72%
#11526 500 154.00 77,000 33.2% A
A Items
80 –
Percent of annual dollar usage
70 –
60 –
50 –
40 –
30 –
20 – B Items
10 – C Items
0 – | | | | | | | | | |
10 20 30 40 50 60 70 80 90 100
Percent of inventory items
Cont…
Other criteria than annual dollar volume may be
used
Anticipated engineering changes
Delivery problems
Quality problems
High unit cost
Cont…
Important Assumptions
1. Demand is known, constant, and independent
2. Lead time is known and constant
3. Receipt of inventory is instantaneous and complete
4. Quantity discounts are not possible
5. Only variable costs are setup and holding
6. Stockouts can be completely avoided
Inventory Usage Over Time, based on the above
assumption
Q
level)
2
Minimum
inventory
0
Time
Objective of EOQ is to minimize total costs
Relevant costs The relevant costs are as follows:
■ Annual cost of placing orders.
■ Annual cost of carrying inventory.
minimum total costs
Total cost of
holding and setup
(order)
Annual cost
Holding cost
Order quantity
Case
Cont….
EOQ Determination: Trial and error
The following table shows the cost for different
orders quantities
The following figure represents the above table
The above table and figure show the
following important facts
EOQ Determination: Formula
The previous example shows EOQ occurs at an order quantity when
ordering cost equals carrying cost. Based on that the following formula is
derived:
Using the formula, calculate the EOQ for the
following case
Solution
Reorder point (ROP)
Answer the question when should an order be placed?
EOQ answers the “how much” question
The reorder point (ROP) tells “when” to
order
Demand Lead time for a new
ROP = per day order in days
=dxL
D
d= Number of working days in a year
Cont….
Q*
Resupply takes place as order arrives
Inventory level (units)
Slope = units/day = d
ROP
(units)
Time (days)
Example:
Demand = 8,000 units per year
250 working day year
Lead time for orders is 3 working days
D
d=
Number of working days in a year
= 8,000/250 = 32 units
ROP = d x L
12 - 1
chapter 4
Production Order Quantity
Model
Part of inventory cycle during
which production (and usage)
is taking place
Inventory level
t Time
chapter 4 12 - 2
Production Order Quantity
Model
Q = Number of pieces per order p = Daily production rate
H = Holding cost per unit per year d = Daily demand/usage rate
t = Length of the production run in days
Annual inventory
= (Maximum inventory level)/2
level
= pt – dt
chapter 4 12 - 3
Production Order Quantity
Model
Q = Number of pieces per order p = Daily production rate
H = Holding cost per unit per year d = Daily demand/usage rate
t = Length of the production run in days
Maximum Q Q d
inventory level = p –d =Q 1–
p p p
2
2DS
Q =
H[1 - (d/p)]
2DS
Q*p =
H[1 - (d/p)]
chapter 4 12 - 5
In addition, setup cost is $10 per setup and holding cost
is $0.50 per unit per year
chapter 4 12 - 6
Production Order Quantity
Example
D = 1,000 units p = 8 units per day
S = $10 d = 4 units per day
H = $0.50 per unit per year
2DS
Q* =
H[1 - (d/p)]
2(1,000)(10)
Q* = = 80,000
0.50[1 - (4/8)]
2DS
Q* =
annual demand rate
H 1–
annual production rate
chapter 4 12 - 8
4.7. Materials requirement
planning
Material requirements planning (MRP) is
the system used to avoid missing parts. It
establishes a schedule (priority plan)
showing the components required at each
level of the assembly and, based on lead
times, calculates the time when these
components will be needed.
chapter 4 12 - 9
Objectives of MRP
Material requirements planning has two major objectives: determine
requirements and keep priorities current.
Determine requirements
. It must determine the following:
What to order.
How much to order.
When to order.
When to schedule delivery.
Keep priorities current The demand for, and supply of, components
changes daily. Customers enter or change orders. Components get
used up, suppliers are late with delivery, scrap occurs, orders are
completed, and machines break down. In this ever-changing world, a
material requirements plan must be able to reorganize priorities to keep
plans current. It must be able to add and delete, expedite, delay, and
change orders.
chapter 4 12 - 10
MRP’s Linkages to Other Manufacturing Planning and Control
Functions: Production planning and control
system
chapter 4 12 - 11
Input to material requirement
planning system
chapter 4 12 - 12
Master production schedule. The master production
schedule is a statement of which end items are to be
produced, the quantity of each, and the dates they are to be
completed. It drives the MRP system by providing the initial
input for the items needed.
Inventory records. two kinds of information needed. The
first is called planning factors and includes information
such as order quantities, lead times, safety stock, and
scrap. This information does not change often; however, it is
needed to plan what quantities to order and when to order
for timely deliveries.
The second kind of information necessary is the status of
each item: how much is available, how much is allocated,
and how much is available for future demand..
chapter 4 12 - 13
Bills of Material: a listing of all the
subassemblies, intermediates, parts, and raw
materials that go into making the parent
assembly showing the quantities of each required
to make an assembly – The following shows an
example of bill of materials
chapter 4 12 - 14
Bill of material structure:
format of presenting bill of materials
product tree:
chapter 4 12 - 15
Multilevel bill and single level bill: Compare the
following with the previous single level
chapter 4 12 - 16
A multiple bill is used when companies usually make
more than one product, and the same components are
often used in several products. See the following two
figure
chapter 4 12 - 17
chapter 4 12 - 18
Answer
chapter 4 12 - 19
Answer cont…
chapter 4 12 - 20
M A T E R IA L R E Q U IR E M E N T S P L A N N IN G
PROCESS
The purpose of material requirements planning is to determine the
components needed, quantities, and due dates so items in the
master production schedule are made on time.
The basic MRP techniques to achieve the objective:
Exploding and offsetting
Gross and net requirements
Releasing orders
Capacity requirements planning
Low-level coding and netting
Multiple bills of material
chapter 12 - 21
Exploding and Offsetting. Consider the following product tree.
It includes lead time
Lead time is the span of time needed to perform a process. In
manufacturing it includes time for order preparation, queuing,
processing, moving, receiving and inspecting, and any expected
delays.
chapter 4 12 - 22
From the product tree shown above, if B
and C are available, it will take 1 week to
assemble A. Thus, the lead time for A is 1
week. Similarly, if D and E are available,
the time required to manufacture B is 2
weeks. The purchase lead times for D, E,
and C are all I week.
In this particular product tree, the usage
quantities—the quantity of components needed
to make one of a parent—are all one. To make
an A requires one B and one C, and to make a
B requires one D and one E.
chapter 4 12 - 23
Exploding the requirements. Exploding
is the process of multiplying the
requirements by the usage quantity and
recording the appropriate requirements
throughout the product tree.
Offsetting. Offsetting is the process of placing
the exploded requirements in their proper
periods based on lead time. For example, if 50
units of A are required in week 5 (planned order
receipt), the order to assemble the As must be
released(planned order Release) in week 4,
and 50 Bs and 50 Cs must be available in week
4. SEE the following table
chapter 4 12 - 24
Exploding and Offsetting. The following table shows
time phased inventory record.
chapter 4 12 - 25
Example
Using the product tree and lead times shown
blow, complete the following table to determine
the planned order receipts and releases. There
are 50 As required in week 5 and 100 in week
6. Complete the table that follows:
chapter 4 12 - 26
chapter 4 12 - 27
answer
chapter 4 12 - 28
Gross and Net Requirements
When inventory of items exist at
beginning must be included when
calculating quantities to be produced.
Example Problem
Complete the following table. Lead time for the part is 2
weeks. The order quantity (lot size) is 100 units.
chapter 4 12 - 29
Cont..
chapter 4 12 - 30
Answer
chapter 4 12 - 31
Example 2: Consider how the following table
changes with availability of inventory.
chapter 4 12 - 32
Note the above table is based on the
following product structure
chapter 4 12 - 33
Suppose there are 10 Bs and 20 As inventory, see
how it change the plan as follows:
chapter 4 12 - 34
Scheduled receipts are orders placed on
manufacturing or on a vendor and
represent a commitment to make or buy.
The scheduled receipts row shows the
quantities ordered and when they are
expected to be completed and available.
They are generally expected to be due at
the start of the period for which they are
scheduled.
chapter 4 12 - 35
Example problem: Complete the following
table Lead time for the item is 2 weeks and
the order quantity is 200.
chapter 4 12 - 36
Answer:
chapter 4 12 - 37
Quantity Discount Models
Reduced prices are often available when
larger quantities are purchased
Trade-off is between reduced product cost
and increased holding cost
D Q
TC = S+ H + PD
Q 2
chapter 4 12 - 38
Quantity Discount Models
A typical quantity discount schedule
Discount Discount
Number Discount Quantity Discount (%) Price (P)
1 0 to 999 no discount $5.00
2 1,000 to 1,999 4 $4.80
Table 12.2
chapter 4 12 - 39
Quantity Discount Models
Steps in analyzing a quantity discount
1. For each discount, calculate Q*
2. If Q* for a discount doesn’t qualify,
choose the smallest possible order size
to get the discount
3. Compute the total cost for each Q* or
adjusted value from Step 2
4. Select the Q* that gives the lowest total
cost
chapter 4 12 - 40
Quantity Discount Models
Total cost curve for discount 2
Total cost
curve for
discount 1
Total cost $
0 1,000 2,000
Figure 12.7
Order quantity
chapter 4 12 - 41
Quantity Discount Example
Calculate Q* for every discount 2DS
Q* =
IP
2(5,000)(49)
Q1* = = 700 cars/order
(.2)(5.00)
2(5,000)(49)
Q2* = = 714 cars/order
(.2)(4.80)
2(5,000)(49)
Q3* = = 718 cars/order
(.2)(4.75)
chapter 4 12 - 42
Quantity Discount Example
Calculate Q* for every discount 2DS
Q* =
IP
2(5,000)(49)
Q1* = = 700 cars/order
(.2)(5.00)
2(5,000)(49)
Q2* = = 714 cars/order
(.2)(4.80) 1,000 — adjusted
2(5,000)(49)
Q3* = = 718 cars/order
(.2)(4.75) 2,000 — adjusted
chapter 4 12 - 43
Quantity Discount Example
Annual Annual Annual
Discount Unit Order Product Ordering Holding
Number Price Quantity Cost Cost Cost Total
1 $5.00 700 $25,000 $350 $350 $25,700
Table 12.3
Choose the price and quantity that gives
the lowest total cost
Buy 1,000 units at $4.80 per unit
chapter 4 12 - 44
Probabilistic Models and
Safety Stock
Used when demand is not constant
or certain
Use safety stock to achieve a desired
service level and avoid stockouts
ROP = d x L + ss
chapter 4 12 - 45
Safety Stock Example
ROP = 50 units Stockout cost = $40 per frame
Orders per year = 6 Carrying cost = $5 per frame per year
ROP
Normal distribution probability of
demand during lead time
Expected demand during lead time (350 kits)
0 Lead
time Time
Figure 12.8 Place Receive
order order
chapter 4 12 - 48
Probabilistic Demand
Use prescribed service levels to set safety
stock when the cost of stockouts cannot be
determined
chapter 4 12 - 49
Probabilistic Demand
chapter 4 12 - 52
Other Probabilistic Models
Demand is variable and lead time is constant
chapter 4 12 - 53
Probabilistic Example
Average daily demand (normally distributed) = 15
Standard deviation = 5
Lead time is constant at 2 days Z for 90% = 1.28
90% service level desired From Appendix I
chapter 4 12 - 54
Other Probabilistic Models
Lead time is variable and demand is constant
chapter 4 12 - 55
Probabilistic Example
Z for 98% = 2.055
Daily demand (constant) = 10 From Appendix I
Average lead time = 6 days
Standard deviation of lead time = sLT = 3
98% service level desired
chapter 4 12 - 56
Other Probabilistic Models
Both demand and lead time are variable
chapter 4 12 - 57
Probabilistic Example
Average daily demand (normally distributed) = 150
Standard deviation = sd = 16
Average lead time 5 days (normally distributed)
Standard deviation = sLT = 1 day
95% service level desired Z for 95% = 1.65
From Appendix I
chapter 4 12 - 58
Single Period Model
Only one order is placed for a product
Units have little or no value at the end of
the sales period
Cs
Service level =
Cs + Co
chapter 4 12 - 59
Single Period Example
Average demand = = 120 papers/day
Standard deviation = = 15 papers
Cs = cost of shortage = $1.25 - $.70 = $.55
Co = cost of overage = $.70 - $.30 = $.40
Cs
Service level =
Cs + Co
Service
.55 level
= 57.8%
.55 + .40
.55
= = .578 = 120
.95
Optimal stocking level
chapter 4 12 - 60
Single Period Example
chapter 4 12 - 61
Fixed-Period (P) Systems
Orders placed at the end of a fixed period
Inventory counted only at end of period
Order brings inventory up to target level
chapter 4 12 - 62
Fixed-Period (P) Systems
Target quantity (T)
Q4
Q2
On-hand inventory
Q1 P
Q3
chapter 4 12 - 64
Fixed-Period Systems
chapter 4 12 - 65
All rights reserved. No part of this publication may be reproduced, stored in a retrieval
system, or transmitted, in any form or by any means, electronic, mechanical, photocopying,
recording, or otherwise, without the prior written permission of the publisher.
Printed in the United States of America.
chapter 4 12 - 66