Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Case Study Exercise - Part 1

Instructions: Work out the critical path and the total float for each activity before moving on to part 2

Key

ES – Earliest start time


ES D EF
EF – Earliest finish time
LS – Latest start time
ID
LF – Latest Finish time
D – Duration
LS TF LF
TF – Total float
Case Study Exercise - Part 2
Instructions: Using this fully analysed network draw a Gantt chart showing the critical path and the total floats before moving on to part 3

Key

ES – Earliest start time


ES D EF
EF – Earliest finish time
LS – Latest start time
ID
LF – Latest Finish time
D – Duration
LS TF LF
TF – Total float
- Critical path
Case Study Exercise - Part 3
Instructions: Using this Gantt chart and assuming each task uses one resource calculate the resources per day and draw a resource histogram then move
on to part 4

Gannt chart key

Critical path tasks


Non critical path tasks
Total float
Project start activity
Case Study Exercise - Part 4
Instructions: What happens if we limit the electrical resources installing sockets, lights and TV cables to 2 people, instead of 3?
Case Study Exercise - Part 5
Instructions: By limiting the resources to 2 one of the tasks must be moved to the right - probably "install TV cables". This will extend the project by 2
days.
If the two electrical resources were to work overtime then it may be possible to recover these two days and install the TV cables during weeks 1 to 8.

You might also like