The document provides instructions over 5 parts for a case study exercise involving analyzing a project network diagram, determining the critical path and total floats, drawing a Gantt chart, calculating resource usage, and exploring the impact of limiting resources. It directs the reader to complete each part before moving to the next, with the goal of optimizing the project schedule and resources.
The document provides instructions over 5 parts for a case study exercise involving analyzing a project network diagram, determining the critical path and total floats, drawing a Gantt chart, calculating resource usage, and exploring the impact of limiting resources. It directs the reader to complete each part before moving to the next, with the goal of optimizing the project schedule and resources.
The document provides instructions over 5 parts for a case study exercise involving analyzing a project network diagram, determining the critical path and total floats, drawing a Gantt chart, calculating resource usage, and exploring the impact of limiting resources. It directs the reader to complete each part before moving to the next, with the goal of optimizing the project schedule and resources.
Instructions: Work out the critical path and the total float for each activity before moving on to part 2
Key
ES – Earliest start time
ES D EF EF – Earliest finish time LS – Latest start time ID LF – Latest Finish time D – Duration LS TF LF TF – Total float Case Study Exercise - Part 2 Instructions: Using this fully analysed network draw a Gantt chart showing the critical path and the total floats before moving on to part 3
Key
ES – Earliest start time
ES D EF EF – Earliest finish time LS – Latest start time ID LF – Latest Finish time D – Duration LS TF LF TF – Total float - Critical path Case Study Exercise - Part 3 Instructions: Using this Gantt chart and assuming each task uses one resource calculate the resources per day and draw a resource histogram then move on to part 4
Gannt chart key
Critical path tasks
Non critical path tasks Total float Project start activity Case Study Exercise - Part 4 Instructions: What happens if we limit the electrical resources installing sockets, lights and TV cables to 2 people, instead of 3? Case Study Exercise - Part 5 Instructions: By limiting the resources to 2 one of the tasks must be moved to the right - probably "install TV cables". This will extend the project by 2 days. If the two electrical resources were to work overtime then it may be possible to recover these two days and install the TV cables during weeks 1 to 8.