NORTHERN COALFIELDS LIMITED, SINGRAULI (13/03/23) IR

SI No SIDING Rakes Required LOADING Remarks/Details


1 Dudhichua Silo 9 9
2 Dudhichua Wharfwall 6 6
3 Krishnashila Silo 3 3
Less coal. Rakes detained due to adjustment
4 Bina Silo 2 1
in Bina wharf

Indiscriminate overloading. Three rakes


5 Bina Wharfwall 4 2 backed into siding for adjustment from 13:00
to 20:15 hrs. Loading time lost.
6 Jhingurda 5 4
7 Spur-1 3 3
8 Spur-2 3 3
9 Block B (Gorbi) 2 3
10 Nigahi 2 2
11 Jayant 3rd Silo 4 4
TOTAL 43 40