Professional Documents
Culture Documents
Unit 1 Notes
Unit 1 Notes
Estimation
Types of Estimates:
1. Detailed Estimate:
4. Revised Estimate:
If due to changes in price level data or any
other cause the sanctioned estimate exceeds by
more than 5 %, then alternate estimate is prepared
known as the Revised Estimate.
A comparative statement with details about the
variation related to quantitis, item, rates should be
included with reaseons for the variations.
5. A Supplimentary Estimate:
Estimate prepared for the new/ additional
supplimentary work which was not considered while
framing the first estimate.
The abstract of this new update with previous
estimate should be included along with the total
sanctioned required.
6. A Complete Estimate:
A complete estimate of direct or in-direct cost
related to the project. There are many other expen-
-ses required to complete the project not included
in the detailed estimate.
1. Earthwork:
- The earthwork in excavation and filling is
taken as separate items.
- The unit for measurement of earthwork is
cubic meter (volumne)
- For foundation of building earthwork in
excavation is taken as size of the trench (L*B*H),
while for the filling it is usually neglected.
- Earthwork filling in plinth in considered by
taking inside dimensions.
2. Concrete in Foundation:
- The amount of concrete in foundation is
taken in cubic meter.
3. Soling:
- For soft soil, one layer of broken dry bricks
or stone is added at base of foundation. Its measur-
-ed in term of square meter (L*B).
5. Masonary:
- Masonary is computed in terms of cu. m.
- Both plinth and foundation masonary is taken
as one unit.
- In multi storeyed building. for each floor maso-
-nary is taken as separate unit.
- Deduction for openings, bearings are to taken
into consideration while obtaining quantities.
8. Cornice:
- Large and ornamental cornice is measure in
running meter (or running ft.) including masonary,
plastering, finishing.
9. Pillars:
- Pillars are taken separately for their geometeric
volumn. The plastering of these pillars is measured
in sq.m.
11. Painting:
- The measurement is same as that of the plast-
-ering with proper deductions, measured in the sqm
(or sq.ft. ie 1 brass=100 sq.ft.).
1. Buidling construction
-Site clearance.
-Excavation for foundations.
-P. C. C. in foundations.
-Masonry in foundations.
-C. R. masonary in plinth.
-Damp proof course at plinth level.
-Plinth filling with hard murum.
-Brick Work (or stone masonary) in Superstructure.
-Providing and fixing door and window frames.
-Lintels over openings.
-Flat R.C.C. or sloping roof.
-External and internal plastering and pointing.
-Providing and laying flooring.
-Door and Window shutters.
-Water supply and sanitary arrangement.
-Electrification.
Enlisting the items of work for different Civil
Engineering projects.
2. Road/Highway Construction
-Surveying
-Clearing and Piling
-Earthwork
-Finish Grading
-Surfacing
-Drainage
Assignment
deduct=l*h*thickness of
wall
deduct=l*h*thickness of wall
1. Doors and Windows
L
d. Semi-circular arch:
L
e. Arch Masonary work:
deduct= Lm*t*wall thickness
1. Doors and Windows
1. Face Sheet
Typical Facesheet
Components of Estimate
Rate Analysis:
Lead statement
Provisional Sum
Contingencies: