TC Energy - Southeast Extention Project - Package 1

Id Task Name Duración Comienzo Fin Predecesoras Sucesoras Calendario de 2022 2023
tareas
Semestre 2, 2021 Semestre 1, 2022 Semestre 2, 2022 Semestre 1, 2023 Semestre 2, 2023
N D E F M A M J J A S O N D E F M A M J J A S O
1 On Shore Pipeline 21 Km - 36" 418 d mar 07/12/21 jue 10/08/23 Standard
2 CONTRACTUAL MILESTONES 147 d mié 11/01/23 jue 03/08/23 Standard
3 Package 1 - Tuxpan Pipe 147 d mié 11/01/23 jue 03/08/23 Standard
4 Construction Start 0d mié 11/01/23 mié 11/01/23 31CC Standard 11/01
5 Mechanical Completion On Shore 0d mar 13/06/23 mar 13/06/23 52 Standard 13/06
6 Mechanical Completion Landfall 0d jue 13/07/23 jue 13/07/23 87 7 Ninguno 13/07
7 Ready for Commissioning and Hot Tap 0d jue 13/07/23 jue 13/07/23 6 8FF+15 d Standard 13/07
8 Substantial Completion 0d jue 03/08/23 jue 03/08/23 7FF+15 d Standard 03/08
9 PROJECT MILESTONES 258 d mar 07/12/21 vie 16/12/22 Standard
10 EPC LNTP 0d mar 07/12/21 mar 07/12/21 11CC+75 d Standard 07/12
11 EPC FNTP 0d lun 04/04/22 lun 04/04/22 10CC+75 d 13CC+180 d,59 Standard 04/04
12 Package 1 - Tuxpan Pipe 3d lun 12/12/22 vie 16/12/22 Standard
13 Access to 100% Tuxpan Onshore Pipeline 0d lun 12/12/22 lun 12/12/22 11CC+180 d 17CC-5 d Standard 12/12
14 Contractor Welding Systems and Procedures Approved (30 days prior welding) 0d vie 16/12/22 vie 16/12/22 35CC-30 d Standard 16/12
15 PERMITS 0d mar 06/12/22 mar 06/12/22 Standard 06/12
16 Package 1 - Tuxpan Pipe 0d mar 06/12/22 mar 06/12/22 Standard 06/12
17 100% Permits & ROW for Tuxpan Onshore Pipeline (By Owner- According to 0d mar 06/12/22 mar 06/12/22 13CC-5 d 21FF+10 d,56 Standard 06/12
Permit Matrix)
18 ENGINEERING 260 d mié 01/06/22 mar 13/06/23 Standard
19 Package 1 - Tuxpan Pipe 260 d mié 01/06/22 mar 13/06/23 Standard
20 Scope Division #1 260 d mié 01/06/22 mar 13/06/23 Standard
21 100% Alignment Sheets - Onshore 1 - SDTT to SEE Tuxpan, Tuxpan to 150 d mié 01/06/22 mar 10/01/23 17FF+10 d 26FF+6 d,31 Standard
Landfall 1
22 As-Builts 60 d mié 22/03/23 mar 13/06/23 48FF+18 d Standard
23 PROCUREMENT 0d mié 18/01/23 mié 18/01/23 Standard 18/01
24 Package 1 - Tuxpan Pipe 0d mié 18/01/23 mié 18/01/23 Standard 18/01
25 Scope Division #1 0d mié 18/01/23 mié 18/01/23 Standard 18/01
26 100% Line Pipe by TC - Onshore 1 - SDTT to SEE Tuxpan, Tuxpan to Landfall 0d mié 18/01/23 mié 18/01/23 21FF+6 d Standard 18/01
1

27 CONSTRUCTION 343 d mar 05/04/22 jue 10/08/23 Standard


28 Package 1 - Tuxpan Pipe 110 d mié 11/01/23 mar 13/06/23 Standard
29 Scope Division #1 110 d mié 11/01/23 mar 13/06/23 Standard
30 Onshore 1 Segment - SDTT to SEE Tuxpan, Tuxpan to Landfall 1 (21 km NPS 36) 88 d mié 11/01/23 vie 12/05/23 Standard
31 Clearing y Rescate ambiental 42 d mié 11/01/23 jue 09/03/23 21 32CC+4 d,4CC Standard
32 ROW 42 d mar 17/01/23 mié 15/03/23 31CC+4 d 33CC+5 d,42,45CC+5Standard
d,47CC
33 Stringing 42 d mar 24/01/23 mié 22/03/23 32CC+5 d 34CC+3 d Standard
34 Bending 42 d vie 27/01/23 lun 27/03/23 33CC+3 d 35CC+10 d Standard
35 Welding 42 d vie 10/02/23 lun 10/04/23 34CC+10 d 36CC+5 d,43CC+10 d,14CC-30
Standard d
36 Field Joint Coating 42 d vie 17/02/23 lun 17/04/23 35CC+5 d 37CC+4 d Standard
37 Trenching & Bedding 42 d jue 23/02/23 vie 21/04/23 36CC+4 d 38CC+5 d Standard
38 Lowering 42 d jue 02/03/23 vie 28/04/23 37CC+5 d 39CC+4 d,41CC+4 d Standard
39 Tie-ins 42 d mié 08/03/23 jue 04/05/23 38CC+4 d 50FF+7 d,40 Standard
40 Tie-in with facility 6d vie 05/05/23 vie 12/05/23 39 Ninguno
41 Padding & Backfilling 42 d mié 08/03/23 jue 04/05/23 38CC+4 d Standard
42 Machine Clean Up/Restoration 42 d jue 16/03/23 vie 12/05/23 32 Standard
43 HDD Crossing 55 d vie 24/02/23 jue 11/05/23 35CC+10 d Standard
44 Onshore Facilities 88 d mar 17/01/23 vie 19/05/23 Standard

āTask Rolled Up Task Inactive Task Manual Summary Rollup Project Summary
Critical Task Rolled Up Critical Task Inactive Milestone Manual Summary Group By Summary
Data: vie 05/11/21 Progress Rolled Up Milestone Inactive Summary Start-only Deadline
Milestone Rolled Up Progress Manual Task Finish-only
Summary Split Duration-only External Tasks

Pagina 1 de 2
TC Energy - Southeast Extention Project - Package 1

Id Task Name Duración Comienzo Fin Predecesoras Sucesoras Calendario de 2022 2023
tareas
Semestre 2, 2021 Semestre 1, 2022 Semestre 2, 2022 Semestre 1, 2023 Semestre 2, 2023
N D E F M A M J J A S O N D E F M A M J J A S O
45 MLV 1 60 d mar 24/01/23 lun 17/04/23 32CC+5 d 46CC+10 d Standard
46 MLV 2 60 d mar 07/02/23 lun 01/05/23 45CC+10 d Standard
47 Launcher trap 82 d mar 17/01/23 mié 10/05/23 32CC Standard
48 Tie-in to POR at Montegrande EMRyC 5d vie 12/05/23 vie 19/05/23 51CF 22FF+18 d Standard
49 Precommissioning 46 d mar 11/04/23 mar 13/06/23 Standard
50 Hydrotest 25 d mar 11/04/23 lun 15/05/23 39FF+7 d 51FC+3 d Standard
51 Kaliper 10 d vie 19/05/23 jue 01/06/23 50FC+3 d 52FC+3 d,48CF Standard
52 Drying 5d mié 07/06/23 mar 13/06/23 51FC+3 d 5 Standard
53 Tuxpan Landfall 1 Km - 36" 343 d mar 05/04/22 jue 10/08/23 Standard
54 PERMITS 0d mar 06/12/22 mar 06/12/22 Standard 06/12
55 Tuxpan Landfall 0d mar 06/12/22 mar 06/12/22 Standard 06/12
56 100% Permits& ROW for Tuxpan Landfall (By Owner- According to Permit 0d mar 06/12/22 mar 06/12/22 17 Standard 06/12
Matrix)
57 ENGINEERING 160 d mar 05/04/22 lun 14/11/22 Standard
58 Tuxpan Landfall 160 d mar 05/04/22 lun 14/11/22 Standard
59 Civil Engineering (Access/Platform) 40 d mar 05/04/22 lun 30/05/22 11 60FC-5 d Standard
60 Tunnel Engineering/Pit 100 d mar 24/05/22 lun 10/10/22 59FC-5 d 61FC-15 d Standard
61 Costruction Planning/Procedure 40 d mar 20/09/22 lun 14/11/22 60FC-15 d 64 Standard
62 CONSTRUCTION 183 d mar 15/11/22 jue 10/08/23 Standard
63 Tuxpan Landfall 183 d mar 15/11/22 jue 10/08/23 Standard
64 Access Preparation 25 d mar 15/11/22 lun 19/12/22 61 65 Standard
65 Site Preparation (Platform and Temporary Area) 35 d mar 20/12/22 lun 20/02/23 64 66FC-5 d,67,75 Standard
66 Pipes Stringing String 1 (including umbelical) 4d mar 14/02/23 vie 17/02/23 65FC-5 d Standard
67 1st string welding (center line), NDT and Coating 5d mar 21/02/23 lun 27/02/23 65 68 Standard
68 Hydrotest String 1 3d mar 28/02/23 jue 02/03/23 67 69 Standard
69 Pipes Stringing String 2 (including umbelical) 4d vie 03/03/23 mié 08/03/23 68 70 Standard
70 2st string welding (external string) NDT and Coating 5d jue 09/03/23 mié 15/03/23 69 71 Standard
71 Hydrotest String 2 3d jue 16/03/23 lun 20/03/23 70 72 Standard
72 Pipes Stringing String 3 (including umbelical) 4d mar 21/03/23 vie 24/03/23 71 73 Standard
73 3st string welding (middlle string) NDT and Coating 5d lun 27/03/23 vie 31/03/23 72 74 Standard
74 Hydrotest String 3 3d lun 03/04/23 mié 05/04/23 73 Standard
75 Pit Preparation and Foundation 20 d mar 21/02/23 lun 20/03/23 65 76FF,77FF Standard
76 Direct Pipe Machine arrival at site 0d lun 20/03/23 lun 20/03/23 75FF Standard 20/03
77 Launch Seal Installation 3d jue 16/03/23 lun 20/03/23 75FF 78 Standard
78 Direct Pipe Machine assembly 4d mar 21/03/23 vie 24/03/23 77 79 Standard
79 Drilling 1 section 15 d lun 27/03/23 vie 14/04/23 78 80 Standard
80 Weld 1 and string 3 shift to the center line 3d lun 17/04/23 mié 19/04/23 79 81 Standard
81 Drilling 2 Section 20 d jue 20/04/23 mié 17/05/23 80 82 Standard
82 Weld 2 and string 2 shift to the center line 3d jue 18/05/23 lun 22/05/23 81 83 Standard
83 Drilling 3 Section 25 d mar 23/05/23 lun 26/06/23 82 84 Ninguno
84 Push out and Head Recovery 7d mar 27/06/23 mié 05/07/23 83 85,87 Standard
85 Umbelical Recovery 8d jue 06/07/23 lun 17/07/23 84 86 Standard
86 Direct Pipe Demob 0d lun 17/07/23 lun 17/07/23 85 Standard 17/07
87 Pipeline connection (last mile and tie-in) 6d jue 06/07/23 jue 13/07/23 84 88,6 Standard
88 Restoration 20 d vie 14/07/23 jue 10/08/23 87 Standard

āTask Rolled Up Task Inactive Task Manual Summary Rollup Project Summary
Critical Task Rolled Up Critical Task Inactive Milestone Manual Summary Group By Summary
Data: vie 05/11/21 Progress Rolled Up Milestone Inactive Summary Start-only Deadline
Milestone Rolled Up Progress Manual Task Finish-only
Summary Split Duration-only External Tasks

Pagina 2 de 2