DALMIA

CEMENT (B) LIMITED – CEMENT PLANT


BELGAVI
INSTRUMENTATION SMP
Issue No. 01 Rev. No: 00 Effective Date: 09.01.2016 SMP/INST/16
Issued By: Approved By: HOD
SMPFOR PULLCORD AND BELTSWAY

Scope/Purpose: This SMP is applicable for Pull cord and Beltsway Switches
Responsibility : Instrumentsection -Engineer
Accountability : Section In-Charge
PPE:
1. Safety Gloves
2. Safety shoes
3. Safety helmet
4. Safety goggles
5. Nose mask

Tools:

1. Multi meter
2. Spanner Set
3. Screw driver set

Hazard Analysis:

Risks associated Mitigating Measures

Entering dust into lungs and eyes Wear safety goggles and nose mask
Leg Injury Carefully walk on staircase with help of handrail

Training needs:

1. First aid procedures
2. Operating procedures
3. Safety talk should be held between workmen and in-charge

Procedure:

Ø Obtain necessary work permit and LOTO for the respective belt before carrying out
maintenance work
Ø Clean Pull cord/Belt sway switch and Intermediate JB from dust and foreign material.
Ø Open the cover and check tightness at terminal block of pull cord and Intermediate JB
Ø Isolate the power for pull cord/ belt sway and Keep multi meter in continuity mode and
Connect one probe at NC/NO another probe at COM point of the contact then operate the
pull cord/belt sway and check the operation

1/2
DALMIA CEMENT (B) LIMITED – CEMENT PLANT
BELGAVI
INSTRUMENTATION SMP
Issue No. 01 Rev. No: 00 Effective Date: 09.01.2016 SMP/INST/16
Issued By: Approved By: HOD
SMPFOR PULLCORD AND BELTSWAY

Ø Restore the supply to pull cord/ belt sway and operate the pull cord/belt sway and cross check
with CCR
Ø Check tightness of the gland if found loose tight with proper tools
Ø Check for gland hole opening if found open, cover the gland hole using plug or silver tape
Ø For Belt sway check handle tightness and condition
Ø Check rope connected with pull cord properly and tightness of the rope
Ø After completion of maintenance work clear the LOTO and check healthiness at CCR

Emergency / Emergency Shut OFF:


1. If any unconsciousness is there, give First aid and inform to the Safety
department or Call Emergency number 7760996046.

Records/Annexure:
1. Daily check list
2. SMP for operating procedure
3. Calibration Reports

JOB SAFETY ANALYSIS:(JSA)
Job Safety Analysis Job: Calibration of Date: 08 –10 - 2012 Analysis by: Reviewed by:
Rotor scale

Title of employee Supervisor: Department: Section: Approved by:


doing job: Instrument Section Engineer Instrumentation Instrument
Mechanic

Req’d/recommended PPE: Helmet, Safety shoes, Nose mask, Safety goggles



Sequence of Basic Recommended Safe What Could Go Corrective
Potential Hazards
Job Steps Job Procedure Wrong Action

Clean Pull cord/Belt


Dust entry into Use Safety goggles coughing due to Use proper safety
sway switch and
eyes & Lung and nose mask while heavy dust PPEs
Intermediate JB from cleaning
dust and foreign
material

2/2