RATE ANALYSIS

Pilling
2' Dia, 55' Deep Pile Boring, Steel & Concreting.

Unit = Rft Quantity 100

Particulars Unit Quantity Rate (Rs.)

A. MATERIALS/ Activities

1 Boring For Pile Rft 100.000 400.00 40,000.00

3 Concrete (Ready Mix from Plant) Cft 100.00 175.00 17,500.00

Total 57,500.00

Add 5% wastage 2,875.00


% 57,500.00 5%
Sub Total ( A ) 60,375.00

B LABOUR

Concrete Poring Cft 100.00 10.00 1,000.00

Sub Total ( B ) 1,000.00

C TOOL & PLANT

5% of (A+B) % 61,375.00 5% 3,068.75

Sub Total ( C) 3,068.75

Total (A + B + C) 64,443.75

Prime Cost / Rate per Rft 644.44

D Profit, Overheads & I/Tax

Add 28% againstprofit, overheads & I/Tax % 64,443.75 25% 16,110.94

Sub Total ( D) 16,110.94

Total (A + B + C+D) 80,554.69


Cost / Rate per Rft 805.55