2005 Construction Progress Report
2005 Construction Progress Report
Program Initiated
December 2005
$ 300,165,000
December 2005
General Issues
1998 Deferred Items Enrollment Growth Aging of Existing Facilities Continued Technology Needs
December 2005
Length of Program
December 2005
Program Duration
Bond Sales 2004 through 2009 Construction through 2011 Phase I & II In Progress Phase III In Planning Currently On Track
December 2005
December 2005
IH
35
Carrollton
NSHS
Dallas
Denton Dr
Whitlock
Keller Springs
Pre-k SFC
Coppell
Luna Rd
Josey Ln
Belt Line Rd
lle Va
iew yV
rw LBJ F
December 2005
Nort hwe s
t Hw
Marsh Ln
Stark
Midway Rd
Irving
Farmers Branch
Addison
Midway Rd
y Hw 11 4
December 2005
Actual
Budget
December 2005
10
NSHS Renovation
December 2005
11
NSHS Renovation
December 2005
12
Actual Budget
December 2005
13
December 2005
14
Actual Budget
December 2005
15
December 2005
16
December 2005
17
IH
35
Carrollton
Blanton
Dallas
Pre-k
Whitlock
Keller Springs
Coppell
Standridge
RLT
Luna Rd
Josey Ln
Belt Line Rd
lle Va
iew yV
rw LBJ F
December 2005
Nort hwe s
t Hw
Marsh Ln
Midway Rd
Irving
Farmers Branch
Addison
Midway Rd
y Hw 11 4
18
Technology - $7.0 M
Continue improvements
December 2005
19
December 2005
20
Furneaux
Sheffield Pri.
Creekview
McWhorter
IH
35
Carrollton
Denton Dr
Dallas
Whitlock
Coppell
Josey Ln
Belt Line Rd
Elementary/Pre-K
Luna Rd
LaVillita
lle Va
iew yV
LaVillita
rw LBJ F
December 2005
Nort hwe s
t Hw
Marsh Ln
Midway Rd
Irving
Farmers Branch
Addison
Midway Rd
y Hw 11 4
21
Projection
0.3500 0.3000 0.2500 Actual
1998
1999
2000
2001
2002
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2007 Estimate based on $45 million bond sale with 1.5% growth in values
December 2005 22
CFB
Allen
Carroll
Coppell
Irving
Lew isville
Mesquite
McKinney
Plano
Richardson
Assuming approximately $45 million bond sale in 2006 With 1.5% value growth
December 2005 23
Other Issues
December 2005
24
Davis Elementary
Current Enrollment 645 7 Temporary Classrooms Enrollment Appears Stable Adjacent schools have capacity
December 2005
25
Davis Elementary
Review special programs Monitor growth If growth continues, consider boundary adjustment
December 2005
26
McLaughlin Elementary
Current Enrollment 681 7 Temporary Classrooms Adjacent schools have capacity
December 2005
27
McLaughlin Elementary
Consider boundary adjustment with Montgomery/Blair
December 2005
28
Consider to Rezone: Area between Josey Lane & Nix and Between Beltline & Fyke Road
December 2005
29
$ 5.1 Million $ 7.7 Million $27.6 Million $ 9.6 Million $ 9.9 Million $ 6.5 Million $ 9.5 Million $ 8.7 Million $ 9.8 Million $ 3.7 Million $ 4.0 Million $ 4.5 Million $ 3.3 Million $17.0 Million
31
QUESTIONS ?