ENTREPOSE ALGERIE
________________________________________________________________________________________
Project : MLN-MSA-1369-TSD-2015 Client : COPAL
Localization : MLNW6
Documentation :
General Tool box talks.
Specific Tool box talks in the work area.
Spark potential permit, isolation certificate,
Specific TRIC
Detailed drawings
Materials :
a) Basic PPE. k) Hiab truck
b) Continuous Gas detector (Spider). l) Compactor
c) Safety Harness. m) Loader
d) Barriers and barricade. n) Water truck
e) Lifting tools o) Welding machine
f) Side boom (Pipe layer) p) Gypsum truck
g) Temporary support q) Excavator
h) Car r) Compactor small model
i) Crane s) Concrete malaxor
j) Lowboy truck
Manpower :
a) HSE supervisor f) Crane operator
b) Team Leader g) Loader operator
c) QC supervisor h) Banks man
d) Rigger i) Drivers
e) Helpers
Method statement :
Before starting work:
Emergency procedures to be explained for all workers,
Prepare the fire extinguishers ,
Spider gas detector should be provided,
Prepare the necessary tools (straps, lifting material …),
All tools will be inspected and color coding applied (Yellow),
Hard barricade will be in place around the work area,
All vehicles, engines should have fire arrestors to avoid any ignition source or fire hazards,
011-EA- METHOD STATEMENT TO REPAIR CONCRETE PIPE SUPPORT
ENTREPOSE ALGERIE
________________________________________________________________________________________
Tasks Sequences
1. Collect the relevant permits to work from control room/ liaise with MLN Production/shutdown team after getting
the go ahead from production,
2. Toolbox talks for job hazards / risks and emergency procedures to be carried out prior to task commencement,
3. Walk the job with performing supervisor to identify hazardous operations and ensure control measures as
specified in a TRIC are in place,
4. Confirm that the line has been drained/depressurized or isolated by MLN operator and hi will sign the worksite
isolation checklist,
5. Lift carefully and shift the existing pipe using a side boom and put the temporary support.
6. When the pipe was lifted as required and supported we move to the next step which is removing the existing
concrete pipe supports using side boom.
7. Levelling sand under pipe support locations using manual shovels.
8. Apply gypsum watered and compacted for a total depth of 30 cm for each position
9. Pouring lean concrete
10. After one day we put the new support on correct position
11. Move the existing pipe and put it back in its right position
12. When finishing this operation we proceed to remove the temporary supports
13. Carry out housekeeping checks and clear the area.
Name: BELABBACI Ahmed Name: SADI Naim/KORTI Hassane Name : DJEDOUANI Mouldi
Signature: Signature: