Professional Documents
Culture Documents
TOPIC 4 Planning and Scheduling
TOPIC 4 Planning and Scheduling
TOPIC 4 Planning and Scheduling
Topic 4
Planning and Scheduling
Contents
The techniques of planning
and scheduling.
Gantt Chart
S-curve in construction
planning
1
Project schedule is the project plan
in an altered format.
❑ Small Project
– Gantt Chart or Bar Chart
2
Tool When to use Example
Simple sequential
Gantt Chart Logic with few parallel Road construction
activities
Complex sequential
Bridge construction
Logic with many parallel
Network Diagram Water supply system
activities
construction
3
▪ the most simple and easiest way to produce a scheduling form in the
construction industry.
▪ widely used due to its simplicity and multiple adaptations to numerous
events.
▪ A bar charts is formed with a list of activities, specifying the start date,
duration of the activity and completion date of each activity, and then
plotted into the project time scale. The detailed level of the bar chart
will depend on your project complexity and the intended use of the
schedule.
4
Type I
Reporting date
Reporting date
5
Type II
0 8 28 55 75 90 96
Reporting
(b) Type II Reporting: Case 2 date
6
• Early bar chart is drawn using the ES times of activities,
while the late bar chart is drawn using the LS times.
7
Advantages Disadvantages
8
❑ Developed in the 1950s by the US Navy
9
• Use of nodes and arrows
10
• There are two ways of displaying a project network
• Activities on arrows (AOA) network
• The activities are shown as arrows and events
as nodes
• Generally, more difficult to draw but depicts the
technical relationships of the activities well
• Activities on nodes (AON) network
• Each task is shown as a node and the
technological relationship is shown by the arrows
• AON network usually associated with CPM
• AOA network usually associated with PERT
11
12
13
14
15
Start to Start SS Start to Finish SF
Finish to
Finish to Start FS Finish FF
B
A
A must finish before either B or C
can start
C
A
C
both A and B must finish before C
B can start
A
C
both A and C must finish before
B either of B or D can start
D
A
B
A must finish before B can start
Dummy
both A and C must finish before D
can start
C
D
16
Activity
constraint
options in
precedence
networks
17
Clearly defined, independent and stable activities
• Completion date?
• On Schedule?
• Within Budget?
• Critical Activities?
• How can the project be finished early at the
least cost?
18
The CPM is a systematic
scheduling method for a project
network and involves four main
steps:
Forward Pass
▪ Earliest Start Time (ES)
▪ earliest time an activity can start
▪ ES = maximum EF of immediate predecessors
Backward Pass
Latest Start Time (LS)
Latest time an activity can start without delaying critical path time
(LS= LF – t)
Latest finish time (LF)
latest time an activity can be completed without delaying critical path
time
LS = minimum LS of immediate predecessors
19
• Draw the CPM network
• Analyze the paths through the network
• Determine the float for each activity
• Compute the activity’s float
• float = LS - ES = LF - EF
• Float is the maximum amount of time that this activity can be
delay in its completion before it becomes a critical activity, i.e.,
delays completion of the project
• Find the critical path is that the sequence of activities and events
where there is no “slack” i.e.. Zero slack
• Longest path through a network
• Find the project duration is minimum project completion time
20
• Draw the CPM network
• Analyze the paths through the network
• Determine the float for each activity
• Compute the activity’s float
• float = LS - ES = LF - EF
• Float is the maximum amount of time that this activity can be
delay in its completion before it becomes a critical activity, i.e.,
delays completion of the project
• Find the critical path is that the sequence of activities and events
where there is no “slack” i.e.. Zero slack
• Longest path through a network
• Find the project duration is minimum project completion time
• Duration and finance budget expenditure to carry every activity for project : Lift Irrigation in the
farm were as follows:
Activity Activity Event/ Duration Budget
(Week) Expenditure
Symbol Predecessor
(RM)
A Site selection 1-2 2 20,000
21
Network analysis diagram by using arrow activity
4
6 10
F
C 4
2
1 2 5 6
A D G
0 0 2 2 4 5 9 9 3 12 12
B E
6 3
3
6 6
A 1-2 2 0 2 2 4
F 4-6 2 6 8 10 12
G 5-6 3 9 12 9 12
22
Prepare bar chart based on network results of the analysis that achieved
23
https://www.youtube.com/watch?v=NDa-Fq5jeuM
24
EXAMPLE
PDM – Draw
Nodes and
Dependenci
es
PDM –
Durations
25
PDM -
Forward
Pass
PDM -
Backward
Pass
26
PDM -
Calculate
Float and its
type
Leads and
Lags
27
Task list for
the furniture
project
28
Furniture
project:
precedenc
e network
diagram
Time analysis
for the
furniture
project
29
Gantt chart
for the
furniture
project
TUTORIAL 1
30
ANSWER
TUTORIAL 2
• What is the duration of the critical path?
• Which activities have total float?
• Which activities have free float?
31
ANSWER
A display of cumulative costs, labour hours or other quantities plotted against time.
The name derives from the S-like shape of the curve, flatter at the beginning and
end and steeper in the middle, which is typical of most projects. The beginning
represents a slow, deliberate but accelerating start, while the end represents a
deceleration as the work runs out.
The name derives from the S-like shape of the curve, flatter
at the beginning and at end and steeper in the middle,
which is typical of most projects. The beginning represents
a slow, cautious but accelerating start, while the end
represents a deceleration as the work runs out.
32
• There are a variety of S-curves that are
applicable to project management
applications, including:
Prepare a baseline schedule (schedule with planned start and finish dates, used as reference to compare
with actual schedule) of your project with few activities, duration and planned start & finish dates.
Assign weightage to each activity and it could be man-hours, cost or other quantities which represent the
grade of that activity, among others.
The weightage allotment based on one of these criterions alone may not be so logical because the
activity with larger effort (man-hours) cost cheap or costly activity could complete with lesser effort. Still,
this is the fundamental way and is followed every time.
Those who think differently could correlate the three project management triangle attributes (cost,
schedule and scope) together in some logical way and allocate a better weightage value for each activity.
I have used a tentative formula to correlate and calculate the weightage for the mentioned activities.
Further these values were converted to fractions of 1000 (total value) to make next calculations
comprehensible.
33
34
35
Typical Project - Plan
Project
Budget
Final testing,
project winding down
Money
We’re on time
Money
Spent
We’re on budget
Life is good
(We’re probably lying)
0 Progress
36
Typical Project - Actual
Project
Budget
Spent
We’re on budget
Life is great!
Now we’re really lying!
0 Progress
Project
Budget
We’re on budget
We’re concerned
Are there liquated damages?
0 Progress
37
Typical Project - Actual
Project
Budget
Spent
We’re on time
Money
0 Progress
0 Progress
38
Typical Project - Actual
Project
Budget
Spent
0 Progress
Project
Budget
BAD
Money
GOOD
0
39
akmanida@puo.edu.my
40