It is required to produce the given tail stock by sand casting process from cast iron
material (GG20).
Draw the casting drawing.
Draw the pattern drawing.
Draw the core only if it is required.
Draw the assembly of the flask to illustrate the gating system and the
location of riser if it is required.
State the suitable molding sand.
Calculate the gating system if S=2.3, W casting=18 Kg, and µ=0.6.
Pattern material:
- Assume Q < 500 Pieces Using wooden pattern (Split Pattern)
Pattern Allowances:
- Machining allowance
1) At Z1= 52 & S1= 90 ( up= 5 ) , ( down=3.5 ≈ 5 )
2) At Z2,3= 52 & S2,3= 90 ( up= 5 ) , ( down=3.5 )
3) At Z4,5 (The slot width < 20 mm so it will be machined after casting)
4) At Z6= 25 & S6= 240 ( up= 5 ) , ( down=3.5 )
5) At Z7= 50 & S7= 60 ( up= 4.5 ) , ( down=3 ≈ 4.5 )
- Shrinkage allowance
For GG20 Pearlite C.I (Disabled shrinkage allowance = 0.9)
- Draft allowance
1) At H1=45 α =1° 30ʹ a = 1 mm
2) At H2,3=50 α =1° 30ʹ a = 1 mm
3) At H1=35 α =1° 30ʹ a = 1 mm
𝜋
(Vfl) 1, 3= 4 ∗ 152 ∗ (30 + 10) + 70 ∗ 30 ∗ (30 + 10) = 91.1 𝑐𝑚3
100 s 100 6
(VR) 1, 3= (Vfl)1,3 ∗ ∗ 100 = 91.1 ∗ ∗ 100 = 54.66 𝑐𝑚3
c 10
2 𝜋 3 𝜋
(VR) 1, 3= 54.66 = 4 D1,3 ∗ 𝑙 = 2 D1,3 l = 2D
3 2∗54.66
D 1, 3= √ =3.3 cm=33 mm
𝜋 D D1 D2 V B r
From table (2-20) At D 1, 3=35 35 45 65 175 25 6
𝜋 𝜋
(VR) 1, 3 Standard = 4 D12 ∗ 𝑣 = 4 ∗ 4.52 ∗ 17.5=278.3 𝑐𝑚3
𝜋
(Vfl) 2= 4 (902 − 412 )(62 + 5) = 337.8 𝑐𝑚3
100 s 100 6
(VR) 2= (Vfl)1,3 ∗ ∗ 100 = 91.1 ∗ ∗ 100 = 54.66 𝑐𝑚3
c 10
𝜋 𝜋
(VR) 2= 202.68 = 4 D22 ∗ 𝑙 = 2 D32 l = 2D
3 2∗202.68
D 2= √ =5 cm=50 mm D D1 D2 V B r
𝜋
From table (2-20) At D 2=50 50 60 80 175 25 6
𝜋 𝜋
(VR) 2 Standard = 4 D12 ∗ 𝑣 = 4 ∗ 62 ∗ 17.5=494.8 𝑐𝑚3
Pouring Cup
4 𝐺𝑔𝑟𝑜𝑠𝑠 5 4 35.84 5
- v = 400 √( ) = 400 √( ) = 1295.3 𝑐𝑚3
𝜏 14
From table (2-16)
v L b h r1 r2 r3
1300 180 110 100 55 44 33