INSPECTION AND TEST PLAN (I&TP) FOR OPTICAL FIBER MANAGEMENT RACK (OFMR)

Type Factory Acceptance Test

Manufacturer Name: Contract No. / Project Title:


Plant Location: I&TP No. : ITP-FOIC-05
Equipment/Material Description: FO Interconnecting Devices and Passive Review Cycle No :
Componnets Date:
Type of Equipment / Material OFMR

Applicable Test Insp. Acceptance Criteria Tests Tentative Remarks Mfr’s


Item Tests Description Sample
Standard Procedures Type Location Dates Compliance

Color / surface finish shall be as


1 Visual Inspection 48-TMSS-12, W per 48-TMSS-12, Rev.0 and there
20%
Rev.0 shall be no scratches or dents.

48-TMSS-12, Dimensions shall be H(2200) x


2 DimensionVerification 20% W
Rev.0 W(900) x D (450) mm

Check for Latch/lock, earth point,


Checking for availability 48-TMSS-12, 20% W
3 cable entry ports, PDU as per data
of components. Rev.0
schedule.

Legend:
W = Witness [by National Grid SA Engineers and/or National Grid SA approved 3rd Party Independent Inspection Agency (IIA) Inspector]
RC = Review of Certificates [by National Grid SA Engineers and/or National Grid SA approved 3rd Party Independent Inspection Agency (IIA) Inspector]

ITP-FOIC-05 Standards & Specifications Department PAGE 1 OF 2

License=Al Sharif Group & KEC Co. Ltd/SA-881-t Not For Resale ,1/23/2023 8:15:15 PM Saudi Time
INSPECTION AND TEST PLAN (I&TP) FOR OPTICAL FIBER MANAGEMENT RACK (OFMR)

General instructions:
1- Manufacturer’s compliance shall be indicated in front of each test.
2- Approved Data Schedule & final drawings for the equipment / Material shall be attached.
3- Test Procedure & Day-to-day activity schedule shall be attached for approval.
4- The ITP must be duly signed and stamped by manufacturer's authorized personnel.
5- This document is valid for testing after S&SD approval.

Prepared by (Mfr's authorized QC test inspector) Approved by: (Mfr's authorized QA/QC personnel)

Date:

Date:
Manufacturer Stamp

S&SD Approval

ITP-FOIC-05 Standards & Specifications Department PAGE 2 OF 2