Professional Documents
Culture Documents
Post Tension Slab System. Method of Installation, Stressing and Grouting
Post Tension Slab System. Method of Installation, Stressing and Grouting
YM Open
Pages
amazon.ae
Shop Now
Font size + 15
Download here
MATERIALS.
Strands:
We have several types of strand, but a common type is
Strand 12.7 mm/15.2 mm-Grade 270,1860 Mpa lower
relaxation.
Live Anchorage:
Live anchorages suitable for traditional internal post-
tension using tendons made up of high-strength steel
strands and should be as per NFA-35-045 or EN- 10138
standard.
Each anchorage device shall be capable of safely
transmitting a force not less that the ultimate strength of
the tendon without over stressing the concrete.
Wedges 13 mm / 15 mm.
Pocket Former.
Multi-Jack:
Stressing Pump:
Onion Jack:
Used in tendons less than (30) m to create an onion shape
at the end of these strand by spreading and separating the
wires.
Dispensers:
Device used for manual insertion of strands into cable
ducts.
Stapler:
Used for attaching duct chairs with Form-work when
concreting.
INSTALLATION.
Cutting & Preparation of the Strand:
Cutting list to be prepared from the shop drawing for each
tendon considering the stressing lengths are 300 mm for
single live end stressing and 600 mm for double live ends.
The area of cutting should away free pedestrians and
vehicles.
Display the Safety Sign Board that states Work in Progress.
Arrange the Dispenser, coil, electric connection, grinder, and
strip cutter.
Loading the strand to the strand dispenser.
Mark the lengths of the strands as per the cutting list, pull
and cut the strands to the correct marked length.
Make the dead end by using the onion jack for the tendons
that have single live end.
The size of the dead end to be 80 mm so that the concrete
can bond with the dead end.
Bundle the strands and tag it with the length, number of
strands and tendon number.
Every Coil is having a tag which states the coil No. the
below to be fill form which indicates which coil was
installed in which Tendon.
Slab installation:
Once the slab form-work is ready and has a safe access
and safe edges to work, the bottom mesh has been fixed;
the material should be lifted in the correct racks or boxes.
All item should be shifted by a crane which must be
supervised by the Rigger.
Mark the side shutter with the location of anchors and dead
ends.
Ready to download
فتح itvmob
Make sure the Pan Boxes have been fixed in the required
alignment and height.
Make sure the additional rebar is fixed around the pan box
as per the details.
Fill up the installation check list prior to handover the slab
installation undertaking.
CONCRETING:
The concreting operation for a post tensioned floor is very
similar to that for a reinforced floor, the contractor must be
aware of the following:
Ducts can be easily damaged during concreting; this would
cause problems in the stressing and grouting operations.
Anchorages and tendons must not get displaced during
concreting; Vibrations should not be allowed to contact the
tendons.
The concrete behind and around the anchorages is well
compacted.
STRESSING:
Stressing of the tendons is the central and most important
operations of the post tensioning process.
Prior starting the Stressing, the following needs to be
checked.