Petroleum Development Oman LLC Effective: Dec 22

A2.1 TTP / TTP with DP: Feasibility & Concept Checks/ Approvals (1 of 2)
Item Description Responsible for execution
(PDO action party to initial and collate evidence)

PDO Construction Isolation


Contractor Vendor

2.1 Feasibility & Concept Design Signature Tick if info Tick if info
provided provided
2.1.1 Justification established CE

2.1.1.1 Ensure isolation questionnaires are PLE


complete, accurate and signed off for both
Tecno-plug and door Plug
2.1.2 Run Pipe Data Obtained

2.1.2.1 Process Operating Conditions Established. CE

2.1.2.2 Check Material specification/grade PLE


compatibility as per MSR for Tecno-plug set
location and trap barrel
2.1.3 Inspection

2.1.3.1 Check run pipe for laminations at set CSR Constr.


location. Also launcher barrel Mgr.
2.1.3.2 Establish actual wall thickness at set CSR Constr.
locations and door plug location Mgr.

2.1.3.3 Confirm pipe material suitability for plug PLE


and door plug
2.1.3.4 Confirm suitability of launcher / receiver for PLE
launching and receiving the plug
2.1.3.5 Confirm type of Pipeline Tee’s and PLE
suitability of pigging the plug
2.1.3.7 Confirm a secondary / contingency SET PLE
location
2.1.3.8 Confirm suitability of valves (passing or PLE
holding) to be used for loading and pigging
purposes (clause 2.2.16)
2.1.4 Calculations
2.1.4.1 Stress summary calculation to be carried PLE
out for plug set location and door plug
location
2.1.4.2 Deployment Assessment of the plug based PLE
on data received
2.1.4.3 Confirm chemical stability of PLE
product in the line with plug components

2.1.4.4 Heat Transfer Calculation to be carried out in PLE


event of welding behind plug during isolation
2.1.4.5 Flow Calculations carried out PLE

2.1.4.6 Tether disconnect location and operation PLE


identified and defined
2.1.4.7 Pigging / stem bar deployment engineered. PLE

2.1.4.8 Isolation feasibility report (including design & PLE


MS of external clamp installation if
applicable)

Printed 01/01/23 SP-2314 Pipeline isolation plug management specification Page 28

Printed copies are UNCONTROLLED.


Revision: 2.0
Petroleum Development Oman LLC Effective: Dec 22

A2.1 TTP / TTP with DP: Feasibility & Concept Checks / Approvals (2 of 2)

Item Description Responsible for execution


(PDO action party to initial and collate evidence)

PDO Construction Isolation


Contractor Contractor

2.1.5 Drawings
2.1.5.1 Ensure deployment plan prepared PLE

2.1.5.2 Ensure loading / retrieval frame details PLE


prepared
2.1.5.3 Ensure plug GA and Door plug GA PLE
details prepared
2.1.5.4 Ensure Operational Layout details PLE
prepared
2.1.5.5 Ensure Valve Tag details have been PLE
prepared
2.1.6 Variances
2.1.6.1 Variances (if any) are approved by PE
respective TAs

Above checks verified:

…………………………………. ……………………………
Project Engineer Pipeline DA1

………………………………….
Pipeline Engineer (TA2 Pipelines):

…………………………….
Asset Delivery Team Lead (Name and Reference Indicator)

Printed 01/01/23 SP-2314 Pipeline isolation plug management specification Page 29