JSA Fiber Tank Lifting
JSA Fiber Tank Lifting
Part 3: Equipments / Tools to be used: Heavy Vehicles, Crane, Rigging accessories & Hand Tools
Part 4: Contingency Plans. Standard PPE’s: First aid kit must be present at work site and the HSE personnel will be the first response in case of
emergency, ERPs & Emergency contact numbers to be in placed at job location
Part 5:JSA Review Process. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? In
case of any new hazard indentified by any of the working team member during the job, JSA review process should be carried on.
JSA No: JOB TITLE: Lifting & unloading of fibre Tank & vehicle/equipment movement
Step Describe Job Step Potential Hazards Hazard Controls
No
1 Mobilization of equipment/vehicle Crane/vehicle hit with Ensure banks man to monitor movement
people/equipment & materials of heavy vehicles/crane
Involvement of unskilled personnel Ensure JSA briefing & TBT
Movement of crane/vehicle without Take care of overhead structures/pipe
presence of banks man racks
Breaking of culvert due to movement of Use of appropriate PPE’s
heavy vehicles Ensure placement of steel plates on culvert
Vehicles/equipments hit with overhead to avoid its damaging
structure/pipe racks Hard barricade structures (as required)
Unauthorised/ uninspected Only Third party inspected
equipment/tools at site Equipment’s/Tools must be allowed at
work site
Use right tools for right job
Personnel injury / property damage All of materials to be secured while its
transportation to work site
Close safety supervision
JSA No: JOB TITLE: Lifting & unloading of fibre Tank & vehicle/equipment movement
Step Describe Job Step Potential Hazards Hazard Controls
No
2 Lifting & unloading of steel plates Uncertified Crane & Operator, Crane & its operator should be certified
Personnel/structures hit by movement Banks man/signal man should be available
of crane Place crane at levelled & compacted
Unbalancing of out riggers ground surface
Unauthorized personnel involvement Ensure wooden/rubber packing to avoid
Sharp edges of steel plates damaging of web belts/slings
Careful handling with steel plates, use of
appropriate PPE’s
Keep away all unauthorized people during
movement of heavy vehicle/equipments
Ensure Close HSE monitoring
/supervision
Be careful of nearby structures/pipe racks
Third Party Certified Sling broken, load Ensure proper & inspected accessories
drop being used for lifting operation
Miscommunication/signal error Ensure that load is properly placed &
lifted
Ensure proper communication between
rigger/signal man & operator
Keep away during crane operation
Swing area should properly barricaded
Slip, Trip & fall Ensure proper stacking of all materials
Keep access/walk ways always clear from
any obstruction
Ensure proper housekeeping of workplace
JSA No: JOB TITLE: Lifting & unloading of fibre Tank & vehicle/equipment movement
Step Describe Job Step Potential Hazards Hazard Controls
No
Inclement weather condition Stop crane work in case of any inclement
weather conditions (Rain, storm, fog etc.)
Restrict movement of heavy
vehicles/equipments in rain/fog
Fire & explosion Ensure availability of inspected fire
extinguishers at site
Flame arrestor to be installed in all
vehicles/equipments
4 Demobilization Same as item one Same as item one