Progress:
Manpower
653 WBS Planned Actual
Engineering 90.63% 97.78%
Procurement 65.47% 75.81%
PMT 39,150
Construction 41.10% 54.06%
MHs GES+ 31,340
Cont. 1,396,834 Procurement:
LTI 0 o Approved 25 NMR-601 and 24 NMR-602 out of 25.
RDI 0 o Received 3 differential pressure gages.
o Received 3 Local Control Panels for Lighting Panel Boards.
MTC 0
FAI 0 No. Description Unit QTY Total # PO POs Placed QTYs Delivered ETA
1 Pipes M 900 4 4 900 Delivered
NM 25
2 Pipe fittings Each 383 11 11 383 Delivered
COVID-19 0 3 Valves Each 165 9 9 165 Delivered
4 E&I Cables M 88,000 5 5 87,000 Sep 30th,2022
Electrical (CP, glands,
5 Each 9,117 15 15 8,636 Sep 30th, 2022
etc.)
6 Instruments Each 95 15 15 59 Nov 15th, 2022
7 Structure Steel Ton 13.7 8 8 13.7 Delivered
8 Tanks Ton 1000 4 4 995 Oct 15th, 2022
9 FW equipment Each 10 3 3 6 Oct 15th, 2022
Demolition:
Restoration
Challenges:
o Tank 109 remains with product preventing restoration team from completing internal tank assessment.
o Tank 102 remains with product preventing restoration team from executing the conversion of tank to Diesel/Jet.